Fletcher Building/Announcement
Fletcher Building logo

Fletcher Building Updates on NZICC

Legal5 June 2025FBUMaterials

Fletcher Building Limited, 810 Great South Road, Penrose, Auckland 1061, New Zealand

6 June 2025


Fletcher Building Updates on New Zealand International Convention Centre

Fletcher Building acknowledges the legal action announced today by SkyCity

Entertainment Group (SkyCity) against its subsidiary, Fletcher Construction, regarding the

New Zealand International Convention Centre (NZICC) project. The risk of a dispute with

SkyCity over delay and costs associated with the NZICC has been flagged in previous

disclosures, including most recently in the Company’s 2024 Annual Report and the FY25

Interim Financial Results.


The Company notes that Fletcher Construction has already paid significant liquidated

damages to SkyCity in relation to the delays in delivering the NZICC in accordance with

the building works contract. Accordingly, Fletcher Construction will vigorously defend

itself against the SkyCity claim for further liquidated damages beyond the capped

amount provided for in the building works contract. Whilst the delivery of the NZICC

project has suffered from a number of challenges, including as a consequence of the fire

and Covid-related impacts, Fletcher Building rejects absolutely that it has breached its

contract with SkyCity in the manner alleged.


More generally, Fletcher Building confirms that it has completed the construction work

on the NZICC. Its focus has now moved to remediating defects and, seeking to work

collaboratively with SkyCity, completing the complex commissioning processes and

securing required Council sign-offs. Fletcher Building anticipates handing over the site

to enable SkyCity to commence its operational readiness activities during the second

half of 2025, in preparation for SkyCity’s announced opening in February 2026.


The net costs to complete the NZICC have been re-assessed, including taking into

account the costs and resources estimated to be required for the project’s final stages,

with the result that Fletcher Building expects to record a further provision of c$12–15

million, in addition to provisions previously reported in February 2024. That provision

does not include any costs associated with the SkyCity dispute announced today. The

Group also continues to pursue recoveries under the NZICC Third Party Liability (TPL)

insurance policy of more than $100 million and has brought legal action against the

roofing membrane subcontractors in relation to the fire, which will commence shortly in

the High Court. While the Company considers it has good grounds to recover material

amounts under the TPL policy and the Court action, it has not recognised any recoveries

at this time.




Fletcher Building remains committed to delivering this landmark project and is confident

that once it is available to be seen and used by the public and international guests they

will be delighted with the quality of the asset that will make a meaningful contribution to

the New Zealand economy.


ENDS


Authorised for release to the market by Haydn Wong, Company Secretary.

_____________________________________________________________________________________________________________

For further information please contact:


INVESTORS Will Wright, Chief Financial Officer +64 21 490 251 Will.Wright@fbu.com

MEDIA Christian May, Chief Corporate Affairs Officer +64 21 305 398 Christian.May@fbu.com


For information on Fletcher Building visit fletcherbuilding.com

Data sourced from publicly available filings. Our datasets may not be complete. Automated analysis can produce errors. If you believe any data on this page is incorrect, please contact us at hello@nzxplorer.co.nz. For informational purposes only. Not investment advice.

Other issuers discussed similar conditions around this time

Matched by meaning across NZX announcement text, not keywords — based on our semantic index of announcement bodies.