Channel Infrastructure NZ Limited logo

Q3 Conversion Project Update

Quarterly Update12 October 2022CHIEnergy

channelnz.com


NZX RELEASE


13 October 2022


Q3 Conversion Project Update

Channel Infrastructure (CHI), New Zealand’s largest fuel import terminal business based at Marsden Point in

Northland, has today released its quarterly conversion project update for the three months ended 30

September 2022 (Q3 FY22).


Key conversion project highlights for Q3 FY22 include:

• Six months of terminal operations successfully completed with 35 import shipments received and

discharged;

• Permanent decommissioning of refinery plant is now over 70% complete and on track for completion

of decommissioning in H1 FY23

• Significant workforce transition largely complete with 97% of those who have left having secured

their next opportunity; and

• Conversion costs tracking to budget, with approximately $98 million spent project to date.


CEO Naomi James said “After six months of terminal operations, our business is now firmly focused on the

future, with imported fuel flowing through our infrastructure and the first delivery of sustainable aviation fuel

receipted into Marsden Point. We are progressing work to source lower cost renewable electricity, and have

had significant interest in our RFI, while at the same time we continue to work with customers to support

them with the import of fuels which offer more choice to consumers. We are delivering on our plans to utilise

Marsden Point’s highly strategic assets to deliver long-term shareholder value, while at the same time

supporting our customers to decrease their environmental impact in the future.”


Overall, the terminal and pipeline supplied nearly one-and-a-half billion litres of product to the Auckland and

Northland markets since 1 April. Jet fuel throughput continues to grow steadily and is approaching 60% of

pre-COVID levels. Further strong growth in jet demand is expected as more overseas airlines return to

Auckland over the summer period and long-haul routes and capacity is added.


Decommissioning of refining plant continues to progress well and remains on schedule for completion in H1

2023.


Terminal upgrade works (including changes to increase vessel discharge rates and commissioning of the

first fire-system and secondary-containment upgrades) and continued private storage tank conversion work

is ongoing and progressing well.


The extensive workforce transition program is now largely complete. Channel Infrastructure had a target for

at least 90% of employees securing a job or retraining within 6 months of leaving, and this has been reached

with 97% of those who have left having secured their next opportunity.


Conversion costs are tracking to plan with $98 million spent to 30 September 2022 (30 June 2022: $73

million), including c$7m of private storage costs. The conversion spend, partly offset with positive cash flows


channelnz.com

from terminal operations, resulted in an increase in net borrowings from $215 million as at 30 June 2022 to

$230 million as at 30 September 2022.


- ENDS -



Authorised by:

Chris Bougen

General Counsel and Company Secretary

Investor Relations contact:

Anna Bonney

investorrelations@channelnz.com


Media contact:

Laura Malcolm

communications@channelnz.com

+64 21 02363 297


About Channel Infrastructure NZ

Channel Infrastructure is New Zealand’s leading fuel infrastructure company.

Channel Infrastructure owns critical infrastructure, supplying the Northland and Auckland markets, which

make up 40% of New Zealand’s transport fuel demand and all of the jet fuel to the Auckland International

Airport. Utilising the deep-water harbour and jetty infrastructure at Marsden Point, as well as 280 million

litres of storage tanks, and the 170-kilometre pipeline from Marsden Point to Auckland we receive, store, test

and distribute fuel owned by our customers. Channel Infrastructure’s wholly-owned subsidiary, Independent

Petroleum Laboratories, provides fuel quality testing services at Marsden Point and around New Zealand.

Channel Infrastructure is well positioned to support New Zealand’s changing future fuel needs, with growth

opportunities at the Marsden Point site including additional fuel storage to support fuel security, renewable

electricity supply through the Maranga Ra solar project, and work underway with customers and partners on

biofuel and hydrogen opportunities.

For more information on Channel Infrastructure, please visit: www.channelnz.com

Data sourced from publicly available filings. Our datasets may not be complete. Automated analysis can produce errors. If you believe any data on this page is incorrect, please contact us at hello@nzxplorer.co.nz. For informational purposes only. Not investment advice.

Other issuers discussed similar conditions around this time

Matched by meaning across NZX announcement text, not keywords — based on our semantic index of announcement bodies.