Market Update

• Formal Processing Agreement and Processing Site lease

• Plant Commissioning and Trials.


With the price of gold at all-time highs, New Talisman Gold Mines Ltd is pleased to provide

an update on the commissioning of its recently purchased ore processing plant and planned

commencement of production from the historically rich Talisman mine.

New Talisman has previously indicated its intention to enter production by the end of the first

calendar quarter. With plant assembly well advanced it has become clear that while we could

meet that self-imposed deadline by processing a symbolic amount, it is better to defer

processing by a few weeks into April, allowing us to put more meaningful volumes into the

plant, and optimise the operation of the plant through this commissioning and testing phase.

There have been no “showstoppers” or insurmountable problems assembling the plant, but

as largely anticipated, it has been a complex bespoke operation that will continue to be fine-

tuned to reach optimal recovery levels from the Talisman ore.

The commissioning/trialling period will involve frequent weighing and assaying of both ore

and of concentrate to ascertain and tune recovery levels. At this stage, we anticipate scaling

up volumes in May to approx. 300T, and running at that level for a period while we assess

the grades discovered by advancing the face of Mystery North vein. This work will inform

our decisions on whether to open up further faces, significantly increase volumes, and

consider upgrading the means of conveyance underground.

The Terra Firma team have demonstrated a broad range of capabilities in preparing the

processing site and assembling the plant and New Talisman is pleased to confirm the terms

of the Heads of Agreement with Terra Firma Mining for providing a processing site,

commissioning, and operating the processing plant have now all been met. Consequently,

the related formal agreements confirming these arrangements are being implemented.

We will continue to update the market as we progress in this exciting time in the company’s

evolution to producing explorer.





John Upperton

General Manager

New Talisman Gold Mines Limited

2b Gibraltar Cres,

Parnell, Auckland 1052

Office +64 9 303 1893

info@newtalisman.co.nz

Data sourced from publicly available filings. Our datasets may not be complete. Automated analysis can produce errors. If you believe any data on this page is incorrect, please contact us at hello@nzxplorer.co.nz. For informational purposes only. Not investment advice.

Other issuers discussed similar conditions around this time

Matched by meaning across NZX announcement text, not keywords — based on our semantic index of announcement bodies.

  • SMI — Santana Minerals Ltd: RAS Mineral Resource Estimate Review
    2025-03-03

    6 March 2025 RAS Mineral Resources Open Pit & U/G cut-offs Category Cut-Off (g/t Au) Tonnes (Mt) Au (g/t) rounded Contained Gold (koz) Open pit Indicated 0.5 18.9 2.5 1534 Inferred 6.5 2.1 434 Total 25.4 2.4 1,968 Underground Indicated 1.5 0.03 4.1 4 Inferred 1.…”