Santana Minerals Ltd logo

Investor Presentation - Diggers and Dealers Mining Forum

Investor Presentation5 August 2024SMIMaterials

The Silver Fern:
Turns to Gold

Diggers and Dealers Conference, Kalgoorlie

August 2024

Damian Spring, CEO

Santana Minerals Limited ASX:SMI NZX SMI

Disclaimer
Disclaimer

All information contained in this presentation is of a general nature. Potential investors are cautioned

against using the content of this presentation, in isolation, for making investment decisions and should

also refer to Santana Minerals Limited (‘Santana’) Annual Reports and ASX:SMI and NZX:SMI

releases. For further information about Santana visit our website at www.santanaminerals.com.

Best efforts have been made to ensure the accuracy of information contained (at the time of

preparation). Where forward targets and/or assumptions have been included – all such instances are

indicative only and subject to alteration and/or cancellation as and when the management of Santana

determines.

Research and advice of a qualified financial advisor or accountant are strongly recommended to

anyone considering investing in listed company securities, including those of Santana.

Forward-Looking Statements

Forward-looking statements in this presentation include, but are not limited to, statements with

respect to Santana’s future plans, strategy, activities, events or developments the Company believes,

expects or anticipates will or may occur. By their very nature, forward-looking statements require

Santana to make assumptions that may not materialize or that may not be accurate. Although

Santana believes that the expectations reflected in the forward-looking statements in this presentation

are reasonable, no assurance can be given that these expectations will prove to have been correct,

as actual results and future events could differ materially from those anticipated in the forward-looking

statements. Accordingly, viewers are cautioned not to place undue reliance on forward-looking

statements. Santana does not undertake to update publicly or to revise any of the included forward-

looking statements, except as may be required under applicable securities laws.

Previous Disclosure - 2012 JORC Code

The information in this report that relates to Mineral Resources or Ore Reserves is based on information in

numerous announcements to the ASX and NZX including information relating to general Resources,

Exploration Targets and Exploration Data associated with the Company’s projects.

A copy of these announcements are available to view on the Santana Minerals Limited website

www.santanaminerals.com or on the ASX platform www.asx.com.au or on the NZX platform www.nzx.com.

The reports are issued in accordance with the 2012 Edition of the JORC Australasian Code for Reporting of

Exploration Results, Mineral Resources and Ore Reserves including the appropriate Competent Person’s

statements. The Company confirms that the form and context in which the Competent Person’s findings are

presented have not been materially modified from the original market announcements.

The Company confirms that it is not aware of any new information or data that materially affects the

information included in the original market announcements and, in the case of estimates of mineral

resources, that all material assumptions and technical parameters underpinning the estimates in the relevant

market announcement continue to apply and have not materially changes.

2

3

Largest single discovery of gold
in NZ over past 40 years

4

Waihi (TSX:OGC):

•Commenced at Martha Hill in 1988 with 1Moz at 5.9 g/t

1


Macraes (TSX:OGC):

•Commenced at Round Hill in 1990 with 1.8Moz at 1.4g/t

2

Globe Progress (TSX:OGC):

•2007-2016 started with 0.6Moz at 2.0 g/t

4

Snowy River (Federation Mining):

•Commenced development in 2022 0.7Moz at 23.0 g/t

5

Santana Minerals Ltd (ASX/NZX:SMI):

•Rise and Shine in 2024 with 2.2Moz at 2.3g/t

Bendigo-Ophir

Gold Project

OGC’s Globe Progress

FED’s Snowy River Gold mine

OGC’s Macraes Gold mine

Amongst world-class New Zealand gold operations

OGC’s Waihi Gold mine

Sources:

1

Gosling, Expansion at the Martha Mine, Waihi, AusIMM, 1997

2

Angus et al, Exploration Along the Hyde Macraes Shear, AusIMM, 1997

3

OceanaGold website

4

Cooksey, et al, Challenges of Selective Mining, AusIMM, 1997

5

Federation Mining website

Bendigo-Ophir (BOP) Gold Project
Multiple gold discoveries over five kilometres of strike

Come In Time

59koz @ 1.5 g/t Au

Rise and Shine

2,217koz @ 2.3g/t Au Incl

Indicated of 1,445koz @ 2.4g/t Au

Shreks

174koz @ 1.1 g/t Au

Shreks-East

11koz @ 1.3 g/t Au

Combined Total

2,463koz @ 2.1 g/t Au*

* refer to ASX release 2 July 2024

CIT

RSSZ

RAS

SHR

SRE

5

Project Location
•One hour east of

Queenstown

•Central Otago region of the

South island

•90km West of OceanaGold’s

Macraes gold mine

•15min drive from Cromwell

with 8,000 people

•In the semi-arid Central

Otago

•Private farmland, with

agreements to mine in place

6

7

The Bendigo-Ophir Gold Project – Simplified History
1860’s gold rush.

July 2022 drilling expands to 1.68 Moz

(27.2 Mt @ 1.8g/t Au). All Inferred

1

Feb. 2023 drilling expands to 2.66 Moz

(33.5 Mt @ 2.5g/t Au). 11.7% Indicated

1

Feb. 2024 infill drilling adds to >80,000m

of diamond drilling and refines MRE to

2.22 Moz (30.8 Mt @ 2.2g/t Au) with

58.4% Indicated

1

Santana embarks on Scoping

Study on RAS Indicated only to

reveal initial economic outcomes.

Coincident gold and arsenic

soil anomalies exposed.

MDD007

40.3m @ 2.05 g/t in TZ4 schists

under 120m of TZ3 cover rock

Shreks Area

Low-grade near surface

mineralsation in TZ4

schists

April 2021 - MDD007 changes the

game.

1

2012 JORC Guidelines for Mineral Resource Estimation

The Bendigo-Ophir Gold Project – Simplified History
1860’s gold rush.

July 2022 drilling expands to 1.68 Moz

(27.2 Mt @ 1.8g/t Au). All Inferred

1

Feb. 2023 drilling expands to 2.66 Moz

(33.5 Mt @ 2.5g/t Au). 11.7% Indicated

1

Feb. 2024 infill drilling adds to >80,000m

of diamond drilling and refines MRE to

2.22 Moz (30.8 Mt @ 2.2g/t Au) with

58.4% Indicated

1

Santana embarks on Scoping

Study on RAS Indicated only to

reveal initial economic outcomes.

Coincident gold and arsenic

soil anomalies exposed.

MDD007

40.3m @ 2.05 g/t in TZ4 schists

under 120m of TZ3 cover rock

Shreks Area

Low-grade near surface

mineralsation in TZ4

schists

April 2021 - MDD007 changes the

game.

1

2012 JORC Guidelines for Mineral Resource Estimation

•A blind discovery
•85,000m+ of

Diamond Drilling

•1.7 km down-

plunge and open

•450m wide

•High-grade core

(150m-200m wide)

(30 - 40m thick)

•Bulk barren waste

pre-strip


The Rise & Shine (RAS)

5

1.7km

The Rise & Shine (RAS)
5

The Rise & Shine (RAS)
5

•A blind discovery
•85,000m+ of

Diamond Drilling

•1.7 km down-

plunge and open

•450m wide

•High-grade core

(150m-200m wide)

(30 - 40m thick)

•Bulk barren waste

pre-strip


The Rise & Shine (RAS)

5

1.7km

The Rise & Shine (RAS)
5

RAS - Scoping Study
Come In Time

59koz @ 1.5 g/t Au

Rise and Shine

2,216koz @ 2.2g/t Au

Shreks

174koz @ 1.1 g/t Au

Shreks-East

11koz @ 1.3 g/t Au

Combined Total

2,462koz @ 2.1 g/t Au*

CIT

BOP

RAS

SHR

SRE

Feb-24 RAS 1.3 Million oz

Indicated only17.1 Mt @ 2.4 g/t Au

* refer to ASX release 2 July 2024

RAS Scoping Study – Initial Physical Outcomes
•Base case US$1,650/oz (A$:US

0.66) or A$2,500/oz.

•Process Plant: CIL 1.5Mtpa

•Staged Open Pit

•11.8m

3

pre-strip (32Mt)

•8-year pit (12.1Mt @ 2.5g/t)

•Post pre-strip Strip ratio 9.8:1

•Underground (upper part only)

•4 years production

•2.3Mt @ 3.1 g/t

•84% Indicated

•Metallurgical Recovery 93%

•Total Ounces Produced

•1.12Moz recovered (10yrs)

Shepherds

Creek

Rise and

Shine Creek

RAS Scoping Study – Initial Physical Outcomes
•Base case US$1,650/oz (A$:US

0.66) or A$2,500/oz.

•Process Plant: CIL 1.5Mtpa

•Staged Open Pit

•11.8m

3

pre-strip (32Mt)

•8-year pit (12.1Mt @ 2.5g/t)

•Post pre-strip Strip ratio 9.8:1

•Underground (upper part only)

•4 years production

•2.3Mt @ 3.1 g/t

•84% Indicated

•Metallurgical Recovery 93%

•Total Ounces Produced

•1.12Moz recovered (10yrs)

Shepherds

Creek

Rise and

Shine Creek

Looking west

RAS Scoping Study – Initial Physical Outcomes
•Base case US$1,650/oz (A$:US

0.66) or A$2,500/oz.

•Process Plant: CIL 1.5Mtpa

•Staged Open Pit

•11.8m

3

pre-strip (32Mt)

•8-year pit (12.1Mt @ 2.5g/t)

•Post pre-strip Strip ratio 9.8:1

•Underground (upper part only)

•4 years production

•2.3Mt @ 3.1 g/t

•84% Indicated

•Metallurgical Recovery 93%

•Total Ounces Produced

•1.12Moz recovered (10yrs)

Shepherds

Creek

Rise and

Shine Creek

Looking west

Inferred

RAS Scoping Study – Initial Fiscal Outcomes
Key Financial AssumptionsUnitBase Case AUDApprox Spot AUD

Gold Price Assumed$/ozA$2,500/ozA$ 3,650/oz

Key Project Metrics

Gold ProducedOz pa~ 112,000 oz/year

Initial Mine LifeYears10 years

Key Project Metrics

Gold Revenue$MA$ 2,800MA$ 4,088 M

Total Cash Operating Cost$M

$/oz

A$ 914M

A$ 816/oz

A$ 914 M


Project EBITDA$MA$ 1,886MA$ 3,174 M

Depreciation and Amortisation$MA$ 503MA$ 503M

Total Production Cost

$M

$/oz

A$ 1,417M

A$ 1,265/oz

A$ 1,417 M


After Tax Profit$MA$ 987 MA$ 1,902 M

Capital

Capital Plant and Infrastructure$MA$ 130M

Working Capital (pre-strip and

set-up).

$MA$ 103M

Sust. Capital (funded from prod’n)$MA$ 270M

A$250m in Capex

Benchmarking

110,000 oz per annum

C2 Costs of A$ 820/oz

Total Cost of A$ 1,265/oz

NPAT of $1.92 billion over 10 yrs

NPV

10

after tax of A$870m

IRR of 75%

Upgrading to PFS

Dec Quarter

A gold developer’s dream
Bendigo-Ophir

RAS Gold Project

Cromwell

8,000 people

Queenstown

International Airport

1hr away

No FIFO

No major camps

Main road access

Access to fresh water

Cheap power

State Highway 8

EASY ACCESS

Borefield

FRESH WATER

Clyde Dam Hydro Power

LOW COST GREEN ENERGY

5km

20

66kV Substation

8km from the project

Next Steps
21

Study Activity

Progress

Heritage surveysCompleted

Socio-economic baseline studyCompleted

Ecology fieldworkCompleted

Recreational baseline studyCompleted

Annual baseline water quality reportCompleted

Additional environmental studiesOngoing

Mine planning and engineeringOngoing

Drilling at satellite depositsOngoing

To DateDecember QuarterQ1 CY2025

Activity

Finish PFS

Engage financiers

Fast Track Approvals Bill - Vote

Activity

Apply for project consents

6 months under Fast Track Bill

12-14 month build time

PATHWAY TO

CONSTRUCTION

22
High-grade core

23

Thank you