New Talisman Gold Mines Ltd logo

Quarterly Report

Quarterly Update31 January 2018NTLIndustrials

Market Announcement
ASX: NTL, NZX: NTL

For Immediate Release

HIGHLIGHTS

 Rehabilitation reaches 600m underground;

 Sampling of broken ore stockpiles underground yields

positive results;

 Metallurgical testwork for concentrator plant underway;

 Ore extraction commences;

 Ventilation and Power infrastructure near completion.


During the period under review works progressed at the Talisman mine site with

the commencement of major infrastructure installation. Works on both power and

ventilation are nearing completion and gold bearing material continues to be

stockpiled.

Timing of the first blast at Mystery is currently being determined by the technical

team which is likely to commence upon completion of final remedial works at

Mystery.

The company continued to evaluate several opportunities for Toll treatment and

concentrate sales both in NZ and elsewhere.


Quarterly Activities Report to 31 December 2017

31 January 2018

Commodity Exposure


GOLD and SILVER


Board and Management


Charbel Nader

Chairman/Independent Director


Matthew Hill

Chief Executive/Managing Director


Murray McKee

Independent Director


Murray Stevens

Non executive Director


Tony Haworth

Independent Director


Jane Bell

Company Secretary


Wayne Chowles

Chief Operating Officer


Ash Clarke

Chief Financial Officer



Capital Structure


Ordinary Shares on issue -

2,164,503,303


Listed Options

17,036,384 listed options expiry

30/09/2022



www.newtalisman.co.nz

Phone - +64 27 5557737

Email – matt@newtalisman.co.nz

541 Parnell Road, Parnell


Mine Refurbishment

Excellent progress has been made by the underground team and remedial works have now

progressed more than 600m into the mine at the location of the second bypass. This is some

30m from Keillors Crosscut and is the final step

to make the No 8 level drive fully trafficable all

the way to the Mystery Workings. The project

has not been without its challenges, but these

have been met within budget and only a minor

impact on timing. The company remains in a

position to commence works on the Bulk

sampling project early in 2018

Geotechnical assessment of those areas which

will possibly provide access to 9 level and below

is currently underway. Access to these levels

will allow the team to undertake sampling

activities in the highly prospective areas of the

high-grade Dubbo Zone directly below the area

delineated by the 2004 exploration

programme. The intersection of the Maria vein

here in 1989 borehole BM37 drilled from 8

Level, assayed at 656g/t gold over 1.8m which

included 1154g/t over 1.0m. This with channel

sampling and drilling by NTL confirmed the

presence of a high-grade shoot that has been further supported by modelling work of historic

grade data in the recent mineral resource upgrade.

NTL announced on 05 December 2017 that

extraction and stockpiling of ore has commenced at

the Talisman mine site. The ore is currently being

stockpiled while treatment options are being

reviewed.

Prospecting

Prospecting activities continue with several sources

of broken ore having been identified. Results of

sampling carried out to date have been largely

positive and a more detailed update will be released

once all results are available and have been

assessed.

Prospecting activities are also underway at Taukani

Hill where previously, 21 rock chip grab samples of

Figure 1 - Underground loader operating in the

first bypass area

Figure 2 - Shotcreting to seal a historic

orepass


quartz vein outcrop yielded highly encouraging gold assay results ranging between <0.02g/t

and 345g/t. These results were announced to the market by Heritage Gold Ltd on 29 July,

2011. The Company wishes to increase its knowledge of this highly prospective area along

with other targets in the mining permit and develop a more detailed exploration programme

for inclusion into the broader mine development schedule.

Prefeasibility Study

In 2013 the company completed a Pre-Feasibility Study on development of the Talisman Mine.

This study proposed a mine plan,

focussed on the high confidence

areas adjacent to No 8 level, to

produce some 32,000 ounces of

gold from 106,000 tonnes of ore

over a five-year period with an

average Run of Mine grade of

9.9g/t Au. At a then gold price of

USD 1,700/Oz and a USD: NZD

exchange rate of 1:0.8 the project

yielded an indicative NPV10% of

NZD 16.5 million at an on mine

cash cost of below NZD700/Oz

Learnings from the design of the

Bulk Sampling Project as well as

the revised mineral resource estimate are being incorporated into this study. The recent

increased grades are expected to have a significant positive effect on production costs as more

gold will be produced for the same effort. Costs are based on tonnage not gold content i.e.

one tonne of low grade ore attracts the same cost profile as a tonne of high grade ore, but

the revenue profile varies along with the contained metal.

Scoping Study

Good progress has been made on the Talisman Deeps scoping study. This study is the first step

in the development of the much larger Talisman Deeps operation based on the significantly

expanded 469,000 AuEq Oz Mineral resource details of which can be found in company

releases of 12 July 2017, 25 July 2017 and 05 September 2017.

A pre-feasibility study, (PFS) is a technical study as defined in the JORC Code and can be used

for the purposes of defining an Ore Reserve. Because of this a PFS is confined to examining

only the higher confidence Measured and Indicated Resources and cannot take account of the

extensive information available pertaining to the deeper extents of the mine where the

Mineral Resources are classified in the Inferred Resource category. While indicative of the

short to medium term potential of the project this is not reflective of the considerable value

increase posed by the depth extensions of the vein system. Mine design and production

Figure 3 - View from the portal during installation of the air lock

structure


scheduling covering the much larger, 469,000 Oz AuEq mineral resource, is likely to point

towards a significantly larger, longer life operation than has previously been considered. It is

equally likely that, considering the increased grade of the recently upgraded mineral resource

(6.6g/t AuEq vs 15.1 g/t AuEq), that economic prospects for the project will increase

significantly.

A Scoping Study, as referred to above, is based on low-level technical and economic

assessments, and is insufficient to support estimation of Ore Reserves or to provide assurance

of an economic development case at this stage, or to provide certainty that the conclusions

of the Scoping Study will be realised.

The Scoping Study will also identify opportunities for the exploration activities to be

undertaken to gain the information required to increase confidence in portions of the Maria

Vein outside the recent resource model upgrade. Current information from the

Talisman/Bonanza Zone has identified a target area of some 154,000m

2

on the plane of the

Maria vein wireframe beyond the current resource that is likely to yield a vein width of

between 1.6m and 2.4m with mean AuEq grade ranging between 17.10g/t and 21.6g/t.

This target constitutes an Exploration Target as defined in the 2012 JORC Code. The potential

quantity and grade is conceptual in nature and there has been insufficient exploration to

estimate a Mineral Resource. It is uncertain if further exploration will result in the estimation

of a Mineral Resource.

Concentrator Plant

Metallurgical testwork on representative samples of ore from both the Mystery and Dubbo

veins is currently underway in South Africa. This test-work will inform the final design of the

plant to ensure that metal recovery is fit for purpose before deciding on proceeding with a

pilot plant. Such a plant will provide the opportunity to produce a saleable high-grade

concentrate while still meeting the requirements of traffic movement flows from the mine

specified in the existing resource consent.

The plant will include a crushing and grinding circuit followed by a gravity concentrator which

may be supplemented by a froth flotation cell. A closed loop water system is proposed

ensuring that no contamination of natural water ways will take place. All metals contained in

the feed stock will be recovered to the concentrate while reject material will be completely

inert and suitable for placement as backfill.

Upon completion of this metallurgical programme NTL will have a greater understanding of

precious metal recoveries achievable as well as the costs involved in installing and operating

such a plant.

Tenure

The Talisman Mine is held under a mining permit, MMP51326, which was granted in 2009 for

a period of 25 years, we are compliant with the conditions of that permit. The operation is an


existing mine on conservation land and the Company holds all the necessary permits and

consents to execute the work programme.


Rahu Project (wholly owned subsidiary 100% Rahu Resources Pty Ltd)

In 2016 NTL entered into a joint venture with Newcrest New Zealand Exploration Pty Ltd, a

subsidiary of Newcrest Mining Limited, to further explore and develop the Rahu project.

Initially, Newcrest held 80% of the project with the remaining 20% held by NTL. On 22

September 2017, NTL entered into a sale and purchase agreement with Newcrest which

resulted in the successful acquisition of Newcrest’s 80% share.

During the time of their involvement with the project the Newcrest team carried out a

significant programme of work on the permit, this included:

 Extensive field investigations.

 Spectral analysis of drill core to identify hydrothermal clay alteration patterns that

indicate proximity to gold mineralisation.

 Relogged drill core and reinterpreted the rock type, structure and geochemistry;

 Updated the geological model and determined drill targets.

All data gathered during the period was transferred to NTL who have continued with further

analysis.

The figure below shows the results of a CSAMT geophysical survey that shows the top of the

host andesite host rock is nearest surface at the southern end of prospect.



Based on Newcrest’s and NTL’s interpretive work, the area selected for the first drill hole has

distinctive clay hydrothermal alteration patterns plus the mineral adularia, indicative of

proximity to gold mineralisation in Waihi Gold District epithermal vein systems.

NTL has previously delineated a small resource at Rahu, however the main target for a high-

grade extension of Talisman lies at depth.

Newcrest were supportive of NTL’s belief that geological evidence points towards to the area

being the upper extent of what could be a significant epithermal gold deposit.

Your company is completing its geological work to validate the deep target and finalising its

drill hole planning and administrative work for drilling in the first quarter of the 2018.

This deep target constitutes an Exploration Target as defined in the 2012 JORC Code. The

potential quantity and grade is conceptual in nature and there has been insufficient

exploration to estimate a Mineral Resource. It is uncertain if further exploration will result in

the estimation of a Mineral Resource.


Tenement Holdings

Project Permit Number Ownership

Talisman MMP 51326 100% New Talisman Gold Mines

Ltd

Rahu MEP 60144 100% Rahu Resources Pty Ltd a

100% owned subsidiary of NTL





_______________________________________________________________________

About New Talisman Gold Mines Ltd

New Talisman Gold is a dual listed (NZSX & ASX: NTL) with over 2250 shareholders who are mainly from

Australia and New Zealand and has been listed since 1986. It is a leading New Zealand minerals

development and exploration company with a mining permit encompassing the Talisman mine, one of

New Zealand’s historically most productive gold mines. The company has commenced prospecting and

upgrading activities at the mine, and advance the exploration project and increase its considerable

global exploration target into JORC 2012 resources.

Its gold properties near Paeroa in the Hauraki District of New Zealand are a granted mining permit,

including New Zealand’s highest-grade underground gold mine, a JORC 2012 compliant mineral

resource of over 427,000 ounces Au_Eq at an average above 15 gt Au_Eq and a JORC compliant reserve

statement. The company owns 100% exploration permit Rahu, which lies along strike from the Talisman

mine of which 80% was recently acquired from Newcrest Mining. The company will shortly commence

exploration activities at Rahu.


Statement of Compliance

The information in this report which refers to estimates of Mineral Resources is extracted from the

original market announcements of 12 July 2017, 25 July 2017 and 05 September 2017. The company

confirms that it is not aware of any new information or data that materially affects the information

included in the original market announcements and that all material assumptions and technical

parameters underpinning the estimates continue to apply and have not materially changed. The

company confirms that the form and context in which the competent persons findings are presented

have not been materially modified from the original market announcement.

Information in this report which refers to estimates of Ore Reserves is extracted from the original report

titled “Ore Reserves Definition – Talisman Gold Project” which was released to the market on 07 August

2013 and is available on the company website. The company confirms that it is not aware of any new

information or data that materially affects the information included in the original market

announcements and that all material assumptions and technical parameters underpinning the

estimates continue to apply and have not materially changed. The company confirms that the form and

context in which the competent persons findings are presented have not been materially modified from

the original market announcement.

The information in this report which refers to exploration results at Taukani Hill is extracted from the

original market announcement by Heritage Gold Ltd on 29, July 2011 and is available on the NZX

website (https://www.nzx.com/announcements/211837). The company confirms that it is not aware

of any new information or data that materially affects the information included in the original market

announcements and that all material assumptions and technical parameters underpinning the

estimates continue to apply and have not materially changed. The company confirms that the form and

context in which the competent persons findings are presented have not been materially modified from

the original market announcement.

Cautionary Statement for Public Release

Certain information contained in this public release may be deemed “forward-looking” within the

meaning of applicable securities laws. Forward-looking statements and information relate to future

performance and reflect the Company’s expectations regarding execution of business strategy,

business prospects and opportunities of New Talisman Gold Mines and its related subsidiaries. Any

statements that express or involve discussions with respect to predictions, expectations, beliefs, plans,

projections, objectives, assumptions or future events or performance are not statements of historical

fact and may be forward-looking statements. Forward-looking statements are subject to a variety of

risks and uncertainties which could cause actual events or results to differ materially from those

expressed in the forward-looking statements and information. They include, among others, the

accuracy of mineral reserve and resource estimates and related assumptions and inherent operating

risks. There are no assurances the Company can fulfil forward-looking statements and information.

Such forward-looking statements and information are only predictions based on current information

available to management as of the date that such predictions are made; actual events or results may

differ materially as a result of risks facing the Company, some of which are beyond the Company's

control. Although the Company believes that any forward-looking statements and information

contained in this press release is based on reasonable assumptions, readers cannot be assured that

actual outcomes or results will be consistent with such statements. Accordingly, readers should not

place undue reliance on forward-looking statements and information. The Company expressly disclaims

any intention or obligation to update or revise any forward-looking statements and information,

whether as a result of new information, events or otherwise, except as required by applicable securities

laws. The information contained in this release is not investment or financial product advice.

Data sourced from publicly available filings. Our datasets may not be complete. Automated analysis can produce errors. If you believe any data on this page is incorrect, please contact us at hello@nzxplorer.co.nz. For informational purposes only. Not investment advice.