Auckland, 17 April 2023: Fletcher Building (“the Group”) today provides an update on the Iplex

Australia Pro-fit pipe product issue. In Fletcher Building's 2023 Interim Financial Results issued

in February 2023, it was noted that Iplex Australia had received a number of product quality

complaints relating to a hot and cold water polybutylene pipe product it previously manufactured

(under the name "Pro-fit"). The complaints relate to leaks in homes, primarily built by group home

builders in Western Australia, which have required repair or replacement of the pipes and, in

some cases, damage to the affected homes. It was also noted that the Group was aware that

the Western Australia building regulator (the Department of Mines, Industry Regulation and

Safety, known as DMIRS) was undertaking its own investigation.

Reports to Iplex Australia are that, to date, about 1,200 of the 15,000 houses constructed in

Western Australia using Pro-fit in the period mid-2017 to mid-2022 have experienced leaks. The

date range is relevant as builders have told Iplex Australia that they have not experienced unusual

levels of leaks in homes constructed prior to that period. Iplex Australia ceased the sale of Pro-

fit in mid-2022.

The Pro-fit product was also sold into other States of Australia in that period. Reports to Iplex

Australia are that the leak rate in those States is not materially unusual for a product of this type.

The Pro-fit product was sold only in Australia and the resin used in it during the period in question

was not used by Iplex New Zealand or any other Fletcher Building company for any other

product.

DMIRS has advised Iplex Australia that, while its tests are not yet complete, Iplex Australia should

expect its results to lead to DMIRS finding that the leaks are due to a manufacturing defect. A

Western Australia group home builder has also advised it expects to deliver to Iplex Australia the

results of its own tests once they are completed.

For its own part, Iplex Australia is undertaking its own on-going, extensive investigation into the

root cause. At this time, the work that has been completed does not identify a manufacturing

defect.

In the near term, Iplex Australia expects to work with DMIRS and other stakeholders on the

appropriate path forward. That path will be informed by the cause or causes identified, whether

those matters are agreed or contested, the facts and patterns observed in the data provided by

all parties, whether the regulators accept any proposed response plan and the availability of

resources in the market to undertake work. The range of outcomes of that work plan may include

some form of product replacement in the homes where it was installed, in whole or in part.

In the meantime, Iplex Australia’s assistance to builders is ongoing.



Fletcher Building Limited, Private Bag 92114, Auckland 1142, 810 Great South Road, Penrose, Auckland 1061, New Zealand


Iplex Australia has proposed interim arrangements with two large group homebuilders in Perth

(who together constructed about 90% of the currently affected homes there) to assist them, as,

in turn, they help homeowners. These are commercial proposals on a no liability basis which do

not address, nor are they based on, causation. They offer a basis for an interim period for the two

builders to replace ceiling product in homes that have leaked and repair damage as well as

provide a body of data to allow Iplex Australia and other stakeholders to develop a plan for a

longer-term solution.

In addition, Iplex Australia will establish a Fund of A$2 million to assist other WA plumbers and

builders who also constructed affected homes on a no admissions basis to reimburse costs

incurred by them for the same scope of work as may be agreed with the two group home

builders. Further information about the Fund will be published on Iplex Australia’s website once

available.

Fletcher Building chief executive Ross Taylor said: “We acknowledge the frustration and

inconvenience impacted homeowners and their families are facing. We are working hard with

builders to arrive at an acceptable outcome for affected homeowners.”

In the 2023 Interim Financial Results, Fletcher Building noted that Iplex Australia had made a

provision for this matter but that there was a risk that the provision was inadequate. As a result

of the proposal made to the two group homebuilders and establishing the Fund to support other

affected builders, Iplex Australia will increase that provision from A$2 million to A$15 million. That

amount will be revisited if facts emerge to warrant it and as part of the full year financial reporting

process.

The extent to which Iplex Australia will ultimately have accountability for this matter, the cost that

may be incurred and the timing of any payments is not able to be established at this time. As

noted in the 2023 Interim Financial Results Iplex Australia's exposure to costs incurred by the

leaks will depend on the final determination as to their cause (or causes), the extent to which it

and/or third parties are responsible and how any relevant insurance policies respond. The

amount will also be dependent on the remediation required and the damage suffered by third

parties which is attributed to Iplex Australia. These matters are likely to take some time to be

identified and settled.

The Iplex Australia provision and any other cost relating to the Pro-fit pipe issue are excluded

from the FY23 Group earnings guidance.

Authorised by:

Chris Reid

Company Secretary





Fletcher Building Limited, Private Bag 92114, Auckland 1142, 810 Great South Road, Penrose, Auckland 1061, New Zealand


For further information please contact:


MEDIA

Christian May

General Manager – Group Corporate Affairs

+64 21 305 398

Christian.May@fbu.com


INVESTORS AND ANALYSTS

Aleida White

Head of Investor Relations

+64 21 155 8837

Aleida.White@fbu.com

Data sourced from publicly available filings. Our datasets may not be complete. Automated analysis can produce errors. If you believe any data on this page is incorrect, please contact us at hello@nzxplorer.co.nz. For informational purposes only. Not investment advice.