Half Year Report and Accounts
HALF YEARLY REPORT
to 30 September 2018
2 | NEW TALISMAN GOLD
HALF YEARLY REPORT 2018
• Underground mining related
activities at Talisman
resume for the first time
since 1992;
• Mystery vein: - blasting,
excavation and stockpiling
of high-grade ore
commenced;
• Traffic management plan
approved by HDC;
• Independent review
of Resource Estimate
complete;
• Updated Pre-Feasibility
Study released;
• Updated Ore Reserve
Statement released;
• Independent valuation
completed;
• Pilot plant installation
commenced; and
• Applications for Rahu field
work lodged.
REPORT TO THE SHAREHOLDERS OF NEW TALISMAN GOLD MINES LTD
Half year ended 30 September 2018
HALF YEARLY REPORT 2018
NEW TALISMAN GOLD | 3
The first six months of the 2019 financial year
have been extremely productive for the Company
with strong progress being made in all aspects
of the Talisman project. Refurbishment works
to the Mystery and Dubbo areas of the mine
are complete and blasting of the face of the
Mystery vein to extend the drive into the vein has
commenced. The Mine has never in its recent
history been in such a solid state of repair and has
been refurbished to modern standards allowing
deployment of mining vehicles and equipment
in those areas. Power cables have been installed
throughout level 8, the auxiliary fan installed and
airflow now reaches all the way through to Dubbo.
Approximately 110 tonnes of ore, at an average
grade of 4.5 g/t Au and 68g/t Ag, has been
transported to the Run of Mine stockpile. The
stockpile is now ready for transporting and
processing at the pilot plant which is being
installed at an off site location with commissioning
expected before year end.
The main purpose of the pilot plant is to replicate
the metallurgical testwork completed by Peacock
and Simpson in which the majority of the gold and
silver is recovered through a purely gravity based system which negates the use of cyanide and other
potentially hazardous chemicals. The remaining gold and any other metals will be concentrated into a
secondary saleable by-product leaving an inert sand which can be applied to industrial and commercial
uses.
Once the pilot process has been established a commercial plant, which will allow processing of up to
1,000 tonnes per month, is planned to be commissioned to meet the future needs of the mine.
Mine Refurbishment
Following on from the previous activities, a significant number of key milestones were achieved which
resulted in the commencement of the mining activities at the Talisman Mine.
A major milestone was achieved in September when, following installation and commissioning of the
250kva generator and main fan, the company undertook the first blast on the Mystery Vein.
True to the company’s commitment to environmentally sustainable mining, sound emissions from the
heavily silenced fan are virtually imperceptible beyond the immediate mine site.
Highlights for the period are:
• The Traffic Management Plan “TMP” was approved by HDC and the company has commenced
activities under the resource consent granted by HDC in 2013. This allows transporting of ore from
the mine offsite with one blast event per day which following completion of refurbishments of level
8 will continue for approximately 2 years as the definitive feasibility study is completed.
• Commissioning of the silenced 250KVA generator and control room is complete and the operation
now has reliable power supply to the main ventilation fan and other site equipment.
• Installation and commissioning of the primary ventilation fan is complete. This fan, mounted
above the airlock and connected to the mine via a reinforced concrete tunnel, is fitted with world
leading silencing equipment to reduce noise emissions to conversational level. The fan is capable
of delivering sufficient air to maintain a healthy respirable atmosphere underground while up to
three diesel powered loaders are deployed in the workings, which has significantly increased the
productivity of the mining team.
• Following the final metres of rehabilitation into the Mystery zone the company was able to
commence the blasting at Mystery during the quarter. Approximately 8 tonnes of vein material
4 | NEW TALISMAN GOLD
HALF YEARLY REPORT 2018
have been extracted which has provided promising results. A resue mining method – blasting the
vein material and surrounding waste in separate stages - is being tested with encouraging results
from the first blast. This system will enable the vein material to be trammed separately from waste
material which will maximise the grade of ore delivered to the plant and reduce transport costs.
The blasts which have been undertaken to date have provided no measurable vibration or noise
at surface.
Samples taken from ore generated by the first blast were independently analysed for gold and silver
content at the SGS laboratory in Waihi and yielded an average grade of 7.1g/t Au as announced on
20/09/2018 (Please see https://www.asx.com.au/asxpdf/20180920/pdf/43yhcd15zcxsp5.pdf)
These results are in line with expectations and consistent with the range of grades in this section of
the Mystery Vein. This is in the same area where recent check sampling of ore exposed at the drive
face yielded grades of up to 40 g/t Au as announced to the market on 31 March 2018 (please see
https://www.asx.com.au/asxpdf/20180508/pdf/43tvlpmv420f4f.pdf ) While considerably more work
is required to understand the full extent of this highly prospective vein system these results are
encouraging and represent a very positive first step in this process.
Rehabilitation of old workings through to the start of the BM37 zone at Dubbo was completed in
the half year and, once vehicle access is attained, loading of rock from the base of the BM37 rise
can begin. Clearing of this rock will provide access to the high-grade Dubbo Zone of the Maria
Vein. This is the site of the last mining by previous owners in the late 1980’s and was identified by
borehole BM37 which assayed 656 g/t Au over 1.8m including 1154 g/t Au over 1.0m. Sampling
in this area has previously yielded results exceeding 1% gold (over 10,000g/t), please see https://
www.asx.com.au/asxpdf/20130705/pdf/42gx44jq96lzrs.pdf
• Maintenance of the mine road was completed in September and has significantly improved the
drainage capability and trafficability of the road.
Post Balance Date Mine Refurbishments
• Final cleanup of the 8 Level drive, including securing vehicular access through the “Bandaid” and
“Viaduct” was completed. There was considerable uncertainty regarding the quantity and quality
of ore present in the area and thus timing was uncertain. Loading operations were carried out for
two weeks with no sign of slow down before the decision was made to barricade the area and
build a stopping to retain remaining ore in the stope. A reinforced retaining wall was constructed
incrementally from the hanging wall of the drive and is fitted with drain pipes to ensure no build
up of water behind the seal.
HALF YEARLY REPORT 2018
NEW TALISMAN GOLD | 5
• The viaduct, the area where the historic fall of ground occurred, has been cleared of waste rock left
over during construction.
• Stockpiling of ore underground has continued successfully. In total approximately 110 tonnes of
ore have been loaded and transferred to the Run of Mine stockpile. Regular interval in stream
sampling was carried out with 44 samples yielding grades that are characteristically variable and
range from trace to 66.0g/t Au for an average of 4.5g/t Au, silver grades assayed in a range of
7.1g/t to 633g/t for an average of 68g/t Ag.
This ore will, in part, be used as the initial feed material to test the pilot plant, the final components
of which have arrived in Auckland. Other feedstock totalling 90+ Tonnes removed for old workings
is also currently stockpiled underground.
• Installation of the underground power cable and auxiliary fan is underway. This second fan is on
site and will be transported to position at the Keillors crosscut junction to pump air into the Dubbo
Drive. Upon completion there will be accessibility for vehicles from the Portal all the way through
to Dubbo which will allow for accelerated clearing into the BM37 area.
• All components of the pilot processing plant, have arrived and are currently being installed offsite.
It is expected the plant will be fully installed and operational with the crushing and grinding circuit
by end of December with first production of gold from stockpiled ore by year end.
While the capacity of the pilot plant is relatively low the aim is to replicate the recovery rates which
were achieved using a similar flowsheet in the testwork carried out in South Africa in February 2018
(please see https://www.asx.com.au/asxpdf/20180322/pdf/43sn63s00fjnz6.pdf). Once recovery rates
are confirmed a larger plant, suitable for the longer-term needs will be acquired.
6 | NEW TALISMAN GOLD
HALF YEARLY REPORT 2018
2018 Prefeasibility study
In July the Company announced the completion of a revised Prefeasibility study on the Talisman Project.
This study, based on the updated Mineral Resource Estimate, has demonstrated an increase in the
Net Present Value of the project, (NPV) from NZD15.4m to NZD35.9m at a 9% Discount Rate. The
updated study proposes a mine plan, focussed on high confidence areas adjacent to No 8 level, based
on the production of 45,000 tonnes at 30.6 g/t AUeq with a significant drop in on mine costs to
NZD583 per ounce and C2 cash costs of NZD710 per ounce. The IRR increased significantly to 118%
The key drivers for this increase in value are discussed below:
• Increased ounces available for extraction – this is a result of the Mineral Resource Upgrade which
saw gold equivalent ounces in the Measured and Indicated categories increase by some 18,000
ounces. These are included in the mining plan which has seen an increase in gold production of
some 18,800 Oz AuEq.
• Increased mine life – on the back of the increased ounces life of mine is extended by a year giving
a current expectation of 6 years;
• Grade – Run of Mine grade, on a gold equivalent basis, has increased from 11.2g/t to more than
27 g/t.
• The USD gold price, based on independent forecasts, is expected to continue trading in a narrow
range of between USD1300/Oz and USD1400/Oz;
• Continued USD strength is expected to result in a falling NZD:USD exchange rate over the project
life
• Extended mine life has seen an increase in operating costs of approximately $8m;
• Capital expenditure is reduced by $1m because of the work already completed towards the Bulk
Sampling Project;
Other key project metrics, in comparison with the previous PFS results, are tabulated below
Table 1 - Results of PFS
Unit20132018Variance
Production
Life of MineYears561
Tonnes Milledktpa107 64 -43
Gold RecoveredOz Total32,200 51,000 18,800
Cost
Total RevenueNZD(m)68 109 41
Total Opex (C3)NZD(m)34 42 8
Total CapexNZD(m) 11 12 1
Financial
Cash SurplusNZD(m) 23 55 32
NPV @9% (Pre-Tax)NZD(m) 15 36 21
IRR%83%118%35%
Payback periodYrs 3 2 -1
Unit Costs
C1 cash CostNZD/Oz 692 583 -109
C2 CostNZD/Oz 904 710 -194
C3 CostNZD/Oz1,041 985 -56
Breakeven Gold PriceNZD/Oz1,075 820-255
Full details of the Pre-Feasibility Study were released to the market on 26/06/2018. The release can be
viewed here https://www.asx.com.au/asxpdf/20180626/pdf/43w27wyn66hkx8.pdf .
HALF YEARLY REPORT 2018
NEW TALISMAN GOLD | 7
8 | NEW TALISMAN GOLD
HALF YEARLY REPORT 2018
Ore Reserve Update
The outcome of the PFS supports a 50% increase in the Ore Reserve attributable to the Talisman Mine.
Ore Reserves, based on an average in-situ cut-off grade of 2.6 g/t, are 45,000 tonnes at 30.6 grams per
tonne gold equivalent. Reserves are quoted at the point of delivery to the gold processing plant and
are derived from and contained within, not additional to, the Measured and Indicated portions of the
Mineral Resource.
The study was reviewed by independent experts who found that the proposed mining plan is appropriate
for the style of deposit at Talisman, and that determination of Ore Reserves has been attained through
reasonable evaluation of mining costs and process recoveries.
Mineral Resource and Ore Reserve categories
Mineral Resources
Total NTLGold Equivalent
CategoryTonnesGrade
Ounces
Measured19,60017.457,480
Indicated62,9007.423,100
Inferred
82,50015.9389,200
Total Resources
16500015.1469,800
Ore Reserves
Total NTLGold Equivalent
CategoryTonnesGradeOunces
Proved30,29435.734,791
Probable14,63220.19,470
Total Reserves44,92630.644,260
Full details of the Ore Reserve were released to the market on 26/06/2018. The release can be viewed
here https://www.asx.com.au/asxpdf/20180626/pdf/43w27wyn66hkx8.pdf
HALF YEARLY REPORT 2018
NEW TALISMAN GOLD | 9
A detailed Independent review of the Mineral resources estimate was completed which confirmed the
2012 JORC compliant resource of 469K oz AuEq at an average grade of 15.1g/t. This makes the Talisman
Mine the highest grade underground active mine in NZ for which grades and resources have doubled
in just over a year. The report concluded:
In reviewing NTGM’s MREs Geos Mining has found that the estimations, the data and the resource
models they are based on, meet the guidelines set out in the 2004 and 2012 JORC Codes and have no
serious errors or issues associated with them.
Further work is being carried out on the remaining data for the fourth module relating to Talisman Deeps
which will be included in the growing database as works are carried out. With significant development
into Mystery and Dubbo, the substantial amount of data and knowledge of the orebody acquired
from these activities will support a review of the MRE and upgrade of remaining areas to JORC 2012
compliance standards in H1 2019.
Rahu
Applications for access and consent to initiate fieldwork at the Rahu Project have been lodged with the
relevant authorities
The Year Ahead
Over the next year the company intends accelerating rehabilitation and extraction activities in the
existing Mystery and BM37 areas while commencing the development of the decline system required
to open up the first significant ore reserve block in the Dubbo zone immediately below No 8 Level.
Mineral resources in this area form part of the high confidence Measured Resources where grades are
estimated to exceed 80g/t AuEq (please see https://www.asx.com.au/asxpdf/20170712/pdf/43kl6294htcscp.
pdf ). Limited amounts of ore will be processed through the pilot plant with the balance being stockpiled
for later processing through the final plant.
Opening up and rehabilitation of the BM37 rise will provide the company with access to the area
where 1980’s sampling indicates grades of up to 656 g/t Au over 1.8m including 1154 g/t Au over
1.0m. Sampling in this area has previously yielded results exceeding 1% gold (over 10,000g/t), please
see https://www.asx.com.au/asxpdf/20130705/pdf/42gx44jq96lzrs.pdf . Ore extracted from this area will be
prioritised for treatment through the pilot plant although other opportunities will be investigated.
Several locations for siting of the final plant have been identified and securing a suitable site, in parallel
with procurement of the plant, will be a high priority over the coming months.
The above works will set the company up for full execution of the mining plan proposed in the 2018
Pre-feasibility Study which indicates average production volumes, once steady state has been achieved
of some 850 tonnes per month at an average Run of Mine grade of 27.3 g/t AuEq.
10 | NEW TALISMAN GOLD
HALF YEARLY REPORT 2018
Schematic diagram of the Talisman Mine
HALF YEARLY REPORT 2018
NEW TALISMAN GOLD | 11
NEW TALISMAN GOLD MINES LIMITED
Consolidated Statement of Financial Position
As at 30 September 2018
Note30-Sep-18
$NZ
Unaudited
31-Mar-18
$NZ
Audited
30-Sep-17
$NZ
Unaudited
Equity
Attributable to parent company
shareholders
16,559,193 17,229,80612,999,911
Term liabilities
Provision for closure and rehabilitation
28,39517,79516,755
Total term liabilities28,39517,79516,755
Current liabilities
Payables264,846213,584222,096
Other--15,840
Employee benefits24,22821,33040,558
Total current liabilities289,074234,914278,494
Total liabilities317,469252,709295,249
Total equity and liabilities 16,876,66217,482,515 13,295,160
Current assets
Cash2,814,098 4,828,750 4,370,016
Receivables and prepayments153,091116,992208,625
Total current assets2,967,1894,945,6724,578,641
Non-current assets
Property, plant & equipment273,23289,677 77,442
Assets under construction610,859,8769,638,2688,607,398
Intangible assets52,756,9502,752,90015,637
Investments19,41555,998 16,042
Total non-current assets13,909,473 12,536,843 8,716,519
Total assets16,876,66217,482,51513,295,160
Net tangible assets per security
0.64 cents0.68 cents0.62 cents
For and on behalf of the Board:
Charbel Nader M G Hill
Dated: 6 December 2018 Dated: 6 December 2018
This statement is to be read in conjunction with the accompanying notes and the previous year’s annual
financial statements.
12 | NEW TALISMAN GOLD
HALF YEARLY REPORT 2018
NEW TALISMAN GOLD MINES LIMITED
Consolidated Statement of Comprehensive Income
For six months ended 30 September 2018
Note 6 Months
30-Sep-18
$NZ
Unaudited
6 Months
30-Sep-17
$NZ
UnauditedContinuing Operations
Interest received36,02875,076
Gain/(Loss) on share revaluation(36,583)(1,496)
Operating and administrative expenses(671,527)(634,912)
Loss from operations
(672,082) (561,332)
Loss before tax for the period
(672,082)(561,332)
Income tax expense--
Total comprehensive income/(loss)
(672,082)(561,332)
Net loss attributable to equity holders of the parent(672,082)(561,332)
Comprehensive loss attributable to equity holders of
the parent
(672,082)(561,332)
Earnings per share
Basic earnings/(loss) per share from continuing
operations
(0.032) cents(0.027) cents
Comprehensive earnings/(loss) per share from
continuing operations
(0.031) cents(0.026) cents
NEW TALISMAN GOLD MINES LIMITED
Consolidated Statement of Changes in Equity
For six months ended 30 September 2018
Note6 months
30-Sep-18
$NZ
Unaudited
6 months
30-Sep-17
$NZ
Unaudited
Total comprehensive income/(loss)(672,082)(561,332)
Prior Year Adjustment1,471-
Proceeds from share capital issued4-1,250
Equity at beginning of period17,229,80413,559,993
Equity at end of period16,559,19312,999,911
This statement is to be read in conjunction with the accompanying notes and the previous year’s annual
financial statements.
HALF YEARLY REPORT 2018
NEW TALISMAN GOLD | 13
NEW TALISMAN GOLD MINES LIMITED
Consolidated Statement of Cash Flows
For six months ended 30 September 2018
Note
6 months
30-Sep-18
$NZ
Unaudited
6 months
30-Sep-17
$NZ
Unaudited
Cash flows from operating activities
Cash inflows36,0281,547
Cash outflows(643,435)(562,583)
Net cash outflows from operating activities
7(607,407)(561,036)
Cash flows from investing activities
Cash inflows--
Cash outflows(1,418,147)(824,282)
Net cash inflows/(outflows) from investing
activities
(1,418,147)
(824,282)
Cash flows from financing activities
Cash inflows4-1,250
Cash outflows--
Net cash inflows from financing activities
-1,250
Net increase / (decrease) in cash held
(2,025,554)(1,384,068)
Effect of changes in exchange rates10,902(314)
Cash at beginning of period4,828,7505,754,398
Cash at end of period2,814,0984,370,016
CASH COMPRISES:
Cash at bank1,209,098265,016
Short term deposits1,605,0004,105,000
2,814,0984,370,016
This statement is to be read in conjunction with the accompanying notes and the previous year’s annual
financial statements.
14 | NEW TALISMAN GOLD
HALF YEARLY REPORT 2018
NEW TALISMAN GOLD MINES LIMITED
Notes to the interim financial statements
1. General
New Talisman Gold Mines Limited is a profit-oriented company incorporated and domiciled in New
Zealand, registered under the Companies Act 1993 and listed on the New Zealand Stock Exchange
(NZX) and the Australian Stock Exchange (ASX).
The company is an FMC reporting entity for the purposes of the Financial Markets Conduct Act 2013 and
the financial statements of the group have been prepared in accordance with the Financial Markets Conduct
Act 2013 and comply with NZX Listing Rule 10.6.1. The group consists of New Talisman Gold Mines Limited
(the “company”) and its subsidiaries (“Group”) and these financial statements are the consolidated financial
statements of the group. The group is engaged in mine development and mineral exploration.
These financial statements were approved for issue by the Directors on 6 December 2018.
Statement of compliance
These interim consolidated financial statements presented are for New Talisman Gold Mines Limited
and its wholly-owned subsidiaries, Coromandel Gold Limited, Northland Minerals Limited and Rahu
Resources Pty Limited (“Group”). The information is presented in New Zealand currency which is the
company’s functional currency. The interim financial statements are condensed in accordance with NZ
IAS-34, Interim Financial Reporting. These consolidated financial statements have not been audited.
The comparative information for the year ended 31 March 2017 has been audited. The comparative
information for the period ended 30 September 2017 has not been audited.
2. Accounting policies
The accounting policies and methods of computation adopted in the preparation of these financial
statements are the same as those adopted in the preparation of the annual financial statements for the
year ended 31 March 2018. Those policies are set out in the annual report for the year ended 31 March
2018. There have been no changes to those accounting policies.
3. Seasonality of operations
The results are unaffected to any significant extent by seasonality factors.
4. Share Capital
Share Capital Movement
6 months
30-Sep-18
$NZ
6 months
30-Sep-17
$NZ
Share Capital Opening balance34,590,84935,164,939
Proceeds from Rights issues-1,250
Balance at end of period34,590,84935,166,189
At balance date 2,164,503,303 shares, 17,036,384 listed options and 4,250,000 unlisted options were on issue.
5. Prospecting Costs
Prospecting costs & mining tenements
6 months
30-Sep-18
$NZ
Year ended
31 Mar 18
$NZ
6 months
30-Sep-17
$NZ
Opening balance2,752,9002,744,90011,637
Development expenditure40508,0004000
Balance at end of period2,756,9502,752,90015,637
HALF YEARLY REPORT 2018
NEW TALISMAN GOLD | 15
6. Mining Tenements
Restated
Talisman Mine Development6 months
30-Sep-18
$NZ
Year ended
31 Mar 18
$NZ
6 months
30-Sep-17
$NZ
Opening balance9,638,2677,843,8827,843,882
Development expenditure1,221,6091,794,385763,516
Balance at end of period10,859,8769,638,2678,607,398
Development expenditure consists of mining development costs, professional salaries, data acquisitions
and a small portion of overhead expenses relating to the operation of the mine. Management assesses
the allocation of directly attributable overheads at the end of each reporting date.
7. Reconciliation of net deficit and operating cash flow
6 months
Sep 2018
$NZ
Unaudited
6 months
Sep 2017
$NZ
Unaudited
Net deficit after taxation
(672,082)(561,332)
Add non-cash items:
Depreciation
19,6178,838
Exchange (gain)/loss
(10,902)314
Loss / (Gain) on revaluation of shares
36,5831,496
45,29810,648
Add (less) movement in working capital:
Decrease (increase) in debtors
2,309535
Increase (decrease) in creditors
54,160144,482
Decrease (increase) in accrued income
7,071(73,530)
Decrease (increase) in Prepayments
(22,505)(44,039)
Decrease (increase) in GST
(21,658)(37,800)
19,377(10,352)
Net cashflows from operating activities
(607,407)(561,036)
8. Expenses
A percentage of certain expenses including wages, consulting fees and other operational expenditure
are capitalised to exploration tenements and assets under construction based on a calculation prepared
by management which is reviewed at each reporting date.
9. Commitments
Capital commitments at the end of the period were $nil. The company has signed a lease agreement for
office rental of $1,705.40 per month plus GST which expires in March 2019.
10. Going concern
The financial report has been prepared on a going concern basis. The company has raised sufficient
funds to commence bulk sampling. The directors expect to ensure that financial obligations can
continue to be met for longer than 12 months.
16 | NEW TALISMAN GOLD
HALF YEARLY REPORT 2018
11. Events subsequent to balance date
No major events occurred after balance date.
12. Related Party Transactions
Payments for consulting services to companies in which directors and major shareholders have a
substantial interest amounted to NZ$174,473. Director fees of $121,144 were payable at the end
of the reporting period. Related party receivables at balance date were $2,194. No related party
debts were written off during the year.
13. Board Appointments and Retirements
There were no changes to the board of directors during this period.
HALF YEARLY REPORT 2018
NEW TALISMAN GOLD | 17
18 | NEW TALISMAN GOLD
HALF YEARLY REPORT 2018
HALF YEARLY REPORT 2018
NEW TALISMAN GOLD | 19
www.newtalisman.co.nz
COMPANY DIRECTORY
DIRECTORS
Charbel Nader (Chairman, Independent)
Tony Haworth (Independent Director)
Murray R Stevens (Non-executive Director)
Matthew G Hill (Chief Executive Officer)
COMPANY SECRETARY
S Jane Bell
Registered (Head) Office
541 Parnell Road, Parnell
Auckland, New Zealand
Telephone (+64 9) 303-1893
Facsimile (+64 9) 303-1612
Email: info@newtalisman.co.nz
Website: www.newtalisman.co.nz
PRINCIPAL OFFICE IN AUSTRALIA
1st Floor, 25 Richardson Street
West Perth
Western Australia 6005
Telephone (+61 8) 9481-2040
Facsimile (+61 8) 9481-2041
BANKERS
Westpac Bank, Auckland
National Australia Bank, West Perth
AUDITORS
K S Black & Co
Level 5
350 Kent Street,
Sydney, 2000
SOLICITORS
Chapman Tripp, Auckland
Simpson Grierson, Auckland
Williams & Hughes, Perth
SECURITIES LISTED
New Zealand Stock Exchange
Code: Shares NTL; Options NTLOB
Australian Securities Exchange
Code: Shares NTL; Options NTLOB
SHARE REGISTRARS
New Zealand:
Computershare Investor Services Limited
Private Bag 92119
Auckland 1142
159 Hurstmere Road
Takapuna, Auckland 0622
New Zealand
Telephone (+64 9) 488-8777
Facsimile (+64 9) 488-8787
Australia:
Computershare Investor Services Pty Limited
Yarra Falls
452 Johnston Street
Abbotsford Victoria 3067, Australia
Telephone 1300 850 505
Overseas callers (+61 3) 9415-4000
Managing your shareholding online:
To change your address, update your payment
instructions and view your investment portfolio
including transactions please visit
www.computershare.co.nz/investorcentre
General enquiries can be directed to:
enquiry@computershare.co.nz
Please assist our registrar by quoting your CSN or
shareholder number
Data sourced from publicly available filings. Our datasets may not be complete. Automated analysis can produce errors. If you believe any data on this page is incorrect, please contact us at hello@nzxplorer.co.nz. For informational purposes only. Not investment advice.