Contact Energy Limited logo

Tauhara commissioning update

Operational Update9 November 2023CENUtilities

contactenergy.co.nz
10 November 2023


Contact Energy: Tauhara commissioning update

Contact Energy is working through a range of commissioning issues at its Tauhara geothermal

development, including the remediation of underperforming steam-field valves and liquid

handling systems and the implications of a steam hammer event. Given the range of

commissioning issues identified, some elements of the steam separation plant will require

further design and modification. This work will have a consequential impact on the

commissioning timeline previously communicated.

Contact now expects to have the plant online in Q3 2024 (from Q1 2024) at least at the initial

design capacity of 152MW and is targeting the full planned output of 174MW at the plant’s first

planned outage following further optimisation and plant modifications.

CEO Mike Fuge said “While this outcome is not what we were targeting when we entered

commissioning, this is the stage of any geothermal project when such unknowns will be

brought to the fore and mitigations applied. We are working with the lead design consultant

on the project to understand all contributing factors. The on-site team are experts in major

infrastructure and geothermal development and will look for all opportunities to minimise the

delay while ensuring process safety first on this multi-decade asset.”

Contact is applying strategies to mitigate the deferral of this expected geothermal generation,

in line with its commodity risk framework and confirmed there is no change to its FY24

normalised and expected EBITDAF guidance of $600m. While the plant modifications will

require a cost increase of up to $40m, the project will still achieve an LRMC of around $75 per

MWh

1

. “Tauhara remains a stand-out renewable energy project and will be a fantastic long-

term asset for New Zealand, generating attractive returns for Contact’s shareholders.”


- ends -

Investor enquiries

Shelley Hollingsworth

Investor Relations & Strategy Manager

+64 27 227 2429

shelley.hollingsworth@contactenergy.co.nz


Media enquiries

Louise Wright

Head of Communications and Reputation

+64 21 840 313

louise.wright@contactenergy.co.nz


1

Assumptions include a capital cost of $920m, broker consensus WACC of 7.5%; inflation of 2%; corporate tax rate of 28%;

35-year plant life; $15/MWh operating costs; ~$8m p.a. capex (with major mid-life capex smoothed) as at FID in February 2021.

Data sourced from publicly available filings. Our datasets may not be complete. Automated analysis can produce errors. If you believe any data on this page is incorrect, please contact us at hello@nzxplorer.co.nz. For informational purposes only. Not investment advice.

Other issuers discussed similar conditions around this time

Matched by meaning across NZX announcement text, not keywords — based on our semantic index of announcement bodies.