The overall shutdown is progressing well with the total refinery shut phase completed to plan. Of the five

distinct work fronts four are on plan

1

. Some emergent maintenance work has been identified over the

weekend in the hydrocracker work front. This means that the 39 day shut phase of the hydrocracker unit

will be extended to around 48 days in total.

The impact of the emergent work is a reduction in NPAT of around $5-$7 million and in throughput of

around 500,000 barrels.


Further information:

Greg McNeill

Communications and External Affairs Manager

T: 094325115; M: 021 873623; E: greg.mcneill@refiningnz.com




1

For a description of the shutdown work fronts see page 12 of the FY 2017 analyst pack.