New Talisman Gold Mines Ltd logo

Half Year Report and Accounts

Half Year Results14 December 2018NTLIndustrials

HALF YEARLY REPORT
to 30 September 2018

2 | NEW TALISMAN GOLD
HALF YEARLY REPORT 2018

• Underground mining related

activities at Talisman

resume for the first time

since 1992;

• Mystery vein: - blasting,

excavation and stockpiling

of high-grade ore

commenced;

• Traffic management plan

approved by HDC;

• Independent review

of Resource Estimate

complete;

• Updated Pre-Feasibility

Study released;

• Updated Ore Reserve

Statement released;

• Independent valuation

completed;

• Pilot plant installation

commenced; and

• Applications for Rahu field

work lodged.

REPORT TO THE SHAREHOLDERS OF NEW TALISMAN GOLD MINES LTD

Half year ended 30 September 2018

HALF YEARLY REPORT 2018
NEW TALISMAN GOLD | 3

The first six months of the 2019 financial year

have been extremely productive for the Company

with strong progress being made in all aspects

of the Talisman project. Refurbishment works

to the Mystery and Dubbo areas of the mine

are complete and blasting of the face of the

Mystery vein to extend the drive into the vein has

commenced. The Mine has never in its recent

history been in such a solid state of repair and has

been refurbished to modern standards allowing

deployment of mining vehicles and equipment

in those areas. Power cables have been installed

throughout level 8, the auxiliary fan installed and

airflow now reaches all the way through to Dubbo.

Approximately 110 tonnes of ore, at an average

grade of 4.5 g/t Au and 68g/t Ag, has been

transported to the Run of Mine stockpile. The

stockpile is now ready for transporting and

processing at the pilot plant which is being

installed at an off site location with commissioning

expected before year end.


The main purpose of the pilot plant is to replicate

the metallurgical testwork completed by Peacock

and Simpson in which the majority of the gold and

silver is recovered through a purely gravity based system which negates the use of cyanide and other

potentially hazardous chemicals. The remaining gold and any other metals will be concentrated into a

secondary saleable by-product leaving an inert sand which can be applied to industrial and commercial

uses.

Once the pilot process has been established a commercial plant, which will allow processing of up to

1,000 tonnes per month, is planned to be commissioned to meet the future needs of the mine.

Mine Refurbishment

Following on from the previous activities, a significant number of key milestones were achieved which

resulted in the commencement of the mining activities at the Talisman Mine.

A major milestone was achieved in September when, following installation and commissioning of the

250kva generator and main fan, the company undertook the first blast on the Mystery Vein.

True to the company’s commitment to environmentally sustainable mining, sound emissions from the

heavily silenced fan are virtually imperceptible beyond the immediate mine site.

Highlights for the period are:

• The Traffic Management Plan “TMP” was approved by HDC and the company has commenced

activities under the resource consent granted by HDC in 2013. This allows transporting of ore from

the mine offsite with one blast event per day which following completion of refurbishments of level

8 will continue for approximately 2 years as the definitive feasibility study is completed.

• Commissioning of the silenced 250KVA generator and control room is complete and the operation

now has reliable power supply to the main ventilation fan and other site equipment.

• Installation and commissioning of the primary ventilation fan is complete. This fan, mounted

above the airlock and connected to the mine via a reinforced concrete tunnel, is fitted with world

leading silencing equipment to reduce noise emissions to conversational level. The fan is capable

of delivering sufficient air to maintain a healthy respirable atmosphere underground while up to

three diesel powered loaders are deployed in the workings, which has significantly increased the

productivity of the mining team.

• Following the final metres of rehabilitation into the Mystery zone the company was able to

commence the blasting at Mystery during the quarter. Approximately 8 tonnes of vein material

4 | NEW TALISMAN GOLD
HALF YEARLY REPORT 2018

have been extracted which has provided promising results. A resue mining method – blasting the

vein material and surrounding waste in separate stages - is being tested with encouraging results

from the first blast. This system will enable the vein material to be trammed separately from waste

material which will maximise the grade of ore delivered to the plant and reduce transport costs.

The blasts which have been undertaken to date have provided no measurable vibration or noise

at surface.

Samples taken from ore generated by the first blast were independently analysed for gold and silver

content at the SGS laboratory in Waihi and yielded an average grade of 7.1g/t Au as announced on

20/09/2018 (Please see https://www.asx.com.au/asxpdf/20180920/pdf/43yhcd15zcxsp5.pdf)

These results are in line with expectations and consistent with the range of grades in this section of

the Mystery Vein. This is in the same area where recent check sampling of ore exposed at the drive

face yielded grades of up to 40 g/t Au as announced to the market on 31 March 2018 (please see

https://www.asx.com.au/asxpdf/20180508/pdf/43tvlpmv420f4f.pdf ) While considerably more work

is required to understand the full extent of this highly prospective vein system these results are

encouraging and represent a very positive first step in this process.

Rehabilitation of old workings through to the start of the BM37 zone at Dubbo was completed in

the half year and, once vehicle access is attained, loading of rock from the base of the BM37 rise

can begin. Clearing of this rock will provide access to the high-grade Dubbo Zone of the Maria

Vein. This is the site of the last mining by previous owners in the late 1980’s and was identified by

borehole BM37 which assayed 656 g/t Au over 1.8m including 1154 g/t Au over 1.0m. Sampling

in this area has previously yielded results exceeding 1% gold (over 10,000g/t), please see https://

www.asx.com.au/asxpdf/20130705/pdf/42gx44jq96lzrs.pdf

• Maintenance of the mine road was completed in September and has significantly improved the

drainage capability and trafficability of the road.

Post Balance Date Mine Refurbishments

• Final cleanup of the 8 Level drive, including securing vehicular access through the “Bandaid” and

“Viaduct” was completed. There was considerable uncertainty regarding the quantity and quality

of ore present in the area and thus timing was uncertain. Loading operations were carried out for

two weeks with no sign of slow down before the decision was made to barricade the area and

build a stopping to retain remaining ore in the stope. A reinforced retaining wall was constructed

incrementally from the hanging wall of the drive and is fitted with drain pipes to ensure no build

up of water behind the seal.

HALF YEARLY REPORT 2018
NEW TALISMAN GOLD | 5

• The viaduct, the area where the historic fall of ground occurred, has been cleared of waste rock left

over during construction.

• Stockpiling of ore underground has continued successfully. In total approximately 110 tonnes of

ore have been loaded and transferred to the Run of Mine stockpile. Regular interval in stream

sampling was carried out with 44 samples yielding grades that are characteristically variable and

range from trace to 66.0g/t Au for an average of 4.5g/t Au, silver grades assayed in a range of

7.1g/t to 633g/t for an average of 68g/t Ag.

This ore will, in part, be used as the initial feed material to test the pilot plant, the final components

of which have arrived in Auckland. Other feedstock totalling 90+ Tonnes removed for old workings

is also currently stockpiled underground.

• Installation of the underground power cable and auxiliary fan is underway. This second fan is on

site and will be transported to position at the Keillors crosscut junction to pump air into the Dubbo

Drive. Upon completion there will be accessibility for vehicles from the Portal all the way through

to Dubbo which will allow for accelerated clearing into the BM37 area.

• All components of the pilot processing plant, have arrived and are currently being installed offsite.

It is expected the plant will be fully installed and operational with the crushing and grinding circuit

by end of December with first production of gold from stockpiled ore by year end.

While the capacity of the pilot plant is relatively low the aim is to replicate the recovery rates which

were achieved using a similar flowsheet in the testwork carried out in South Africa in February 2018

(please see https://www.asx.com.au/asxpdf/20180322/pdf/43sn63s00fjnz6.pdf). Once recovery rates

are confirmed a larger plant, suitable for the longer-term needs will be acquired.

6 | NEW TALISMAN GOLD
HALF YEARLY REPORT 2018

2018 Prefeasibility study

In July the Company announced the completion of a revised Prefeasibility study on the Talisman Project.

This study, based on the updated Mineral Resource Estimate, has demonstrated an increase in the

Net Present Value of the project, (NPV) from NZD15.4m to NZD35.9m at a 9% Discount Rate. The

updated study proposes a mine plan, focussed on high confidence areas adjacent to No 8 level, based

on the production of 45,000 tonnes at 30.6 g/t AUeq with a significant drop in on mine costs to

NZD583 per ounce and C2 cash costs of NZD710 per ounce. The IRR increased significantly to 118%

The key drivers for this increase in value are discussed below:

• Increased ounces available for extraction – this is a result of the Mineral Resource Upgrade which

saw gold equivalent ounces in the Measured and Indicated categories increase by some 18,000

ounces. These are included in the mining plan which has seen an increase in gold production of

some 18,800 Oz AuEq.

• Increased mine life – on the back of the increased ounces life of mine is extended by a year giving

a current expectation of 6 years;

• Grade – Run of Mine grade, on a gold equivalent basis, has increased from 11.2g/t to more than

27 g/t.

• The USD gold price, based on independent forecasts, is expected to continue trading in a narrow

range of between USD1300/Oz and USD1400/Oz;

• Continued USD strength is expected to result in a falling NZD:USD exchange rate over the project

life

• Extended mine life has seen an increase in operating costs of approximately $8m;

• Capital expenditure is reduced by $1m because of the work already completed towards the Bulk

Sampling Project;

Other key project metrics, in comparison with the previous PFS results, are tabulated below

Table 1 - Results of PFS

Unit20132018Variance

Production

Life of MineYears561

Tonnes Milledktpa107 64 -43

Gold RecoveredOz Total32,200 51,000 18,800

Cost

Total RevenueNZD(m)68 109 41

Total Opex (C3)NZD(m)34 42 8

Total CapexNZD(m) 11 12 1

Financial

Cash SurplusNZD(m) 23 55 32

NPV @9% (Pre-Tax)NZD(m) 15 36 21

IRR%83%118%35%

Payback periodYrs 3 2 -1

Unit Costs

C1 cash CostNZD/Oz 692 583 -109

C2 CostNZD/Oz 904 710 -194

C3 CostNZD/Oz1,041 985 -56

Breakeven Gold PriceNZD/Oz1,075 820-255

Full details of the Pre-Feasibility Study were released to the market on 26/06/2018. The release can be

viewed here https://www.asx.com.au/asxpdf/20180626/pdf/43w27wyn66hkx8.pdf .

HALF YEARLY REPORT 2018
NEW TALISMAN GOLD | 7

8 | NEW TALISMAN GOLD
HALF YEARLY REPORT 2018

Ore Reserve Update

The outcome of the PFS supports a 50% increase in the Ore Reserve attributable to the Talisman Mine.

Ore Reserves, based on an average in-situ cut-off grade of 2.6 g/t, are 45,000 tonnes at 30.6 grams per

tonne gold equivalent. Reserves are quoted at the point of delivery to the gold processing plant and

are derived from and contained within, not additional to, the Measured and Indicated portions of the

Mineral Resource.

The study was reviewed by independent experts who found that the proposed mining plan is appropriate

for the style of deposit at Talisman, and that determination of Ore Reserves has been attained through

reasonable evaluation of mining costs and process recoveries.

Mineral Resource and Ore Reserve categories

Mineral Resources

Total NTLGold Equivalent

CategoryTonnesGrade

Ounces


Measured19,60017.457,480


Indicated62,9007.423,100


Inferred

82,50015.9389,200


Total Resources

16500015.1469,800

Ore Reserves

Total NTLGold Equivalent

CategoryTonnesGradeOunces


Proved30,29435.734,791


Probable14,63220.19,470


Total Reserves44,92630.644,260

Full details of the Ore Reserve were released to the market on 26/06/2018. The release can be viewed

here https://www.asx.com.au/asxpdf/20180626/pdf/43w27wyn66hkx8.pdf

HALF YEARLY REPORT 2018
NEW TALISMAN GOLD | 9

A detailed Independent review of the Mineral resources estimate was completed which confirmed the

2012 JORC compliant resource of 469K oz AuEq at an average grade of 15.1g/t. This makes the Talisman

Mine the highest grade underground active mine in NZ for which grades and resources have doubled

in just over a year. The report concluded:

In reviewing NTGM’s MREs Geos Mining has found that the estimations, the data and the resource

models they are based on, meet the guidelines set out in the 2004 and 2012 JORC Codes and have no

serious errors or issues associated with them.

Further work is being carried out on the remaining data for the fourth module relating to Talisman Deeps

which will be included in the growing database as works are carried out. With significant development

into Mystery and Dubbo, the substantial amount of data and knowledge of the orebody acquired

from these activities will support a review of the MRE and upgrade of remaining areas to JORC 2012

compliance standards in H1 2019.

Rahu

Applications for access and consent to initiate fieldwork at the Rahu Project have been lodged with the

relevant authorities

The Year Ahead

Over the next year the company intends accelerating rehabilitation and extraction activities in the

existing Mystery and BM37 areas while commencing the development of the decline system required

to open up the first significant ore reserve block in the Dubbo zone immediately below No 8 Level.

Mineral resources in this area form part of the high confidence Measured Resources where grades are

estimated to exceed 80g/t AuEq (please see https://www.asx.com.au/asxpdf/20170712/pdf/43kl6294htcscp.

pdf ). Limited amounts of ore will be processed through the pilot plant with the balance being stockpiled

for later processing through the final plant.

Opening up and rehabilitation of the BM37 rise will provide the company with access to the area

where 1980’s sampling indicates grades of up to 656 g/t Au over 1.8m including 1154 g/t Au over

1.0m. Sampling in this area has previously yielded results exceeding 1% gold (over 10,000g/t), please

see https://www.asx.com.au/asxpdf/20130705/pdf/42gx44jq96lzrs.pdf . Ore extracted from this area will be

prioritised for treatment through the pilot plant although other opportunities will be investigated.

Several locations for siting of the final plant have been identified and securing a suitable site, in parallel

with procurement of the plant, will be a high priority over the coming months.

The above works will set the company up for full execution of the mining plan proposed in the 2018

Pre-feasibility Study which indicates average production volumes, once steady state has been achieved

of some 850 tonnes per month at an average Run of Mine grade of 27.3 g/t AuEq.

10 | NEW TALISMAN GOLD
HALF YEARLY REPORT 2018

Schematic diagram of the Talisman Mine

HALF YEARLY REPORT 2018
NEW TALISMAN GOLD | 11

NEW TALISMAN GOLD MINES LIMITED

Consolidated Statement of Financial Position

As at 30 September 2018

Note30-Sep-18

$NZ

Unaudited

31-Mar-18

$NZ

Audited

30-Sep-17

$NZ

Unaudited

Equity

Attributable to parent company

shareholders

16,559,193 17,229,80612,999,911

Term liabilities

Provision for closure and rehabilitation

28,39517,79516,755

Total term liabilities28,39517,79516,755

Current liabilities

Payables264,846213,584222,096

Other--15,840

Employee benefits24,22821,33040,558

Total current liabilities289,074234,914278,494

Total liabilities317,469252,709295,249

Total equity and liabilities 16,876,66217,482,515 13,295,160

Current assets

Cash2,814,098 4,828,750 4,370,016

Receivables and prepayments153,091116,992208,625

Total current assets2,967,1894,945,6724,578,641

Non-current assets

Property, plant & equipment273,23289,677 77,442

Assets under construction610,859,8769,638,2688,607,398

Intangible assets52,756,9502,752,90015,637

Investments19,41555,998 16,042

Total non-current assets13,909,473 12,536,843 8,716,519

Total assets16,876,66217,482,51513,295,160

Net tangible assets per security

0.64 cents0.68 cents0.62 cents

For and on behalf of the Board:




Charbel Nader M G Hill

Dated: 6 December 2018 Dated: 6 December 2018

This statement is to be read in conjunction with the accompanying notes and the previous year’s annual

financial statements.

12 | NEW TALISMAN GOLD
HALF YEARLY REPORT 2018

NEW TALISMAN GOLD MINES LIMITED

Consolidated Statement of Comprehensive Income

For six months ended 30 September 2018

Note 6 Months

30-Sep-18

$NZ

Unaudited

6 Months

30-Sep-17

$NZ

UnauditedContinuing Operations

Interest received36,02875,076

Gain/(Loss) on share revaluation(36,583)(1,496)

Operating and administrative expenses(671,527)(634,912)

Loss from operations

(672,082) (561,332)

Loss before tax for the period

(672,082)(561,332)

Income tax expense--

Total comprehensive income/(loss)

(672,082)(561,332)

Net loss attributable to equity holders of the parent(672,082)(561,332)

Comprehensive loss attributable to equity holders of

the parent

(672,082)(561,332)

Earnings per share

Basic earnings/(loss) per share from continuing

operations

(0.032) cents(0.027) cents

Comprehensive earnings/(loss) per share from

continuing operations

(0.031) cents(0.026) cents


NEW TALISMAN GOLD MINES LIMITED

Consolidated Statement of Changes in Equity

For six months ended 30 September 2018

Note6 months

30-Sep-18

$NZ

Unaudited

6 months

30-Sep-17

$NZ

Unaudited

Total comprehensive income/(loss)(672,082)(561,332)

Prior Year Adjustment1,471-

Proceeds from share capital issued4-1,250

Equity at beginning of period17,229,80413,559,993

Equity at end of period16,559,19312,999,911

This statement is to be read in conjunction with the accompanying notes and the previous year’s annual

financial statements.

HALF YEARLY REPORT 2018
NEW TALISMAN GOLD | 13

NEW TALISMAN GOLD MINES LIMITED

Consolidated Statement of Cash Flows

For six months ended 30 September 2018


Note

6 months

30-Sep-18

$NZ

Unaudited

6 months

30-Sep-17

$NZ

Unaudited

Cash flows from operating activities


Cash inflows36,0281,547

Cash outflows(643,435)(562,583)

Net cash outflows from operating activities

7(607,407)(561,036)

Cash flows from investing activities

Cash inflows--

Cash outflows(1,418,147)(824,282)

Net cash inflows/(outflows) from investing

activities


(1,418,147)


(824,282)

Cash flows from financing activities

Cash inflows4-1,250

Cash outflows--

Net cash inflows from financing activities

-1,250

Net increase / (decrease) in cash held

(2,025,554)(1,384,068)

Effect of changes in exchange rates10,902(314)

Cash at beginning of period4,828,7505,754,398

Cash at end of period2,814,0984,370,016

CASH COMPRISES:

Cash at bank1,209,098265,016

Short term deposits1,605,0004,105,000

2,814,0984,370,016

This statement is to be read in conjunction with the accompanying notes and the previous year’s annual

financial statements.

14 | NEW TALISMAN GOLD
HALF YEARLY REPORT 2018

NEW TALISMAN GOLD MINES LIMITED

Notes to the interim financial statements

1. General

New Talisman Gold Mines Limited is a profit-oriented company incorporated and domiciled in New

Zealand, registered under the Companies Act 1993 and listed on the New Zealand Stock Exchange

(NZX) and the Australian Stock Exchange (ASX).

The company is an FMC reporting entity for the purposes of the Financial Markets Conduct Act 2013 and

the financial statements of the group have been prepared in accordance with the Financial Markets Conduct

Act 2013 and comply with NZX Listing Rule 10.6.1. The group consists of New Talisman Gold Mines Limited

(the “company”) and its subsidiaries (“Group”) and these financial statements are the consolidated financial

statements of the group. The group is engaged in mine development and mineral exploration.

These financial statements were approved for issue by the Directors on 6 December 2018.

Statement of compliance

These interim consolidated financial statements presented are for New Talisman Gold Mines Limited

and its wholly-owned subsidiaries, Coromandel Gold Limited, Northland Minerals Limited and Rahu

Resources Pty Limited (“Group”). The information is presented in New Zealand currency which is the

company’s functional currency. The interim financial statements are condensed in accordance with NZ

IAS-34, Interim Financial Reporting. These consolidated financial statements have not been audited.

The comparative information for the year ended 31 March 2017 has been audited. The comparative

information for the period ended 30 September 2017 has not been audited.

2. Accounting policies

The accounting policies and methods of computation adopted in the preparation of these financial

statements are the same as those adopted in the preparation of the annual financial statements for the

year ended 31 March 2018. Those policies are set out in the annual report for the year ended 31 March

2018. There have been no changes to those accounting policies.

3. Seasonality of operations

The results are unaffected to any significant extent by seasonality factors.

4. Share Capital

Share Capital Movement

6 months

30-Sep-18

$NZ

6 months

30-Sep-17

$NZ

Share Capital Opening balance34,590,84935,164,939

Proceeds from Rights issues-1,250

Balance at end of period34,590,84935,166,189

At balance date 2,164,503,303 shares, 17,036,384 listed options and 4,250,000 unlisted options were on issue.

5. Prospecting Costs

Prospecting costs & mining tenements

6 months

30-Sep-18

$NZ

Year ended

31 Mar 18

$NZ

6 months

30-Sep-17

$NZ

Opening balance2,752,9002,744,90011,637

Development expenditure40508,0004000

Balance at end of period2,756,9502,752,90015,637

HALF YEARLY REPORT 2018
NEW TALISMAN GOLD | 15

6. Mining Tenements

Restated

Talisman Mine Development6 months

30-Sep-18

$NZ

Year ended

31 Mar 18

$NZ

6 months

30-Sep-17

$NZ

Opening balance9,638,2677,843,8827,843,882

Development expenditure1,221,6091,794,385763,516

Balance at end of period10,859,8769,638,2678,607,398

Development expenditure consists of mining development costs, professional salaries, data acquisitions

and a small portion of overhead expenses relating to the operation of the mine. Management assesses

the allocation of directly attributable overheads at the end of each reporting date.

7. Reconciliation of net deficit and operating cash flow

6 months

Sep 2018

$NZ

Unaudited

6 months

Sep 2017

$NZ

Unaudited

Net deficit after taxation

(672,082)(561,332)

Add non-cash items:

Depreciation

19,6178,838

Exchange (gain)/loss

(10,902)314

Loss / (Gain) on revaluation of shares

36,5831,496

45,29810,648

Add (less) movement in working capital:

Decrease (increase) in debtors

2,309535

Increase (decrease) in creditors

54,160144,482

Decrease (increase) in accrued income

7,071(73,530)

Decrease (increase) in Prepayments

(22,505)(44,039)

Decrease (increase) in GST

(21,658)(37,800)

19,377(10,352)

Net cashflows from operating activities

(607,407)(561,036)

8. Expenses

A percentage of certain expenses including wages, consulting fees and other operational expenditure

are capitalised to exploration tenements and assets under construction based on a calculation prepared

by management which is reviewed at each reporting date.

9. Commitments

Capital commitments at the end of the period were $nil. The company has signed a lease agreement for

office rental of $1,705.40 per month plus GST which expires in March 2019.

10. Going concern

The financial report has been prepared on a going concern basis. The company has raised sufficient

funds to commence bulk sampling. The directors expect to ensure that financial obligations can

continue to be met for longer than 12 months.

16 | NEW TALISMAN GOLD
HALF YEARLY REPORT 2018

11. Events subsequent to balance date

No major events occurred after balance date.

12. Related Party Transactions

Payments for consulting services to companies in which directors and major shareholders have a

substantial interest amounted to NZ$174,473. Director fees of $121,144 were payable at the end

of the reporting period. Related party receivables at balance date were $2,194. No related party

debts were written off during the year.

13. Board Appointments and Retirements

There were no changes to the board of directors during this period.

HALF YEARLY REPORT 2018
NEW TALISMAN GOLD | 17

18 | NEW TALISMAN GOLD
HALF YEARLY REPORT 2018

HALF YEARLY REPORT 2018
NEW TALISMAN GOLD | 19

www.newtalisman.co.nz
COMPANY DIRECTORY

DIRECTORS

Charbel Nader (Chairman, Independent)

Tony Haworth (Independent Director)

Murray R Stevens (Non-executive Director)

Matthew G Hill (Chief Executive Officer)

COMPANY SECRETARY

S Jane Bell

Registered (Head) Office

541 Parnell Road, Parnell

Auckland, New Zealand

Telephone (+64 9) 303-1893

Facsimile (+64 9) 303-1612

Email: info@newtalisman.co.nz

Website: www.newtalisman.co.nz

PRINCIPAL OFFICE IN AUSTRALIA

1st Floor, 25 Richardson Street

West Perth

Western Australia 6005

Telephone (+61 8) 9481-2040

Facsimile (+61 8) 9481-2041

BANKERS

Westpac Bank, Auckland

National Australia Bank, West Perth

AUDITORS

K S Black & Co

Level 5

350 Kent Street,

Sydney, 2000

SOLICITORS

Chapman Tripp, Auckland

Simpson Grierson, Auckland

Williams & Hughes, Perth

SECURITIES LISTED

New Zealand Stock Exchange

Code: Shares NTL; Options NTLOB

Australian Securities Exchange

Code: Shares NTL; Options NTLOB

SHARE REGISTRARS

New Zealand:

Computershare Investor Services Limited

Private Bag 92119

Auckland 1142

159 Hurstmere Road

Takapuna, Auckland 0622

New Zealand

Telephone (+64 9) 488-8777

Facsimile (+64 9) 488-8787

Australia:

Computershare Investor Services Pty Limited

Yarra Falls

452 Johnston Street

Abbotsford Victoria 3067, Australia

Telephone 1300 850 505

Overseas callers (+61 3) 9415-4000

Managing your shareholding online:

To change your address, update your payment

instructions and view your investment portfolio

including transactions please visit

www.computershare.co.nz/investorcentre

General enquiries can be directed to:

enquiry@computershare.co.nz

Please assist our registrar by quoting your CSN or

shareholder number

Data sourced from publicly available filings. Our datasets may not be complete. Automated analysis can produce errors. If you believe any data on this page is incorrect, please contact us at hello@nzxplorer.co.nz. For informational purposes only. Not investment advice.