Meridian Energy Limited logo

Meridian to build Ruakaka Battery Energy Storage System

Operational Update14 December 2022MELUtilities

Release






Meridian Energy Limited (ARBN 151 800 396) A company incorporated in New Zealand

287-293 Durham Street North, Christchurch 8013


meridianenergy.co.nz

Stock Exchange Listings NZX (MEL) ASX (MEZ)

Meridian to build Ruakākā Battery Energy Storage System

15 December 2022

Meridian Energy will begin construction of the Ruakākā Battery Energy Storage System (BESS)

in the first quarter of 2023. The project will construct New Zealand’s first large-scale grid

battery storage system, providing Meridian with a versatile North Island asset, situated

south of Whangārei.

Meridian Energy Chief Executive Neal Barclay says the company’s approach to a battery

storage system has evolved during its development phase.

“A North Island battery was originally part of our response package to Rio Tinto’s

termination of its electricity contract for the Tiwai Point Aluminium Smelter. As we

developed the opportunity, the BESS business case proved to be an economic investment

irrespective of Rio Tinto’s future in New Zealand.”

Mr Barclay says the BESS offers multiple new revenue streams, providing the ability to load

shift between price periods and to participate in the North Island reserve electricity market.

“As intermittent renewable generation increases in this country, the Ruakākā Battery Energy

Storage System will help manage supply fluctuations through a low carbon footprint,

reducing this country’s reliance on fossil fuels,” Mr Barclay says.

“We have a bold vision for Ruakākā, with a grid-scale solar farm planned to further speed up

our transition to a productive low carbon economy. The shared infrastructure provided by

the BESS will significantly improve the economics of the future solar farm,” adds Mr Barclay.

Global battery specialist Saft will provide integrated battery supply, installation,

commissioning and operational services for the Ruakākā BESS. Meridian Energy will manage

a multi contract delivery approach, with project completion expected in the second half of

2024.


ENDS

Neal Barclay

Chief Executive

Meridian Energy Limited


For investor relations queries, please contact:

Owen Hackston

Investor Relations Manager

021 246 4772

For media queries, please contact:

Rheilli Uluilelata

External Communications Advisor

022 589 1052

RUAKĀKĀBATTERY ENERGY STORAGE SYSTEM
15 DECEMBER 2022

2
Today’s announcement

15 DECEMBER 2022

RUAKĀKĀ BESS INVESTMENT DECISION

The BESS project is stage one of a two-stage project that

anticipates the future construction of a 130MW solar farm

§Meridian has committed to construction

of the RuakākāBattery Energy Storage

System (BESS)

§NPV positive project that significantly

improves the investment economics of

the stage two solar project

§Strategic location immediately adjacent

to Transpower’s 220kV Bream Bay

substation

§Direct revenue from electricity price

arbitrage and reserve market

participation

§Reduced price separation benefit to

Meridian’s portfolio

3
Project overview

15 DECEMBER 2022

RUAKĀKĀ BESS INVESTMENT DECISION

SH5 egress

§BESS site is a 30 minute drive from Whangārei,

located adjacent to Transpower’s 220kV Bream Bay

substation, Channel Infrastructure’s fuel import

terminal and Northport

§The balance of the land, along with additional

nearby land, will be used for development of a

130MW solar farm

§A ‘multi contract’ approach will be used to deliver

the project

§Bulk of the project capital cost is the battery

contract with Saft

§Balance of plant delivers the civil and electrical

infrastructure for the battery and provides the

export path via a connection to Transpower

§Balance of plant also includes operations,

maintenance and switch room buildings

4
Project overview

15 DECEMBER 2022

RUAKĀKĀ BESS INVESTMENT DECISION

SH5 egress

Meridian Civil Works

Including: site access, drainage, pad, BESS foundations, fencing, firewater

§Four major contracts will be running in parallel: Meridian's civil and electrical works, Saft BESS

contract and Transpower's grid connection works

Transpower Works Agreement

33kV switchgear

Meridian Electrical Works

33kV switchgear

Bream Bay substation

Saft BESS Contract

Saft battery container

Power Electronics inverter

Power Electronics

transformer and switchgear

power

flow

SCADA control, comms

Transpower

connection

100MW peak and 200MWh (2 hours) energy storage
3hectare project site (land purchased in 2021)

Project completion in second half of 2024

Battery Energy Storage Solution (integrated supply, install, commission, operational services)

Shared infrastructure (switchgear, buildings) will reduce stage two solar project unit cost by ~$20\MWh

$186m capital investment, including contingency

$20m -$30m EBITDAF p.a. (average, low -high scenarios)

$6moperating costs p.a. mainly transmission costs (connection, benefit-based investment and residual charges)

Up to $35mrevenue p.a. from price arbitrage, reserve market participation, indirect revenue

5

Project specifications

15 DECEMBER 2022

RUAKĀKĀBESS INVESTMENT DECISION

§Arbitrage means buying power at low

price periods and selling at high price

periods.This form of ‘load shifting’ will

secure revenue, as well as providing

support to the grid at peak times

§As the volume of intermittent generation

grows, arbitrage will increasingly include

operating in response to fluctuating

output from wind and solar

§6 second fast reserve (FIR) and 60 second

sustained reserve (SIR) are procured by

island and are co-optimisednationwide

§A BESS will operate and secure revenue

from both the FIR and SIR markets in the

North Island simultaneously alongside any

arbitrage activity

§Increasing supply in the North Island

reserve markets will increase HVDC

transfers, with a corresponding reduction

in North Island thermal generation

§Reduced separation between North Island

and South Island prices will deliver energy

margin benefits

6
Disclaimer

The information in this presentation was prepared by Meridian

Energy with due care and attention. However, the information is

supplied in summary form and is therefore not necessarily complete,

and no representation is made as to the accuracy, completeness or

reliability of the information. In addition, neither the company nor

any of its directors, employees, shareholders nor any other person

shall have liability whatsoever to any person for any loss (including,

without limitation, arising from any fault or negligence) arising from

this presentation or any information supplied in connection with it.

This presentation may contain forward-looking statements and

projections. These reflect Meridian’s current expectations, based on

what it thinks are reasonable assumptions. Meridian gives no

warranty or representation as to its future financial performance or

any future matter. Except as required by law or NZX or ASX listing

rules, Meridian is not obliged to update this presentation after its

release, even if things change materially.

This presentation does not constitute financial advice. Further, this

presentation is not and should not be construed as an offer to sell or

a solicitation of an offer to buy Meridian Energy securities and may

not be relied upon in connection with any purchase of Meridian

Energy securities.

This presentation contains a number of non-GAAP financial

measures, including Energy Margin, EBITDAF, Underlying NPAT and

gearing. Because they are not defined by GAAP or IFRS, Meridian's

calculation of these measures may differ from similarly titled

measures presented by other companies and they should not be

considered in isolation from, or construed as an alternative to, other

financial measures determined in accordance with GAAP. Although

Meridian believes they provide useful information in measuring the

financial performance and condition of Meridian's business, readers

are cautioned not to place undue reliance on these non-GAAP

financial measures.

The information contained in this presentation should be considered

in conjunction with the company’s financial statements, which are

available at:

www.meridianenergy.co.nz/investors

All currency amounts are in New Zealand dollars unless stated

otherwise.

15 DECEMBER 2022

RUAKĀKĀ BESS INVESTMENT DECISION

Data sourced from publicly available filings. Our datasets may not be complete. Automated analysis can produce errors. If you believe any data on this page is incorrect, please contact us at hello@nzxplorer.co.nz. For informational purposes only. Not investment advice.

Other issuers discussed similar conditions around this time

Matched by meaning across NZX announcement text, not keywords — based on our semantic index of announcement bodies.