Infratil’s CDC Data Centres valuation rises by A$448m

Property8 October 2023IFTUtilities

Infratil Limited 5 Market Lane, PO Box 320, Wellington, New Zealand Tel +64-4-473 3663 www.infratil.com

9 October 2023

Infratil’s CDC Data Centres valuation rises by A$448 million

The 30 September 2023 independent valuation of Infratil’s investment in CDC Data Centres (‘CDC’)

shows an increase of A$448 million over the six months since the 31 March 2023 valuation.

Infratil’s 47.99% investment in CDC is now valued at between A$3,641 million to A$4,186 million (with

a midpoint of A$3,884 million), up from A$3,145 million to A$3,744 million (with a midpoint of A$3,436

million) at the end of March 2023. The 30 September 2023 NZD valuation of Infratil’s CDC

investment is $3,921 million to $4,507 million (with a midpoint of $4,182 million).

Infratil’s CEO Jason Boyes said “CDC’s data centre design, operating model and customer base is

strategically positioned to benefit from the new growth in demand for artificial intelligence services.

These market dynamics have seen a significant uptick in inbound customer interest. In response to

this demand CDC is expecting a significant acceleration of construction and expansion of

development planning in all locations – Canberra, Sydney, Melbourne and Auckland”.

The 30 September 2023 valuation assumes 268MW of existing operating facilities, another 265MW

currently under construction and 517MW classified as future builds to 2028, details of which are set

out in the table below.

This represents an increase of 223MW under construction and a total additional capacity including

future builds of 264MW since 31 March 2023. CDC currently has access to the vast majority of the

land required to complete these future builds.

The current forecast cost to build is consistent with recent performance.

The blended cost of equity used in the valuation has increased from 9.60% to 11.20% between March

and September 2023. This reflects an increase in the asset-specific risk premium, driven by the

acceleration of CDC’s construction programme, expansion in CDC’s assumed future build pipeline

and the valuer’s assessment of the relative increase in the scale and complexity of its

commercialisation and delivery. It also reflects an increase in the risk-free rate (3.65% to 3.75%) and

an increase in gearing as a result of higher forecast debt levels as CDC continues investment in its

expanded development pipeline.

Net debt as at 30 September was A$2,270 million.

CDC’s FY2024 full-year EBITDAF guidance of A$260 million to $270 million remains unchanged.

Further information, including the estimated International Portfolio Fair Market Value and the impact

on International Portfolio incentive fees, which are calculated on a whole of portfolio basis, will be

provided as part of Infratil’s Interim Result which is due to be released on 16 November 2023.


Region

Status Build Capacity (MW)

Canberra

Operating 117

Sydney

Operating 123

Auckland

Operating

28

Total Operating Capacity 268

Canberra Under Construction 56

Sydney

Under Construction 147

Melbourne

Under Construction 32

Auckland

Under Construction 30

Total Under Construction Capacity 265



2







Any investor enquiries should be directed to:

Mark Flesher

Investor Relations

mark.flesher@infratil.com

Region

Status Build Capacity (MW)

Canberra Future Build 55

Sydney Future Build

151

Melbourne Future Build 208

Australian Expansion Future Build 22

Auckland Future Build 81

Total Future Build Capacity 517

Total Capacity 1,050