Infratil Limited/Announcement
Infratil Limited logo

Tilt Renewables: Dundonnell Wind Farm Update

Guidance9 July 2020IFTUtilities

Infratil Limited 5 Market Lane, PO Box 320, Wellington, New Zealand Tel +64-4-473 3663 www.infratil.com

10 July 2020



Tilt Renewables: Dundonnell Wind Farm Update

Tilt Renewables Limited (‘Tilt Renewables’), in which Infratil is a 65% shareholder, announced this morning

that it expects its FY2021 EBITDAF to be in the range of A$65 million to A$80 million, which is a decrease

from its earlier guidance range of A$80 million to A$95 million. The Tilt Renewables announcement is also

attached.

As part of Infratil’s FY2020 results announcement on 29 May 2020, Infratil advised that the continued

uncertainty over the duration and impact of the COVID-19 pandemic meant FY2021 Group earnings or

dividend guidance could not be provided at that stage, but Infratil would provide FY2021 Group guidance

when it had sufficient certainty. As part of that same announcement, Infratil provided component guidance

for FY2021 EBIDTDAF for each of Trustpower, Tilt Renewables and CDC Data Centres, which included the

earlier Tilt Renewables FY2021 EBITDAF guidance range referred to above.

Infratil does not yet have sufficient certainty to provide FY2021 Group guidance but notes the updated

guidance range provided by Tilt Renewables’ today.


Any enquiries should be directed to:

Mark Flesher, Investor Relations, Infratil Limited mark.flesher@infratil.com

---

Tilt Renewables GPO Box 16080
Phone: +61 1300 660 623 Collins Street West

tiltrenewables.com Melbourne Victoria, 8007

Australia


NZX AND ASX ANNOUNCEMENT 

9 July 2020 

DUNDONNELL WIND FARM UPDATE 

Tilt Renewables Limited (“TLT”) is pleased to announce that turbine erection activities at the 336MW 

Dundonnell Wind Farm (“DDWF”) located in Western Victoria have been completed, with all 80 turbines 

now erected, in‐line with the original project schedule.  Construction

 activities at the site are now winding 

down and focused on completing commissioning and grid connection of the final batch of turbines.   

To date no Lost Time Injuries have been recorded at the project during more than 600,000 working hours. 

TLT CEO Deion Campbell said, “to deliver 80 of the 

largest wind turbines ever installed in the southern 

hemisphere safely and on time is a superb result and a credit to all involved in the planning and execution 

of the project”.  

To allow DDWF to connect to the Victorian 500kV network TLT has been following an agreed 

commissioning plan to confirm

 compliance with the Generator Performance Standards which were 

negotiated with the Australian Electricity Market Operator (“AEMO”) prior to reaching financial close in 

respect of DDWF in 2018.  Turbine commissioning has progressed such that 113MW is now fully 

operating, however, there is now expected to be a delay in increasing above 

this output due to concerns 

raised by AEMO.   

TLT continues to work with AEMO and turbine supplier, Vestas, to mitigate AEMO's unanticipated 

concerns and allow an increase in the output of DDWF to its full 336MW capacity.  

At this time, whilst discussions continue with AEMO, TLT considers there is insufficient clarity

 of the 

process required by AEMO for TLT to forecast the length of the delay to production ramp up.  

Given the current restriction on DDWF production, TLT now estimates that group EBITDAF for FY21 will 

fall below the guidance range provided to the market in May 2020.  The remaining uncertainty

 with 

production ramp up at DDWF means it is difficult to accurately forecast the EBITDAF contribution from 

DDWF for the full year.  Recognising the uncertainties surrounding the likely outcomes, at this time TLT 

expects FY21 EBITDAF to be in the range of A$65m to A$80m, assuming P50 wind conditions.   

Deion 

Campbell further commented, “the delay to reaching full production at DDWF is unfortunate given 

TLT has followed the prescribed connection process, however it should be remembered that this is a long 

term infrastructure asset which will eventually move to full production and produce strong cashflows for 

more than 30 years”. 

 

ENDS 

 

 

For further information from Tilt Renewables, please contact: 

Steve Symons  

Chief Financial Officer 

Tilt Renewables 

Phone +61 419 893 746

Data sourced from publicly available filings. Our datasets may not be complete. Automated analysis can produce errors. If you believe any data on this page is incorrect, please contact us at hello@nzxplorer.co.nz. For informational purposes only. Not investment advice.