New Talisman Gold Mines Ltd logo

Quarterly Activities Report 30 Sept 2018

Quarterly Update31 October 2018NTLIndustrials

1

New Talisman Gold Mines

Limited


Responsible,

Environmentally

Sustainable Mining


ASX/NZX Code NTL

____________________


Commodity Exposure

GOLD and SILVER


Board and Management


Charbel Nader Chairman/Independent Director

Matthew Hill Chief Executive/ Managing Director

Murray Stevens Non-Executive Director

Tony Haworth Independent Director

Jane Bell Company Secretary

Wayne Chowles Chief Operating Officer




Capital Structure

Ordinary Shares at 30/10/2018

2,164m


Share Price

Share Price at 30/10/2018 (NZX) 1.6cps

Share Price at 30/10/2018 (ASX) 1.4cps




New Talisman Gold Mines Limited

ACN

Address 541 Parnell Rd, Parnell,

Auckland

Phone +64 27 5557737

Website www.newtalisman.co.nz


Email info@newtalisman.co.nz


Market Announcement

For Immediate Release

HIGHLIGHTS

• Underground Mining related activities at Talisman

resume for the first time since 1992;

• Mystery vein: - blasting, excavation and stockpiling of

high-grade ore commenced;

• Extraction and stockpiling of ore from stopes and old

workings continues with 40 tonnes extracted in the last

two weeks.;

• Traffic management plan approved by HDC;

• Independent review of Resource estimate complete;

• Pilot plant installation commenced; and

• Applications for Rahu field work lodged.


Following on from the previous successful quarter, a significant number of key

milestones were achieved which resulted in the commencement of the mining

activities at the Talisman Mine.

This quarter marked a milestone for the project as it is the month that the

Talisman became a mine again in the full sense of the word. It was noted

previously that the primary fan had been delivered to site and the 250kva

generator had been delivered to Waihi, these have now been installed and

commissioned. With these in place the company undertook the first blasts in the

Talisman mine with the initial blast taken on the Mystery Vein.

True to the company’s commitment to environmentally sustainable mining,

sound emissions from the heavily silenced fan are virtually imperceptible beyond

the immediate mine site.

Matthew Hill said “as New Zealand’s oldest incorporated and listed gold mining

company, we are pleased to have finally commenced underground mining

activities under our resource consent and reopened one of New Zealand’s most

productive mines which is coming up to its 125

th

anniversary of operations. With

the granting of the TMP we are now able to blast and transport the ore offsite for

stockpiling and ultimately processing.”

Quarterly Activities Report to 30 September 2018


2


TALISMAN MINE PROJECT

The key milestones achieved at the Talisman mine during the quarter include: -

• The Traffic Management Plan (“TMP”) was approved by HDC and the company has commenced

activities under the resource consent granted by Hauraki District Council (“HDC”) in 2013. The

TMP allows transporting of ore from the mine offsite with one blast event per day which will

continue for 2+ years as the definitive feasibility study is completed.

• Commissioning of silenced 250KVA generator and control room is complete and the operation

now has reliable power supply to the main ventilation fan and other site equipment.


• Installation and commissioning of the primary ventilation fan is complete. This fan, mounted

above the airlock and connected to the mine via a reinforced concrete tunnel, is fitted with world

leading silencing equipment to reduce noise emissions to conversational level. The fan is capable

of delivering sufficient air to maintain a healthy respirable atmosphere underground while up to

three diesel powered loaders are deployed in the workings, which has significantly increased the

productivity of the mining team.



• Following the final metres of rehabilitation into the Mystery zone the company was able to

commence the maiden blast at Mystery. Approximately 8 tonnes of vein material has been

extracted which has provided promising results. A resue mining method – blasting the vein

material and surrounding waste in separate stages - is being tested with encouraging results from

the first blast. This system will enable the vein material to be trammed separately from waste

material which will maximise the grade of ore delivered to the plant and reduce transport costs.


3

The blasts which have been undertaken to date have provided no measurable vibration or noise

at surface.


Samples taken from ore generated by the first blast were independently analysed for gold and

silver content at the SGS laboratory in Waihi and yielded an average grade of 7.1g/t Au as

announced on 20/09/2018.

(Please see https://www.asx.com.au/asxpdf/20180920/pdf/43yhcd15zcxsp5.pdf

)

These results are in line with expectations and consistent with the range of grades in this section

of the Mystery Vein. This is in the same area where recent check sampling of ore exposed at the

drive face yielded grades of up to 40 g/t Au as announced to the market on 31 March 2018 (please

see https://www.asx.com.au/asxpdf/20180508/pdf/43tvlpmv420f4f.pdf

) While considerably

more work is required to understand the full extent of this highly prospective vein system these

results are encouraging and represent a very positive first step in this process.

• Work has commenced on clearing ore from a historical stope on the Maria vein in the Talisman

zone. Over 40 Tonnes of ore has been extracted from this area over the last two weeks alone and

has been stockpiled ready for transport offsite to the pilot plant facility once commissioned. This

ore has been extensively sampled during loading and we await the results. The amount of ore

present in this area is uncertain and further extraction and stockpiling of the ore is dependent on

samples taken over the last week. Once removal of rock from this area is complete vehicle passage

further into the mine will be possible and will allow accelerated development on the Mystery vein.


4


• Preparation for installation of the underground power cable and auxiliary fan is underway. This

fan is on site and will be transported to position at the Keillors Crosscut junction to pump air into

the Dubbo Drive. Upon completion there will be accessibility for vehicles from the Portal all the

way through to Dubbo.


5

• Rehabilitation of old workings through to the start of the BM37 zone at Dubbo was completed

during the quarter and, once vehicle access is attained, loading of rock from the base of the BM37

rise can begin. Clearing of this rock will provide access to the high-grade Dubbo Zone of the Maria

Vein. This is the site of the last mining by previous owners in the late 1980’s and was identified by

borehole BM37 which assayed 656 g/t Au over 1.8m including 1154 g/t Au over 1.0m. Sampling

in this area has previously yielded results exceeding 1% gold (over 10,000g/t), please see

https://www.asx.com.au/asxpdf/20130705/pdf/42gx44jq96lzrs.pdf


• Maintenance of the mine road was completed in September and has significantly improved the

drainage capability and trafficability of the road.

• The shaker table and concentrator that form part of the pilot processing plant, have arrived and

are currently being installed offsite. Both the shaker table and gravity concentrator is in the

process of being commissioned and will be tested with a batch of ore which has been crushed to

the free gold size while we await the arrival of crusher and grinder. A number of offsite locations

close to the mine have been identified which are suitable for the plant. It is expected the plant will

be fully installed and operational with the crushing and grinding circuit by end of November with

first production of gold from stockpiled ore by year end.

While the capacity of the pilot plant is relatively low the aim is to replicate the recovery rates

which were achieved using a similar flowsheet in the testwork carried out in South Africa in

February 2018 (please see https://www.asx.com.au/asxpdf/20180322/pdf/43sn63s00fjnz6.pdf

) .

Once recovery rates are confirmed it is likely that a larger plant, suitable for the longer-term needs

will be acquired, dependent on other options.

• A detailed Independent review of the Mineral resources estimate was completed during the

quarter which confirmed the 2012 JORC compliant resource of 469K oz AuEq at an average grade

of 15.1g/t. This makes the Talisman Mine the highest grade underground active mine in NZ for

which grades and resources have doubled in just over a year. The report concluded:

In reviewing NTGM’s MREs Geos Mining has found that the estimations, the data and the resource models

they are based on, meet the guidelines set out in the 2004 and 2012 JORC Codes and have no serious errors

or issues associated with them.

Further work is being carried out on the remaining data for the fourth module relating to Talisman

deeps which will be included in the growing database as works are carried out. With significant

development into Mystery and Dubbo, the substantial amount of data and knowledge of the

orebody acquired from these activities will support a review of the Mineral Resources Estimate

and upgrade of remaining areas to JORC 2012 standards by the end of Q1 2019.

• With mining operations having commenced under the company’s existing resource consent, the

company has initiated a planning assessment of resource consent requirements to support the

longer-term future of the mine in line with the prefeasibility study recently released.

• Applications for access and consent to initiate fieldwork at the Rahu Project have been lodged

with the relevant authorities


Corporate

During the quarter the company continued discussions with a number of parties that have approached

the company for treatment and offtake of the high-grade ore as well as parties interested in acquiring

the concentrate product produced from the plant. With blasting and extraction having commenced

and the pilot plant being installed tuned and subsequently being commissioned, once the recovery

rates are confirmed the company will be better positioned to take these discussions to a commercial

conclusion. It is expected by the end of Q1 2019 we will have sufficient data from the pilot plant to


6

determine the maximum volumes of concentrate and bullion produced which can be produced

directly from the pilot plant and the recovery rates achieved.


About New Talisman Gold Mines Ltd

New Talisman Gold is a dual listed (NZSX & ASX: NTL) with over 2250 shareholders who are mainly from Australia

and New Zealand and has been listed since 1986. It is a leading New Zealand minerals development and

exploration company with a mining permit encompassing the Talisman mine, one of New Zealand’s historically

most productive gold mines. The company has recently reopened the Talisman mine and commenced blasting

and extraction under the resource consent granted. The company continues to progress its prospecting and

upgrading activities at the mine to further advance the mining project to increase its considerable global

exploration target into JORC 2012 resources.


Its gold properties near Paeroa in the Hauraki District of New Zealand are a granted mining permit, including

one of New Zealand’s highest-grade underground gold mines, a JORC 2012 compliant mineral resource of over

469,000 ounces AuEq at an average above 15 g/t AuEq and a JORC compliant reserve statement. The Company

owns 100% of the Rahu exploration permit, which lies along strike from the Talisman mine of which 80% was

recently acquired from Newcrest Mining. The company will shortly commence exploration activities at Rahu.

Data sourced from publicly available filings. Our datasets may not be complete. Automated analysis can produce errors. If you believe any data on this page is incorrect, please contact us at hello@nzxplorer.co.nz. For informational purposes only. Not investment advice.