MKR

Cobar Basin PFS Show Substantial Increase in Profit and NPV

Operational Update29 January 2026MKRMaterials

ASX Announcement
30 January 2026


ASX: MKR





Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000

ABN 80 611 963 225 Tel 02- 7253 2020 www.manukaresources.com.au

Manuka Provides Updated Cobar Basin PFS

Highlighting Substantial Increase in Profit and NPV


Highlights

• Project NPV

8

of A$805 million and IRR of 1,092% based on US$95/oz silver,

US$4,800/oz gold prices and AUD/USD of 0.7000.

• 10-Year Mine Plan to produce 13.2 million ounces of silver and 35 thousand

ounces of gold from existing stockpiles and open pits located at the

Wonawinta Silver Mine and Mt Boppy Gold Mine, Cobar Basin.

• Near term production leveraging existing plant with low capex upgrades

• Existing Wonawinta Processing Plant set to return to production in H1 2026.

• Sensitivity Analysis in Table 7 shows varying NPV outcomes from movements

in Spot Gold & Silver prices.

• The Mine Plan is forecast to generate an average EBITDA of A$127 million p.a.

at an average C1 cost of A$34.4/oz silver (including gold credits).

• Mine Plan of 10.9Mt ore, supported by existing Ore Reserves and Mineral

Resources at both Wonawinta and Mt Boppy.

• Pre-production capital costs are estimated at A$26.6 million (including a

contingency of A$2.2 million).

• The Company raised A$15 million in October 2025 and is in the final stages of

reaching a binding agreement for a US$22.5 million debt facility with Nebari

Natural Resources Credit Fund. This ensures Manuka is fully funded to

production and profitability.

• The Wonawinta plant is a highly strategic asset located within trucking

distance of multiple high grade precious and base metals deposits within the

Cobar Basin, providing the Company with significant commercial optionality.

• Ongoing exploration drilling at Mt Boppy targeting high-grade extensions to

gold mineralisation that has historically delivered ~500,000 ounces grading

~15g/t Au. Assays results due during the current quarter.

• Manuka remains fully unhedged, leaving it leveraged to further upside from

movements in precious metals prices.

Manuka’s Executive Chairman, Dennis Karp, commented:


“Manuka is uniquely positioned among junior ASX resource companies as one that is

well set to translate historically high silver and gold prices into substantial near-term

cash returns for the Company and its shareholders.


With our existing 1Mtpa processing plant set to restart within the coming months, debt




Page 2


funding to support the modest capital costs nearing finalisation, and an initial 10-year

production plan demonstrating outstanding economics, Manuka presents both as a

compelling and significantly undervalued investment opportunity.


Project execution is ramping up, and we look forward to providing updates to the

market as we progress towards first production”




Figure 1: Location Wonawinta and Mt Boppy Projects within the Cobar basin.










Page 3


Project Summary


Manuka Resources Limited (ASX: MKR, “Manuka” or the “Company”) is pleased to

announce the updated 10-Year Mine Plan for the Wonawinta Silver and Mt Boppy Gold

Mines, respectively located 80km due south and 50km due east of Cobar, within the

prolific Cobar Basin mining province of New South Wales (Figure 1).


Wonawinta was built by Cobar Consolidated Resources (“CCR”) in 2011 and acquired

by Manuka in 2016. Wonawinta comprises a granted mining lease, existing open pit

mines, an existing 1Mtpa CIL processing plant and associated infrastructure including

approved tailings dams and accommodation facilities (Figures 2 – 5).


Between 2021 and 2023, Manuka intermittently and separately processed silver ore

from Wonawinta ROM stockpiles and gold ore from the Mt Boppy Gold Mine (“Mt

Boppy”) through the Wonawinta processing plant before placing the operation on active

care and maintenance in early 2024.


The Production Plan described in this announcement outlines the upgrading and

recommissioning of the Wonawinta processing plant to enhance throughput and leach

performance and deliver a Production Target that comprises:


• 10.4Mt silver ore from selected stockpiles and 5 open pits located adjacent to

the Wonawinta processing plant; and


• an initial 0.2Mt of gold ore from selected areas of larger 2.2Mt Rock Dump,

Tailings and Stockpile Resource located at Mt Boppy; and


• 0.3Mt of high-grade gold ore from the existing Open Pit at Mt Boppy.

The Production Plan estimates a capital requirement of A$26.6 million to bring the

processing plant into production, of which A$11.4 million will be spent on a new

desliming circuit to remove clays that have previously inhibited mill throughput and CIL

recoveries. The upgrade and refurbishment of the processing plant is scheduled to

commence in Q1 2026 with first production from Wonawinta Stockpiles and Mt Boppy

Stockpiles in Q2 2026. Mining is scheduled to commence in Q3 2026.


Over the 10-Year Mine Plan, the Project is forecast to generate an average

EBITDA of A$127 million p.a. at a C1 cost of A$34.4/oz silver (including gold

credits) resulting in an NPV

8

of A$805 million and an IRR of 1,092%.


The Production Target (Table 1) is supported by Reserves for Wonawinta as well as

Mineral Resource Estimates for Wonawinta in-ground deposits, Wonawinta Stockpiles,

Mt Boppy in-ground deposits and Mt Boppy Rock Dumps, Tailings and Stockpiles

(Tables A2- A6, Appendix A).


The 10.9Mt Mine Plan is underpinned by 6.9Mt Reserves and comprises 8% Measured

Resources, 54% Indicated Resources and 39% Inferred Resources. There is a low level

of geological confidence associated with Inferred Resources and there is no certainty




Page 4


that further exploration work will result in the conversion of Inferred Resources to

Indicated Resources or return the same grade and tonnage distribution.


The Company has determined that the Production Plan presented herein has been

completed at a Pre-Feasibility Study level.


The 10-Year Mine Plan comprises the mining and reclaiming of a total of 10.9Mt ore

containing 19.0Moz of silver and 46koz of gold. Commencing Q2 2026, Existing ROM

Stockpiles located at Wonawinta and Existing Stockpiles located at Mt Boppy will be

reclaimed and processed through the upgraded Wonawinta Processing Plant. Mining at

Wonawinta will commence in Q3 2026 at the existing Manuka open pit, before

progressing to the Belah, Bimble and Pothole Pits and concluding with the existing

Boundary Pit. Mining of the Mt Boppy Open Pit is scheduled to commence in 2028.


Table 1: Production Target


Source

Tonnes

(Mt)

Waste

(Mt)

Ag

(g/t)

Ag

(Moz)

Au

(g/t)

Au

(koz)

Mt Boppy Stockpiles 0.2 - - 0 1.1 7.3

Mt Boppy Open Pit 0.3 7.0 - - 4.17 39.1

Wonawinta ROM Stockpiles 0.2 - 60 0.4 0.07 0.5

Manuka Open Pit 1.4 3.4 61 2.7 - -

Belah Open Pit 1.1 5.5 67 2.4 - -

Boundary Open Pit 5.5 23.9 54 9.6 - -

Bimble Open Pit 1.8 9 57 3.2 - -

Pothole Open Pit 0.4 0.9 41 0.5 - -

Total 10.9 49.7 53.9 19.0 0.1 46.3

Note: Tonnes and Grade are rounded. Discrepancies in calculated Contained Metal are due to rounding.


A new desliming circuit added to the front end of the Processing Plant will be used to

remove the -38μm size fraction from crushed ROM feed to produce a +38μm product

for milling at a rate between 100 and 135tph (0.8-1.0Mtpa).


Milled feed will leach via an existing CIL and elution circuit with metal recovered via zinc

precipitation to a ~70% silver concentrate filter cake with gold credits that will be shipped

on a weekly basis to the ABC refinery in Sydney.


Previous processing of Wonawinta silver ore by the Company delivered a gold

credit of 1 gold ounce per 435 silver ounces over a 9-month period between

May 2022 and February 2023.


No gold credit has been applied to ore mined from the Wonawinta open pits and

therefore represents a significant potential upside to project cashflows over the

Mine Plan should it continue to be recovered.




Page 5



An annual summary of the Mine Plan and forecast cashflows are outlined in Table 2 and

Table 3 respectively.




Figure 2: Location of existing infrastructure, ROM Stockpiles and existing and

proposed open pits at Wonawinta.




Page 6





Figure 3: The existing Wonawinta Processing Plant.




Figure 4: ROM Stockpiles adjacent to the Wonawinta Processing Plant.




Page 7




Figure 5: Existing Manuka Open Pit.




Figure 6: Mt Boppy stockpiles and open pit mine.




Page 8


Table 2: Annual Summary of Mine Plan - Physicals


Calendar Year Units Total 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035

WWTA Open Pit Waste Mt 42.7 1.3 6.4 6.7 3.6 4.0 6.5 6.9 5.1 1.6 0.5

WWTA In-Ground Mt 10.2 0.5 1.3 1.0 1.0 1.1 1.2 0.9 1.4 1.4 0.5

Silver Grade g/t Ag 56.5 51 64 59 60 56 54 55 53 53 61

WWTA Stockpiles Mt 0.2 0.2 - - - - - - - - -

Silver Grade g/t Ag 60.3 60 - - - - - - - - -

Mt Boppy Stockpiles Mt 0.2 0.1 0.1 - - - - - - - -

Gold Grade g/t Au 1.1 1.11 1.07 - - - - - - - -

Mt Boppy Open Pit Waste Mt 7.0 - - 2.2 4.2 0.6 - - - - -

Mt Boppy In-Ground Mt 0.3 - - 0.0 0.1 0.2 - - - - -

Gold Grade g/t Au 4.2 - - 1.25 3.26 5.00 - - - - -

Total Ore Mined Mt 10.9 0.8 1.4 1.0 1.1 1.3 1.2 0.9 1.4 1.4 0.5

Total Silver Mined Moz 19.0 1.3 2.6 1.9 1.8 2.0 2.0 1.6 2.4 2.4 1.0

Total Gold Mined koz 46.3 2.8 4.5 0.1 14.1 24.9 - - - - -

Measured % 8% 40% 5% 0% 8% 5% - 9% 15% 1% -

Indicated % 54% 55% 80% 88% 82% 85% 22% 35% 58% 5% -

Inferred % 39% 5% 15% 12% 11% 10% 78% 56% 27% 94% 100%

ROM Feed Mt 10.9 0.6 1.2 1.1 1.2 1.3 1.2 1.0 1.2 1.2 1.0

Milled / Leached Mt 7.8 0.4 0.9 0.8 0.9 0.9 0.8 0.7 0.8 0.8 0.7

Milled/Leached Silver Moz 16.3 0.7 1.7 1.8 1.9 1.8 1.7 1.6 1.6 1.7 1.6

Recovered Silver Moz 13.2 0.6 1.3 1.5 1.6 1.4 1.4 1.3 1.4 1.5 1.4

Recovered Gold koz 35.2 2.9 2.9 - 4.6 18.2 6.6 - - - -


There is a low level of geological confidence associated with Inferred Resources and there is no certainty that further exploration work will

result in the conversion of Inferred Resources to Indicated Resources or return the same grade and tonnage distribution.




Page 9


Table 3: Annual Summary of Mine Plan – Financials


Calendar Year Units Total 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035

Payable Silver Moz 13.2 0.6 1.3 1.5 1.6 1.4 1.4 1.3 1.4 1.5 1.4

Payable Gold koz 35.2 2.4 3.4 - 4.1 18.2 7.1 - - - -


Silver Price US$/oz


95.0 95.0 95.0 95.0 95.0 95.0 95.0 95.0 95.0 95.0

Gold Price US$/oz


4,800 4,800 4,800 4,800 4,800 4,800 4,800 4,800 4,800 4,800

Exchange Rate A$:US$


0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70 0.70


Net Silver Revenue A$M 1,786 74 169 196 209 192 186 176 192 199 192

Net Gold Revenue A$M 241 17 23 - 28 125 48 - - - -

Govt. Royalties A$M (66) (3) (6) (6) (8) (11) (8) (6) (6) (6) (6)

Net Revenue A$M 1,961 88 186 189 229 306 226 170 186 193 186

Wonawinta Mining A$M (274) (11) (35) (36) (27) (29) (35) (36) (33) (23) (11)

Mt Boppy Mining A$M (84) (4) (7) (18) (35) (19) (2) - - - -

Processing A$M (266) (17) (31) (27) (29) (32) (28) (26) (26) (26) (24)

G&A + Logistics A$M (71) (5) (7) (7) (7) (7) (7) (7) (7) (7) (7)

EBITDA A$M 1,265 52 106 101 131 220 153 101 120 136 145

Pre Revenue Capex A$M - - - - - - - - - - -

Sustaining Capex A$M (70) (29) (5) (6) (6) (1) (7) (2) (5) (8) (0)

Net Project Cashflow A$M 1,196 23 101 95 125 219 147 99 114 129 144

Cumulative Cashflow A$M


23 124 219 344 563 710 808 923 1,051 1,196

NPV

8


A$M

805.3


IRR

%

1,092%


Average EBITDA p.a.

A$M

126.5




Page 10


Financial Assumptions

• A silver price of US$95/oz (~25% below spot of US$118/oz) and a gold price of

US$4,800/oz (~15% below spot of US$5,525/oz) have been used for the base

case financial evaluation.

• An AUD/USD exchange rate of 0.7000 has been adopted reflecting the spot

price.

• A refining charge of A$0.25 per recovered ounce has been applied to both silver

and gold based on typical commercial terms.

• A 4% Government Royalty net of allowable deductions including refining costs,

processing costs and depreciation has been applied.

• The model has been prepared on a real, pre-tax, pre-finance basis. It is noted

however that the Company has an accumulated tax loss position of

approximately A$70 million available to offset against future profits.

• A discount rate of 8% has been applied to calculate NPV.


Project Costs


Operating Costs (Table 4) and Capital costs (Table 5) have been built up from first

principles using a combination of supplier/contractor quotes, recent operating

experience and previous actual costs incurred at Wonawinta and Mt Boppy by Manuka.


Table 4: Operating Cost Summary


Item

LOM Total

(A$M)

A$/oz Ag Unit Rate Unit

Open Pit Mining - Wonawinta 273.8 20.7 5.2 $/t Mined

Open Pit Mining - Mt Boppy 63.0 4.8 8.6 $/t Mined

Stockpile Reclamation - Mt Boppy 2.6 0.2 10.2 $/t Mined

Ore Haulage to Wonawinta 18.7 1.4 38.0 $/t Ore Hauled

Processing Costs 266.0 20.1 34.2 $ Ore Milled

G & A & Logistics 71.1 5.4 9.1 $ Ore Milled

Total Opex 695.2 52.6 89.4 $ Ore Milled

Net Gold Credits (241.0) (18.2) (6.8) $ Ore Milled

Net Opex (C1 incl Gold Credits) 454.3 34.4 82.6 $ Ore Milled





Page 11


Table 5: Capital Cost Summary (A$M)


Item

Pre-

Production

During

Production

Total

Crushing/Screening/Deslime Plant 11.1 0.3 11.4

Ads Tk 1

Repairs/Pumpcell/Platforms/Gantry Crane

0.5 0.0 0.5

Control System Upgrade 0.2 0.2 0.4

Product Room (Filter/Retort) 0.4 - 0.4

Restore Site Services 0.5 - 0.5

Elution (Burners/Regen Kiln/Column) 1.1 0.0 1.2

Dewatering Thickener and Detox Upgrade 0.7 1.7 2.3

Plant Repairs/Restoration 0.5 0.4 0.9

Lab Equipment and Restock 0.3 - 0.3

Camp Repairs, Upgrade and Restock 1.1 - 1.1

Offices/Site Ablutions/Laundry 1.2 - 1.2

Replenish Inventory 0.1 - 0.1

Geo Sample Storage/Technical Hardware

and Software

0.7 - 0.7

Safety, Pre-Employment Medicals and

Uniforms

0.3 0.0 0.3

First Fill Reagents 0.5 0.4 0.9

Tailings Dam Lifts 2.3 33.3 36

Mt Boppy Camp Upgrade

- 1.4 1.4

Mt Boppy Technical Services

- 0.6 0.6

TSF3 Bunding

- 3.1 3.1

Sustaining Capex Provision - 3.9 3.9

Contingency 2.2 0.6 2.8

Sub-Total 23.9 45.9 69.7

Processing Staff Ramp Up 1.4 - 1.4

Admin and Management Staff Ramp Up 1.4 - 1.4

Total Capex 26.6 45.9 72.5







Page 12


Project Sensitivities

Table 7: Project Sensitivity Matrix: NPV (A$M) vs Silver (US$/oz) vs Gold (US$/oz) at 10%

price increments and AUD/USD 0.7000

A$M

Silver Price change (US$/oz)

48 57 67 76 86 95 105 114 124 133 143

-50% -40% -30% -20% -10% 0% 10% 20% 30% 40% 50%

Gold Price Change (US$/oz

)


7,200 50% 303 421 539 656 774 892 1,009 1,127 1,245 1,362 1,480

6,720 40% 286 404 521 639 757 874 992 1,110 1,227 1,345 1,463

6,240 30% 269 386 504 622 739 857 975 1,092 1,210 1,328 1,445

5,760 20% 251 369 487 604 722 840 957 1,075 1,193 1,310 1,428

5,280 10% 234 352 470 587 705 823 940 1,058 1,176 1,293 1,411

4,800 0% 217 335 452 570 688 805 923 1,041 1,158 1,276 1,394

4,320 -10% 200 317 435 553 670 788 906 1,023 1,141 1,259 1,376

3,840 -20% 182 300 418 535 653 771 888 1,006 1,124 1,242 1,359

3,360 -30% 165 283 401 518 636 754 871 989 1,107 1,224 1,342

2,880 -40% 148 266 383 501 619 736 854 972 1,089 1,207 1,325

2,400 -50% 131 248 366 484 601 719 837 954 1,072 1,190 1,307



Base Case Spot Case


Figure 7: Project Sensitivity Chart (NPV vs Project inputs)

400

500

600

700

800

900

1000

1100

1200

-25%-20%-15%-10%-5%0%5%10%15%20%25%

Project NPV

RecoveryWTA Mining CostsCapexGold

SilverMtB Mining CostsProcessing Costs




Page 13


Implementation Schedule


The Company is targeting financial close on the debt facility and a Final Investment

Decision in Q1 2026. The Company aims to be in production by late Q2 2026 (Table 8).


Table 8: Indicative Implementation Schedule


Workstream

2026

Jan


Feb


Mar


Apr


May


Jun


Jul


Aug


Sep


Oct


Nov


De

c


Debt Funding / Final Investment Decision

Re-establish Camp

Re-establish Offices, Stores & Workshop

Refurbish, Modify & Processing Plant

Commission Process Plant

Steady State Production

Construct TSF Lift 3

First Shipment of Silver Concentrate

Mobilise Mining

Mining Commencement


Value Enhancement Opportunities


• Early Production from Mt Boppy Stockpiles: Mt Boppy ore does not require

processing through the proposed new deslime circuit and therefore can be fed

directly into the existing mill. There is an opportunity, given the current gold price,

to commence hauling ore from Mt Boppy Stockpiles to Wonawinta in Q1 2026

and feeding it to the existing plant to generate immediate gold credits.

• Strategic Opportunities in the Cobar Basin: Operating a processing facility

within the Cobar Basin positions Manuka to unlock strategic value. The plant’s

capacity to treat precious metal ores presents opportunities to monetise and

potentially support nearby stranded assets that lack sufficient scale to justify

standalone processing infrastructure.

• Gold Credit from Wonawinta Silver Ore: As previously noted, Manuka has

been generating a modest but meaningful gold credit while processing stockpiles

of Wonawinta silver ore. If gold continues to be recovered consistently throughout

the life of mine, it could deliver a materially positive impact on both project

cashflows and overall valuation.

• Continued Haulage of Mt Boppy Gold Ore: The current Mine Plan incorporates

0.2Mt of gold ore stockpiles from Mt Boppy—a small fraction of the broader 2.2Mt

Resource of mineralised rock dumps, tailings, and stockpiles at the site. Ongoing

identification of high-grade zones within these materials offers the potential to

further increase gold ore feed and enhance cashflow generation.




Page 14


• Further Resource-to-Reserve Conversion: The current Mine Plan utilises

10.4Mt of ore—approximately 25% of the total defined in-ground and stockpiled

Resources at Wonawinta. Additional drilling and sampling could enable the

conversion of further Resources into Reserves, thereby extending mine life and

strengthening project economics.

• Exploration Drilling at Mt Boppy and Pipeline Ridge: Manuka is currently

undertaking a gold exploration drilling program at Mt Boppy and Pipeline Ridge.

Positive results at the high-grade Mt Boppy gold mine or at the shallow Pipeline

Ridge deposit may lead to an increase in Resource tonnes that could be

incorporated into the mine plan at a later point

• Mining Fleet Optimisation: As procurement discussions with mining contractors

advance, there is scope to reassess and refine equipment requirements and

associated costs. These negotiations offer the potential to reduce unit mining

costs and improve operating margins.

• Re-optimisation of Open Pit Design: The Wonawinta and Mt Boppy Open Pit

designs were based on pit shells optimised for a silver price of A$50/oz and a

gold price of A$4,000/oz respectively. Given the significant change in precious

metal pricing since the optimisations were complete, there exist an opportunity

to update pit optimisations to determine whether additional lower grade or deeper

ore can be brought into the mine plan and therefore extend mine life.


This announcement has been approved for release by the Board of Manuka Resources

Limited.


For further information contact:


Dennis Karp

Executive Chairman

Manuka Resources Limited

Tel. +61 412 268 114


About Manuka Resources Limited


Manuka Resources Limited (ASX: MKR) is an Australian mining and exploration

company with key gold and silver assets located in the Cobar Basin (NSW), and offshore

vanadium and titanium bearing iron sands in the South Taranaki Bight of New Zealand.




Page 15


Compliance Statements

Information relating to in-ground Mineral Resources Estimate for the Wonawinta Silver

Mine is extracted from the announcement titled “43% Increase in Measured & Indicated

Resources at Wonawinta Silver Project” dated 1 April 2021 and available to view on the

Company’s website. The Company is not aware of any new information or data that

materially affects the information used to compile the Mineral Resource and all material

assumptions and technical parameters underpinning the estimates in the relevant

market announcements continue to apply and have not materially changed.

Information relating to Mineral Resources Estimate for the Wonawinta Stockpiles, Mt

Boppy Rock Dump, Tailings and Stockpiles, and Ore Reserves relating to the in-ground

Wonawinta deposit, the Wonawinta Stockpiles and the Mt Boppy Rock Dump, Tailings

and Stockpiles is extracted from the announcement titled “Updated Cobar Basin

Production Plan” dated 30 May 2025 and available to view on the Company’s website.

The Company is not aware of any new information or data that materially affects the

information used to compile the Mineral Resource and all material assumptions and

technical parameters underpinning the estimates in the relevant market announcements

continue to apply and have not materially changed.

Information relating to the Mineral Resource Estimate and Ore Reserves relating to the

in-ground Mt Boppy Deposit, is extracted from the announcement titled “29 July 2025

Announcement Clarification” dated 5 August 2025 and available to view on the

Company’s website. The Company is not aware of any new information or data that

materially affects the information used to compile the Mineral Resource and all material

assumptions and technical parameters underpinning the estimates in the relevant

market announcements continue to apply and have not materially changed.




Page 16


Appendix A: Project Implementation Plan


Location and Access


Wonawinta and Mt Boppy are located 100km south and 50km east respectively of Cobar

in central New South Wales (Figure A1).


Access to Cobar from the major regional centre of Dubbo is via 300km of State

highways. Access to Wonawinta from Cobar is via 70km of sealed highway and 30km

of shire and private unsealed roads. Access to Mt Boppy is via sealed highway and local

sealed road. The distance by road between Mt Boppy and Wonawinta is approximately

150km via Cobar.




Figure A1: Location of and access to Wonawinta and Mt Boppy relative to Cobar.




Page 17


Project Tenure


The granted tenements held by Manuka Resources Ltd and its wholly owned subsidiary

Mt Boppy Resources Pty Ltd that comprise the Project Implementation Plan and Mine

Plan are listed in Table A1.


Table A1: Mining Leases comprising the Mine Plan


ID Holder Area Grant Date Expiry Date

ML1659 Manuka Resources Limited 923.8 Ha 23-11-2011 23-11-2032

EL7345 Manuka Resources Limited 59 Units 25-05-2009 25-05-2028

MPL240 Mt Boppy Resources Pty Ltd 17.8 Ha 17-01-1986 12-12-2033

ML1681 Mt Boppy Resources Pty Ltd 188.1 Ha 12-12-2012 12-12-2033

ML311 Mt Boppy Resources Pty Ltd 10.12 Ha 08-12-1976 12-12-2033

GL5848 Mt Boppy Resources Pty Ltd 8.63 Ha 15-02-1968 15-06-2033

GL5898 Mt Boppy Resources Pty Ltd 7.51 Ha 21-06-1972 12-12-2033

GL3255 Mt Boppy Resources Pty Ltd 8.28 Ha 20-05-1926 20-05-2033

GL5836 Mt Boppy Resources Pty Ltd 6.05 Ha 15-06-1965 15-06-2033


Wonawinta


Manuka is the 100% owner of the Western Lands Lease (pastoral lease) on which the

Project Mining lease and Mineral Resource is situated.


To date, there are no option agreements or joint venture terms in place for the Project

nor are there commercial obligations on ground covered by tenure comprising

Wonawinta. No compensation agreements are in place for the Project.


Mt Boppy


The property on which the Mount Boppy mine situated is Crown Land. A Native Title

Agreement is in place with the traditional owners over a mining lease on the western

edge (ML1681, not within the current project area). The Company notes that no land

within the licence area may be classified as sensitive land and the site has been subject

to over 100 years of intermittent mining activity. No further approvals other than those

required under the Mining Act 1992 are required for current operations.


Site Layout


Recent aerial images of the Wonawinta and Mt Boppy Project areas labelled with key

features are shown in Figure A2 and A3.





Page 18




Figure A2: Existing layout of Wonawinta




Page 19




Figure A3: Existing layout of Mt Boppy




Page 20


Mineral Resource Estimates & Ore Reserves


Wonawinta


The Wonawinta Mineral Resource Estimate comprises:

• 38.3Mt of in-ground Mineral Resource with a grade of 41.3g/t Ag and 0.54% Pb;

• a Stockpile Mineral Resource of 0.2Mt with a grade of 60g/t Ag and 0.07g/t Au.


The Mineral Resource Estimate for Wonawinta was previously released to the ASX on

1 April 2021 and remains unchanged. The Wonawinta Stockpile Mineral Resource

Estimate was previously released to the ASX on 30 May 2025 and remains unchanged.


The Wonawinta Ore Reserve comprises:

• a 6.2Mt of in-ground Reserve with a grade of 56.4g/t Ag;

• a stockpile Reserve of 0.2Mt with a grade of 60g/t Ag and 0.07g/t Au.


The in-ground Ore Reserve and stockpile Ore Reserve for Wonawinta was previously

released to the ASX on 30 May 2025 and remain unchanged.



Mt Boppy


The Mt Boppy Mineral Resource Estimate comprises:

• 0.3Mt in-ground Mineral Resources grading 4.12g/t Au; and

• A Rock Dump, Tailings and Stockpile Resource of 2.2Mt at 0.84g/t Au.


The Mt Boppy Mineral Resource Estimate was previously released to the ASX on 5

August 2025 and remains unchanged. The Rock Dump, Tailings and Stockpile

Resource Estimate was previously released to the ASX on 30 May 2025 and remains

unchanged.


The Mt Boppy Ore Reserve comprises:

• A Rock Dump, Tailings and Stockpiles comprising 0.2Mt at 1.1g/t Au.

• An Open Pit in-ground Reserve comprising 0.3Mt at 4.2g/t Au


The Rock Dump, Tailings and Stockpile Ore Reserve for Mt Boppy was previously

released to the ASX on 30 May 2025 and remain unchanged. The Open Pit Ore Reserve

was previously released to the ASX on 5 August 2025 and remains unchanged.


A breakdown of the Ore Reserves and Mineral Resources underpinning the Cobar

Basin Mine Plan are shown in Tables A2 – A6.




Page 21


Table A2: Mine Plan Ore Reserves


Reserve Category

Tonnes

(Mt)

Ag

(g/t)

Ag

(Moz)

Au

(g/t)

Au

(koz)

Probable – Wonawinta In-Ground 6.2 56.4 11.2 - -

Probable – Wonawinta Stockpiles 0.2 60 0.4 0.07 0.5

Probable – Mt Boppy In-Ground 0.3 - - 4.2 39.0

Probable – Mt Boppy Stockpiles 0.2 - - 1.1 7.3

Total 6.9 52.4 11.6 0.22 46.8



Table A3: Wonawinta In-Ground Mineral Resource Estimate


Resource Category Tonnes (Mt) Ag (g/t) Ag (Moz) Pb (%) Pb (kt)

Measured 1.1 47.3 1.65 0.69 7.5

Indicated 12.3 45.5 18.04 0.83 102.8

Inferred 24.9 39.0 31.25 0.39 96.9

Total 38.3 41.3 50.94 0.54 207.2


Table A4: Wonawinta Stockpiles Mineral Resource Estimate


Resource Category Tonnes (Mt) Ag (g/t) Ag (Moz) Au (g/t) Au (koz)

Measured 0.1 61 0.3 0.03 0.1

Indicated 0.1 58 0.1 0.16 0.4

Total 0.2 60 0.4 0.07 0.5



Table A5: Mt Boppy In-Ground Mineral Resource Estimate


Resource Category Tonnes (Mt) Au (g/t) Au (koz)

Measured 0.2 4.01 21.8

Indicated 0.2 4.24 22.4

Inferred - - -

Total 0.3 4.12 44.2


Table A6: Mt Boppy Mineral Resource Estimate – Rock Dumps, Stockpiles & Tailings


Resource Category Tonnes (Mt) Au (g/t) Au (koz)

Indicated 1.4 0.69 30.0

Inferred 0.9 1.09 30.2

Total 2.2 0.84 60.2


Note: Tonnes and Grade are rounded. Discrepancies in calculated values are due to rounding.




Page 22


Metallurgy - Wonawinta Silver Deposit


Eleven different ore lithologies observed within the Wonawinta Resource have been

grouped into five categories - Oxidised Clays, Fresh Clays, Oxidised Limestone, Fresh

Limestone and Fresh Granite. The proportion of each of these categories within the

Mine Plan is shown in Table A7. These groups have been further assigned a

metallurgical classification of either Clay, Semi-Competent and Competent (Table A8).


The metallurgical characteristics of the Wonawinta ore are intrinsically linked to the

mineralogy of the deposit (Table A8). Analysis of drill cores from the Wonawinta deposit,

were investigated by the CSIRO (2022) utilising a hyperspectral core scanner

(HyLogger3) and X-ray computed tomography to determine mineralogy and 3D

structure. Samples of this core with high Ag content and variable Zn and Pb contents

(from assays provided) were further analysed using the Maia Mapper micro-X-ray

fluorescence scanner to examine the Ag mineralogy and distribution. Characterisation

of the supergene mineralisation and transition zone containing clays and dolostones

indicates Ag occurs along planar features within the cores,and shows that Ag is

transported along cracks within the clay matrix. Pb accumulations are not spatially

correlated with the Ag but, XRF imaging shows they are associated with Mn-oxide and

goethite development in largely clay-rich host rocks. Ag occurs as Ag-halide minerals,

iodargyrite and embolite (a mixture of chlorargyrite and bromargyrite). In some samples

it also occurs with Hg in a phase that preliminary data suggest contains S and Cl but

more work is required to define what this mineral is.


At the top of the underlying dolostone sequence, Ag occurs in clays and goethite

developed in micritic layers and filling vugs in the dolostone. Thermodynamic modelling

shows that Ag mineralogy is controlled by oxidation state within the groundwater, and

that halides can be sourced from the groundwater. Clay mineralogy is controlled by

weathering extent and acidity, while the other economic elements (Zn and Pb) are

deposited in secondary oxide phases and as carbonates respectively.


From a mining perspective the Ag mineralisation is classified into clay, variably oxidised

limestone and dolomite, and fresh limestone and dolomite.


Table A7: Proportion of each Lithology included in the Mine Plan


Lithology Met Class

Tonnes

(Mt)

Oxidised Clays

Clay

5.6

Fresh Clays 2.0

Oxidised Limestone Semi Comp. 1.6

Fresh Limestone

Competent

1.1

Fresh Granite 0.3

Total


10.8




Page 23


Table A8: Stratigraphy and Lithology descriptions for Wonawinta


Ox.

State

Lithology

Met.

Class

Description

Oxidised


Sandstone SST

Clay

S rich (sulphates?) Fe rich fine grained brown sandstone only found in one hole in Bimble in middle of iron rich

clay

Dolomitic and

Limestone

Clays

DOL-CLY +

LST-CLY

High Ca, brown to dk grey clay, well weathered occurring just above, or occasionally within dolomite or

limestone

Light Coloured

Clays

CLY-L

Occurs at the top of drill holes, below soil and silcrete, white, cream, light pink, light grey, light brow, light yellow

etc., low in Fe, Ca and S, except for odd gypsum layer which usually has no silver

Iron Rich Clays CLY-FE

Red, brown, orange with high Fe, low Ca, variable S. Can contain significant proportion of harder material

(manganiferrous ironstone and ferruginous siltstone) occurring usually between light coloured clays and

limestone.

Ferricrete FECR

Found below or within Fe rich clays, and adjoining limestone. Hard, shades of red or brown with highest Fe on

site and low Ca. Can be high Mn (pyrolusite).

Granite OX-GRT Low Ca, S and Fe, medium sized quartz grains occurring at base of drill hole in one hole in Belah

Oxidised

Dolomite and

Limestone

OX DOL +

LST

Semi-

Competent

Highly variable in colour with varying amounts of weathering, Fe, S and quartz-carbonate alteration. Found at

base of drill holes with high Ca. Also known as saprolite (totally oxidised) or saprock (partially oxidised).

Fresh


Dark Clays CLY-C Clay

Grey to black occurring usually below light-coloured clays, sometimes in deeper sections above dolomite and

limestone. Highly variable S sometimes highly elevated.

Fresh Dolomite

and Limestone

FRSH DOL

+ LST

Competent

Grey to dark grey showing no signs of oxidation occurring at base of observed sequences with high Ca and

variable S, sometimes elevated.

Mudstone MDST

Occurring either within or below dark clays often contain visible pyrite and generally dark grey to black but can

occur as shades of olive and pale yellow to brown. Higher S than dark clays and more Fe than iron rich clays.

Low Ca.

Granite FR-GRT Occurring below base of oxidation and assumed to contain sphalerite, galena, silver sulphides and sulphosalts.




Page 24


Deslime mass and silver metal recovery to slimes derived from the -38μm size fraction

of 6 samples collected from crushing/screening trials conducted on the Wonawinta

stockpiles is shown in Figure A4.



Figure A4: Silver/Mass Deportment for -38μm fraction of Wonawinta ore.


Average Leachwell leach recoveries achieved on test work undertaken on more than

600 samples from four pits for various ore lithologies (Table A9).


Table A9: Distribution of Leachwell testwork samples versus lithologies and pits


Met Class Clay

Semi

-

Competent


Competent


LITHO


CODE


SST


DOL

-

CLY +

LST

-

CLY


CLY

-

L


CLY

-

FE


CLY

-

C


FECR


OX

-

GRT


OX DOL + LST


FRSH DOL + LST


MDST


FR

-


GRT


Total


Belah - 5 18 21 25 12 3 5 - - - 89

Bimble 3 5 5 56 46 3 - 9 1 - - 128

Boundary - 6 9 51 61 5 - 30 1 27 - 190

Manuka - 7 16 30 4 4 - 144 19 4 - 228

Total 3 23 48 158 136 24 3 188 21 31 - 635

Avg Rec. 96% 84% 67% 93% 74% 46% 57%










Page 25


Metallurgy – Mt Boppy Gold Deposit


The ore from Mt Boppy is to be sourced from a combination of screened surface dump

and stockpile material by previous mining operations, and open pit ore from planned

dewatering and pushback from the existing open pit. The gold mineralisation at Mt

Boppy is hosted in quartz and quartz-carbonate veins, stockworks and breccias with

pyrite (FeS) the dominant sulphide with subordinate sphalerite (ZnS). The gold

deportment is mostly as very fine grains (~25 μm or finer) hosted within pyrite.


Gold CIL leach recovery for Mt Boppy Stockpile and Open Pit Ore is based on previous

operating experience from when gold ores from Mt Boppy were processed at

Wonawinta by Manuka Resources (Figure A5).


Figure A6 below shows the relationship between feed grade and tail grade for Mt Boppy

ore processed at Wonawinta. It shows that tails below 0.38 g/t gold were never achieved

and a reasonable trend can be shown for tailings grade based on feed grade for feed

grades > 1.3g/t gold. Expected tailings grade is 0.38 g/t for feed grades <1.3g/t gold

and =0.1855*(feed grade g/t gold) + 0.168. Expected gold recovery can then be

calculated from the planned feed grade and predicted tail grade.



Figure A5: Recoveries achieved during the prior processing of Mt Boppy Ore via the

Wonawinta processing plant by Manuka.




Figure A6: the relationship between feed grade and tail grade for Mt Boppy ore processed

at Wonawinta.

0%

20%

40%

60%

80%

100%

0.0

1.0

2.0

3.0

4.0

5.0

Apr-20

May-20

Jun-20

Jul-20

Aug-20

Sep-20

Oct-20

Nov-20

Dec-20

Jan-21

Feb-21

Mar-21

Apr-21

May-21

Jun-21

Jul-21

Aug-21

Sep-21

Oct-21

Nov-21

Dec-21

Jan-22

Feb-22

Jun-23

Jul-23

Aug-23

Sep-23

Oct-23

Nov-23

Dec-23

Recovery

Grade (g/t Au)

Feed (g/t)Tail (g/t)Rec’y (%)

y = 0.1855x + 0.168

R² = 0.8024

-

0.20

0.40

0.60

0.80

1.00

1.20

- 0.50 1.00 1.50 2.00 2.50 3.00 3.50 4.00 4.50 5.00

Tailings Grade Au (g/t)

Feed Grade Au (g/t)




Page 26



CIL Gold recoveries for the Mt Boppy Stockpiles through the Wonawinta Processing Plant are

based on bottle roll test results summarised in Table A10.


Table A10: Gold Recoveries of Mt Boppy Stockpiles


Source

Observed

Recovery

Testwork

Basis

Predicted

Recovery

ROM Stockpiles (+22mm) 59% WWTA Bottle Roll 75%

Oxide Area 1B 0-2 & 2-6m 85% WWTA Bottle Roll 75%

Old tailings ROM Pad 50% WWTA Bottle Roll 50%

Fresh Main Dump A4 56% Gekko Bottle Roll 60%

Fresh Main Dump A6 60% Gekko Bottle Roll 60%

Total 64% 68%


The geometallurgical model developed for the Mine Plan is outlined in Table A11.


Table A11: Geometallurgical Model for the Project


Lithology

Deslime CIL

% slimes rec. % rec. %

Clay (Silver) 36% 84% 90%

Semi Competent (Silver) 23% 86% 75%

Competent (Silver) 6% 94% 50%

Mt Boppy Open Pit (Gold) 0% 100% 69-79%

Mt Boppy Stockpiles (Gold) 0% 100% 68%

Wonawinta Stockpiles (Gold) 0.23% gold oz recovered per Ag oz recovered


A negligible Mt Boppy ore slimes content is based on previous operating experience.


A 90% CIL recovery for clay ore is based on the Leachwell data with some modifications.

Laboratory leach tests with carbon showed improved recoveries with early leach tests

indicating “pre-robbing” behaviour with silver re-adsorbing onto clays and other “preg-

robbing” material. Removal of slimes will improve adsorption.


Assaying and metallurgical testwork on the Wonawinta ROM stockpiles have confirmed

a low tenor recoverable gold credit. It has therefore been deemed reasonable to model

gold being produced from the Wonawinta ROM Stockpiles at a ratio of 0.23% ounces

of gold per silver ounce as it had for the 287kt previously processed by the Company.






Page 27


Mining - Wonawinta


Independent consultants Mining Associates were engaged to undertake pit

optimisation, pit design and mine schedule for the in-ground Wonawinta deposits. This

work was carried out utilising the Deswik CAD package and the SPRY scheduling

package. Source, destination and haulage scheduling were undertaken in SPRY.

Deswik’s optimisation module uses the Pseudoflow optimiser algorithm.


The Life Of Mine Plan prepared by Mining Associates was optimised, designed and

scheduled using Measured, Indicated and Inferred Mineral Resource categories and

used as the basis for financial forecasts presented in this announcement; and


Pit Optimisation


A mining block model was created by regularising the Wonawinta Resource Block

model to a standard minimum unit size of 5m x 10m x 2.5m (xyz) to generate a block

model suitable for pit optimisation purposes. Ore losses and mining dilution were

incorporated into the regularisation process and resulted in a reduction of 2.5% silver

ounces versus the Resource block model.


For the Manuka and Boundary pits that have been previously mined, pit slopes were

set as follows:

• the first 3 benches to have 10m bench heights, 65-degree batter angles and 5m

berm widths.

• lower benches (assuming in rock) to have 10-20m bench heights, 70-degree

batter angles and 5m berm widths


A conservative design approach was adopted to pit slope in Belah, Bimble and Pothole

pits (which are yet to be mined) based on previous geotechnical studies (Table A12).


Table A12: Geotechnical parameters adopted for the Belah, Bimble and Pothole pits.


Pit Depth (m)

Batter Height

(m)

Bench Face

Angle (°)

Berm Width

(m)

Overall Slope

Angle – Toe to

Crest (°)

20 10 65 7 48

30

10 65 11 40

15 55 14 40

40

10 65 13 35

15 55 14 35

50

10 65 14 32

15 55 15 32

60

10 65 14 31

15 55 19 31




Page 28


The marginal cut-off grades used for pit optimisation were estimated on an individual

block by block basis using the processing costs, processing recoveries (based on the

assigned geometallurgical classification of the block), G&A costs and royalty costs.


Marginal cut-off grades used to initially determine ore and waste blocks in the pit

optimisation process are outlined in Table A13.


Table A13: Indicative Marginal Cut-Off Grades for Pit Optimisation


Ore Type

Oxidised

Clay

Fresh

Clay

Oxidised

Limestone

Fresh Limestone/

Granite

Mining Cost (A$/t) 3.50 3.50 3.50 3.50

Process/ G&A (A$/t) 27.39 29.17 27.39 36.26

Recovery (%) 75.6% 79.2% 64.5% 51.7%

Marginal Cut-Off 23.3 g/t Ag 23.7 g/t Ag 31.1 g/t Ag 45.1g/t Ag


*Based on a Silver price of A$50/oz, payability of 99.7%, refining charge of A$0.25/oz and Royalty of 2.4%


The mining block model was subsequently coded with the revenue and cost parameters

shown in Table A14 and an iterative process in Pseudoflow to identify the optimal pit

size for mine design. A pit specific mining cost was applied to account for Manuka’s plan

to initially mine on a dry hire basis (Manuka and Belah Pits) before transitioning to an

owner-operator model (Bimble, Pothole and Boundary Pits).


Table A14: Revenue and Cost assumptions used for pit optimisation and design


Revenue Factors Value Units

Silver Price 32.5 US$/oz

Exchange Rate 0.65 A$:US$

Silver Price 50 A$/oz

Royalty 2.4% Ad Valorem

Refining Charge 0.25 A$/ounce

Ag Payability 99.7% Recovered Ounces

Operating Cost Assumptions

Drill & Blast 1.79 $/t blasted

Grade Control 1.63 $/t ore

Mining – Dry Hire 10.15 $/BCM moved

Mining – Owner Operator 3.23 $/BCM moved

Fixed Processing Costs 10.34 $ per annum

Variable Processing Costs 2.17 $/t crushed

plus

13.45 $/t milled




Page 29


Mine Schedule and Pit Designs


The Life of Mine Plan comprises mining of two existing open pits (Manuka and

Boundary) and 3 new open pits (Belah, Bimble and Pothole) located at Wonawinta. Life

of Mine Plan mine scheduling was undertaken in the Micromine SPRY software

package. Source, destination and haulage scheduling was completed on the Life of

Mine Plan pit design.


The Life of Mine Plan (Figure A7) comprises 59% Measured and Indicated Resources

with 41% being sourced from Inferred Resources. Given the larger portion of Inferred

Resources sourced from the Boundary pit, it was scheduled at the end of the Life of

Mine Plan. Manuka plans to undertake Grade Control drilling that will also upgrade the

Inferred Resources to Indicated Resources well in advance of mining taking place.




Figure A7: Life of Mine Plan Mining Schedule and Resource classification


It is noted that a portion of the Boundary pit included in the Life of Mine Plan extends

beyond the current mining lease. The Company is scheduling the required regulatory

approval process to expand the Mining Lease ahead of entering this portion of the pit

before it is scheduled to be mined in the final years of the Life of Mine Plan.


Mining Operations


Mining at Wonawinta (including Load & Haul and Drill & Blast) will be undertaken by an

experienced mining contractor under technical guidance and supervision by Manuka

staff. It will be completed on a day and night shift roster (~8Mtpa) except for periods in

Production Years 1, 4,5,8, 9 and 10 where only a dayshift will be employed.




Page 30



Figure A8: Life of Mine Pit Designs






Page 31


Open Pit Mining – Mt Boppy


The Resource model was regularised to a standard selective mining unit of 2.5m x 5.0m

x 2.5m. Mining dilution and ore losses were accounted for during the standardisation

process, resulting in a 7.8% reduction in gold ounces. A marginal cut-off grade of 1.0g/t

based on a A$4,000/oz gold price was used for pit optimisation. Optimisations were run

at different gold prices to determine the production target sensitivity to changes in the

gold price. There were only minor changes to the production target for gold prices down

to A$3,500/oz.


The proposed design is a cutback that focusses on the southern and central portions of

the existing pit (Figure A9). Overall pit depth increases by 80m, the equivalent of four

benches. The pit design has a single 10m access ramp with four passing bays of 16.5m

width. Geotechnical parameters including slope angles were adopted assuming that

ground conditions that will be experienced are similar to those in the exposed current

pit. A number of geotechnical risks have been identified that will need to be either further

investigated prior to mining or managed throughout the mining process.


There is currently ~500ML of water at the bottom of the current pit from the previous

flooding event. This water will need to be pumped out before mining in the cutback can

take place. At 83 litres per second there is approximately 2.5 months of pumping

required to dewater the pit.


Mining will initially target a rate of 4.5Mt per annum whilst mining predominately waste

material before tapering off as high-grade ore is exposed (Figure A10). Mt Boppy

operations first operate two shifts per day for 17 months, with a forecast 90% availability

and 80% utilisation. When working room reduces towards the base of the pit, there is

eight months of mining on single shifts and utilisation is reduced to 40% and then to

20%, to allow the drill-blast-load-haul cycle to take place in a confined area.


Mining at Mt Boppy (including Load & Haul and Drill & Blast) will be undertaken by an

experienced mining contractor under technical guidance and supervision by Manuka

staff. Mined ore will be stockpiled on site at Mt Boppy and then hauled 150km to

Wonawinta for processing at a rate of ~13kt per month (Figure 12). A contractor has

supplied





Page 32






Figure A9: Cross-Section looking west (Top) and north (Bottom) showing through the

Mt Boppy Orebody showing orebody shape and grade versus the existing, optimised

and designed pit outlines.




Page 33



Figure A10: Mt Boppy Open Pit Cutback Production Target



Figure A11: Resource Classification of the Production Target




Figure A12: Stockpile and Ore Haulage Schedule



-

1.00

2.00

3.00

4.00

5.00

6.00

7.00

-

50,000

100,000

150,000

200,000

250,000

300,000

350,000

400,000

450,000

147101316192225283134

Gold Grade g/t

Ore tonnes

Ore Mined tWaste Mined tGold Grade g/t

0%

20%

40%

60%

80%

100%

147101316192225283134

% Ore Tonnes Mined

Measured TonnesIndicated Tonnes

-

25,000

50,000

75,000

100,000

125,000

150,000

-

15,000

30,000

45,000

1357911131517192123252729313335

Mined Ore Stockpile

Ore Hauled to Wonawinta

(t)

Closing ROM StockpileOre Hauled to WON




Page 34


Stockpile Reclamation – Mt Boppy


Selected material (Table A15) from the Mt Boppy Stockpile and Rock Dump Resource

has been initially identified for haulage to and processing at Wonawinta as a supplement

to the silver ore from Wonawinta ROM Stockpile and open pit material. Approximately

157kt of material is suitable for direct haulage to Wonawinta. A further 102kt of material

will be screened and upgraded prior to haulage to Wonawinta.


Mt Boppy gold ore has previously been hauled to and processed at Wonawinta by

Manuka at rates up to 125 t/hr with gold recovery typically 75-77% via either

electrowinning cell or by zinc precipitation when silver levels in the feed were high.


Table A15: Selected Mt Boppy material included in the Mine Plan (in order of processing)


Source Tonnes fraction Mass Product Grade Au oz

ROM Stockpiles (+22mm) 84,895 >22mm 100% 84,895 1.11 3,030

Oxide Area 1B 0-2 & 2-6m 60,317 Total 100% 60,317 0.85 1,640

Old tailings ROM Pad 12,112 <2mm 100% 12,112 2.42 942

Fresh Main Dump A4 76,086 <22mm 47% 35,677 0.99 1,130

Fresh Main Dump A6 25,990 <22mm 57% 14,749 1.10 520

Total 259,400



207,750 1.09 7,264

Indicated 247,161 195,510 1.10 6,929

Inferred 12,239 12,239 0.85 334


Stockpile reclamation and screening will be performed by contractors with Manuka

providing on-site supervision and auxiliary vehicles.



Haulage to Wonawinta


Ore mined from the Open Pit and reclaimed from the stockpiles and rock dumps will be

hauled ~150km to Wonawinta for processing. Haulage trucks are typically a B-Double

configuration capable of a 55t payload. The trailers will be covered and self-tipping. Ore

haulage rates are based on four trucks operating 6 days per week. Two and a half trips

per day are planned for each truck with breaks during the day to ensure the task is

performed safely and within current national vehicle (fatigue management) guidelines.

Ore haulage drivers would be accommodated either at the Wonawinta or Mt Boppy

camp at Manuka’s cost.





Page 35


Previous Production via Wonawinta Process Plant


The Wonawinta Plant (Figure A13) was originally built by Cobar Consolidated

Resources (CCR) in 2012. Black Oak (BOK) acquired the Wonawinta operation in

September 2014. Manuka Resources Limited (MKR) acquired Wonawinta in June 2016.



Figure A13: Layout of the existing Wonawinta Processing Plant


Since its construction in 2012, approximately 1.7Mt of Silver Ore has reported to have

been milled at an average grade of 95g/t Ag for the recovery of approximately 3.2Moz

of silver for an average recovery of 63.3% (Table A16).


The original plant by CCR was designed to dry attrition ore via log washer before

screening to separate a -2mm fines fraction for downstream processing. Log-washer

undersize, typically containing >100g/t Ag, was pumped over a 1mm trash screen

before cyanide leaching and adsorption of soluble silver onto carbon, followed by

elution, zinc precipitation and filtration to produce a concentrate which was retorted for

mercury removal and smelted to produce silver bars.


It was quickly established that trash screen oversize comprising 15-20% of total feed

routinely assayed >100g/t Ag and at times >200g/t Ag indicating higher grade

mineralisation in the coarser size fractions. Screened +10mm log washer oversize was

also found to contain ~100g/t Ag and this was stockpiled for future processing.


A mobile jaw crusher was subsequently commissioned to improve silver deportment to

the finer -2mm fraction which was estimated at 70%. Leach feed grades were frequently

below those of trash screen oversize grades confirming extensive silver mineralisation

in the coarser particles. Larger 3mm lower deck log washer screens were subsequently

employed reducing log-washer oversize but increasing trash screen oversize which




Page 36


resulted in more frequent downtime due to frequent bogging of slurry transfer lines and

blinding of intertank screens.


BOK installed an 1800kW ball mill to further liberate silver from harder dolomitic

limestone. Silver recoveries of around 70% were reported against a target of 85%. Low

silver production was attributed to ‘unexpected’ ore types and ‘sub-optimal’ plant

practices and procedures. Silver ore was processed from March to September 2015

before a brief period of processing Mt Boppy gold ore in November 2015. MKR

processed open pit gold ore from Mt Boppy over the period April 2020-March 2022

(560kt @ 3.03 g/t Au for 41Koz Au recovered).


MKR processed silver ore stockpiles through the Wonawinta plant from April 2022

through to January 2023, During the period, the Company completed a series of trial

modifications and innovations to the Wonawinta processing facility including the

introduction of a temporary deslime circuit to remove deleterious fine clays from the ore

and increase feed grade into the CIL circuit. Metallurgical test work, confirmed by

production data, saw an uplift in silver feed grades to the leach circuit by up to 100%.

Higher grades and lower clays increased silver loadings onto carbon.


The Company received a rebate of A$1.07M in relation to the trial production program

under the Government’s R&D tax incentive scheme


Table A16: Historic production of Silver ore at Wonawinta


Period Units

CCR

(Mar 2013 to

Mar 2014)

BOK

(Mar 2015 to

Sep 2015)

MKR

(Apr 2022 to

Jan 2023)

TOTAL

Ore Milled tonnes 885,707 483,671 287,000 1,656,378

Milled Grade Ag (g/t) 100.5 95.8 75.9 94.9

Recovery % 61.3% 71.2% 56.3% 63.3%

Silver

Recovered

oz 1,755,019 1,044,963 381,873 3,181,855


Historical Gold Production from Wonawinta ore


During Manuka processing of Wonawinta silver stockpiles, it was observed that there

were gold credits in silver doré and silver concentrate shipments despite only low levels

of gold being identified in previous drilling and assaying of the orebody. Approximately

1,077oz of gold was recovered along with 381,873oz of silver whilst processing 287,000

tonnes of Wonawinta stockpiled silver ore.


Figure A8 plots the ratio of contained gold to contained silver for each delivery to the

refinery as assayed by the refinery. The cumulative average ratio over the period was

calculated to be 0.23%.






Page 37


Historical Gold Production – Mt Boppy


At Mt Boppy Underground mining from 1897 to 1923 extracted in the order of 1 million

tonnes grading on average 16 g/t Au ore to a maximum depth of about 230m (McQueen

2005). Open pit mining first occurred between 2002-2005 when Polymetals mined to a

maximum depth of 80m extracting ~500kt at 5g/t.


Under Manuka’s ownership, open pit mining at Mt Boppy recommenced between April

2020-February 2022. Over 560kt of ore at approximately 3g/t was mined from the pit

and hauled to Wonawinta for processing before a severe weather event caused flooding

in the pit, instability in the pit wall and the subsequent cessation of mining activities.

During the period June-Dec 2023 Manuka processed screened ROM pad and rock

dump material totaling 151kt which was hauled to Wonawinta for processing.


Production results under Manuka is summarised in Table A17.


Table A17: Production of Mt Boppy ore through the Wonawinta plant by Manuka.


Period Units Apr 20 - Feb 22 Jun 23 - Dec 23 Total

Ore Mined / Milled tonnes 560,429 150,760 711,189

Head Grade Au (g/t) 3.03 1.45 2.697862

Recovery % 75% 70% 75%

Recovered Ounces oz 41,219 4,944 46,164


Processing Plant Upgrade Design Basis


The basis for designing the updated flowsheet for processing of Wonawinta silver ore

is to apply the learnings from the previous attempts at silver recovery by continuing the

successful practices and modifying those which proved detrimental or unsuccessful.

The key learning is that the clays or slimes, which are typically of lower silver grade than

the coarser fractions, contribute to numerous operational issues which adversely impact

overall silver recovery and reliable production, and they should be removed from the

processing stream.


Viscous slurries created from slimes prevented effective classification and contributed

to poor slurry flow through the adsorption tank inter-tank screens resulting in blocked

screens and inability to maintain required carbon levels in the adsorption tanks. Screen

blockages cause the adsorption tanks to overflow losing carbon to the bund below, and

cleaning of the screens allowed any carbon to escape the tank and flow into the

subsequent tank, thereby mixing the carbon resulting in a flatter carbon loading profile

which does not assist adsorption or recovery.


In addition, the fine slimes contributed to poor loading capacity of the activated carbon,

presumably by physically blocking access to adsorption sites within the carbon resulting

in soluble silver losses. High loadings of lead were observed on the carbon, however

leach solutions contained little or no lead in solution suggesting that the lead in the

carbon was physically attached and not chemically adsorbed. No chemical treatment

tested resulted in improvements in activity by removing these foulants.




Page 38


Removing the clays also removes some of the original feed mass but with only a small

proportion of the contained silver. Silver mineralisation is more abundant in the +45μm

to 700μm fractions with lower grades reporting to the finer fractions. No other changes

to the flowsheet are required as the removal of fines should alleviate any previous

operational issues that impaired reliability or recovery.


Flowsheet


The proposed flowsheet is a combination of some of the original CCR plant used in the

previous three attempts at silver ore processing at Wonawinta and new equipment to

be installed based on learnings gained from those previous attempts (Figure A14).


Crushing, Screening and Desliming


Crushing comminution data was initially determined to have an average Impact

Crushing Work Index of 5.4kWhr/t for (Friable) and 4.7kWhr/t for (Limestone) for the

twenty samples tested for each composite. This work was conducted on <10mm

material and cannot be compared to a traditional Bond Crushing Work Index. The

maximum work index recorded on single samples was up to 12.8kWhr/t. A design

crushing work index of 10kWhr/t has been used.


ROM stockpile reclaim ore is loaded by a 980 Loader or similar, at a rate of up to 180t/hr

onto a fixed 600mm grizzly located above a crusher feed hopper. Grizzly oversize will

be cast aside and broken with a rock breaker as required.




Figure A14: Schematic of the Wonawinta Flow Sheet showing elements of the existing

plant and the proposed upgrades




Page 39





Figure A15: Example of the proposed modular Jaw Crusher




Grizzly undersize is fed over a grizzly feeder with +65mm oversize feeding a 110kW jaw

crusher (Figure A15). The Jaw crusher discharge and -65mm undersize feed a 200t/hr

capacity log washer. Coarse, deslimed +6mm product from the log washer is fed to a

220kW cone crusher before further screening along with jaw crusher product at 15mm

prior to milling. The 15mm screen oversize is returned to the cone crusher which is

protected by a fixed magnet. Cone crusher operation is assisted by a feed hopper and

variable speed controller.


The -6mm fine fraction containing the clays from the log washer is sent to a deslime

circuit where the aim is to remove the -38μm slimes. The -6mm stream is fed to the first

of two desliming units where the -75μm fraction is removed and the +75μm/-6mm

dewatered fraction sent to the mill feed conveyor. The -75μm fraction is sent to the

second desliming unit where the -38μm fraction is removed and pumped to the tailings

feed hopper with a new pumping arrangement. The +38μm/-75μm fraction is also

dewatered and sent the mill feed hopper.


Milling


The combined +38μm/-75μm, +75μm/-6mm and -15mm screen undersize are conveyed

to the 1800kW ball mill feed chute. Collectively the mill feed will be ground to p80 =

75μm or finer at a rate of approximately 120 t/hr depending on the slimes/coarse ratio

and amount of deslimed material rejected (Figure A16). The 400kW secondary ball mill

will be run in parallel with the primary ball mill, fed from a fraction of hydrocyclone

underflow, to maintain the throughput and achieve as fine a grind as possible.




Page 40


Mill discharge is classified in a hydrocyclone cluster. Classified slurry is fed over a trash

screen to remove wood, plastic and other contaminants before pumping to the existing

leaching and adsorption circuit.


Hydrated lime is dosed onto the mill feed conveyor from a storage silo to a set pH level

to provide protective alkalinity and ensure most of the cyanide added is kept in solution

and does not evolve as cyanide gas. Liquid oxygen is dosed into the discharge of the

leach feed pump to oxidise any cyanide consuming mineralisation and provide adequate

oxygen for the leach reaction.


Leaching and Adsorption


Ground slurry from the grinding circuit is pumped to the first of two leach tanks where

cyanide is added to a set concentration for optimal leaching. Leached slurry then

gravitates to the first of five carbon adsorption tanks where leached silver is adsorbed

onto the carbon in five stages (Figure A17). The flow of carbon is counter-current to the

slurry and is pumped daily from tank to tank.


Each day a twelve-tonne batch of loaded carbon from the first adsorption tank is

pumped over a screen to wash the slurry from the carbon and dewatered carbon is

added to the loaded carbon hopper to commence the elution cycle. A similar amount

of carbon is then pumped from tank to tank to restore the inventory in each tank and the

barren carbon from the previous elution is then added to the last adsorption tank.




Figure A16: Existing 1800kW Ball Mill




Page 41





Figure A17: Existing CIL and Adsorption Tanks and Elution Column


Leached slurry exits the last adsorption tank and is fed over the carbon safety screen

to catch any carbon that may have escaped from the last tank. Slurry passes through

the screen to the final tailings hopper where ferric chloride is added to detoxify residual

cyanide as it is pumped to the tailings dam.


Elution, Zinc Precipitation, Concentrate Filtering and Retorting


The final part of the process is where loaded carbon is stripped of contained silver, and

a silver concentrate produced after zinc precipitation, filtering and retorting to remove

mercury.


The loaded carbon is first washed in dilute hydrochloric acid to remove acid soluble

contaminants on the carbon and then it is washed in potable water before transferring

to the elution column. A caustic and cyanide solution is heated to approximately 110°C

and then pumped through the elution column removing adsorbed silver into a

concentrated solution which is then mixed with zinc to precipitate a silver concentrate

prior to filtering in existing pressure filters. Filtered concentrate is then heated in a retort

furnace to volatilise and collect any contained mercury before the concentrate is packed

in drums and transported to the refinery.


Future Flotation Optionality


Implementation of a flotation circuit to treat sulphidic base metals ore at Wonawinta is

relatively simple with plenty of space to accommodate the flotation and dewatering

circuits required to produce a flotation concentrate. The fine mineralisation would benefit

from Jameson Cells with their very fine bubble size and their footprint is quite small. A

regrind mill already exists on site. Concentrate logistics are provided by nearby rail

loading facilities at Cobar and Hermidale.




Page 42


Commissioning


Process Plant Commissioning will be managed by the Project Manager with assistance

from the MKR Owners Team and mechanical and electrical installers, process control

contractors and OEM support. Commissioning will occur in 5 stages:


• Equipment Installation Verification Confirm that all mechanical equipment is

correctly installed—alignment, fasteners, guards—and that electrical

installations (cabling, terminations, earthing) meet specification.


• Energisation Apply and verify power to all motors, drives, and control panels,

conduct insulation and safety tests, and ensure all electrical systems operate

reliably under no‐load conditions.


• Wet Commissioning Introduce and circulate water through every process

circuit. Inspect for leaks, confirm pump flow rates, and validate screens,

cyclones, and other water‐handling equipment for proper operation.


• Slurry Commissioning Feed a slurry of solids and water at near‐design

concentrations and flow rates. Calibrate and test sensors, valves, and

throughput controls, and verify mass‐balance and performance across each

unit operation.


• Performance Assessment & Handover Execute acceptance tests to confirm

that throughput, recovery, power consumption, and other key performance

metrics meet contractual guarantees. Resolve any remaining punch‐list items,

compile “as‐run” documentation, and formally hand over the plant to operations.


It is planned to commission the plant using ore from existing ROM stockpiles. A Mineral

Resource Estimate and Reserve of 0.2Mt at 60g/t Ag and 0.07g/t Au has been assigned

to the existing ROM stockpiles at Wonawinta. Further details of the ROM Stockpile

Resource are discussed in Appendix C.


The first stockpiles to be processed will be the remnant Mt Boppy -22mm gold ore

stockpiles located closest to the ball mill feed hopper. This ore can be fed directly into

the ball mill via the feed hopper as it is already crushed and screened.


A blend of stockpiles will be used for initial crushing, screening and deslime circuit

commissioning. The blend would start on more competent material to test the crushing

and screening capability first before introducing more fines to then test the deslime

circuit capability.


It is anticipated to take between 3 and 4 months to complete process plant ramp up and

deplete the existing ROM stockpile and in doing so prepare the ROM Pad for the

commencement of Mining at Wonawinta and receipt of hauled Ore from Mt Boppy


Mt Boppy gold ore would be processed in conjunction with the Wonawinta silver ore

mine from open pits located at Wonawinta as an incremental part of the feed blend using

the upgraded process plant design described above.




Page 43



The nameplate design capacity of the proposed new crushing and screening circuit is

180t/hr and can accommodate the expected maximum feed rate of up to 170t/hr.


The planned 12,698 t/month of gold ore equates to an incremental milling rate of 19t/hr

(assuming 100% mass recovery of Mt Boppy ore through the deslime circuit). With

100t/hr of Wonawinta silver ore this would total 119 t/hr of mill feed. The nameplate

capacity of the grinding circuit is 135 t/hr and has previously been run up to 125 t/hr on

Mt Boppy gold ore screened to <22mm.


Stockpile Management and Ore Blending


The ROM stockpile covers an approximate area of 70,000m

2

of which 300m x 200m or

60,000 m

2

is available for ROM ore stockpiling and blending, close enough to the

proposed jaw crusher feed bin to comfortably feed the circuit with a single CAT 980

loader or similar.


Ore will be stockpiled based on ore lithology, namely clay, pyritic clay, semi-competent

and competent ore. Pyritic clays will be stockpiled close to the ROM until a suitable

processing strategy is identified. Two fingers for each ore lithology will be required, one

finger for dumping whilst the other finger is reclaimed. The stockpile height needs to be

limited to 5m to allow the CAT 980 Loader safe access to the ore for reclaiming with

minimal risk of engulfment.


The available area has space for at least 8 x 20m wide stockpiles which could be up to

300m long if aligned parallel to the mill feed conveyor. Using a bulk density of 1.6t/m3

means that up to 160,000t of ore can be easily stored in this manner. Additional areas

are available for ROM storage if required. Expected crushing rates of up to 180t/hr can

be safely maintained with tramming distances up to 250m.


Tailings Storage Facility


Background


The existing Wonawinta Tailing Storage Facility (TSF) is a “turkey’s nest” type

impoundment situated north of the processing plant with embankments constructed

from mining waste. The northwest and east embankments are keyed into in-situ

sequences in the northeast corner where elevations are higher and form the northern

boundary of the storage.


Tailings deposition on the TSF is with perimeter piping and spigoting feeding towards

the central decant for water recovery maintaining a minimum 0.5m freeboard between

the height of the surrounding crest and the highest level of tailings deposition.


The TSF has a central concrete decant structure accessed by a causeway extending

from the east embankment. Favourable topography and location of the TSF relative to

the process plant enabled installation of a gravity decant system to remove decant water

from the TSF rather than a pumped decant system. The gravity decant drainage pipe

discharges decant water through a conduit passing beneath initial embankment and is




Page 44


embedded into the natural foundation. The reclaimed water is returned to the HDPE

lined Process Water Pond for reuse.


The original TSF design planned for seven upstream lifts to be constructed in nine

stages. An initial 10m starter embankment (Stage 1A) and a downstream 3m

embankment (Stage 1B) were to be followed by seven 2.5m lifts to a final crest height

of RL 279.5. To date Lift 1 (Stage 1A and Stage 1B) and Lift 2 have been completed.


Future Lifts


Noting that the practice of upstream lifts on old tailings is no longer the favoured/default

construction technique and either a centreline or downstream lift construction

methodology is encouraged where possible, Life of Mine tailings storage capacity has

been estimated using the existing starting footprint, centre-line construction

methodology with 8 x 2.5m lifts on top of Lift 1 Stage B and a consolidated tailings bulk

density of 1.6t/m

3

acquired from recent drilling data resulting in a notional capacity of

1.7Mt tails for each lift providing a total 10.8Mt tailings storage capacity


Calculated tailings capacity versus the 10-year mine plan conceptual lift construction

methodology and are shown in Table A18 and Figure A18. The next lift on the TSF will

be required to be completed mid-2026 assuming a H1 2026 start of production. It is

therefore planned to commence construction of Lift 3 in Q2 2026 with completion of

design / alternative solutions, approvals and construction documentation expected in

Q1 2026. Construction methodology has not been finalised but would be completed by

a specialised earthmoving and civil-construction contractor using their own fleet and

personnel, working under the instructions and supervision of a Project Manager and

TSF Designer.


Table A18: Calculation Tailings Capacity versus the Life of Mine Plan


CY 25 26 27 28 29 30 31 32 33 34 35 Total

Tonnes - 1.19 1.06 1.14 1.13 1.10 1.12 1.04 1.17 1.17 0.66 10.79

Cum. - 1.19 2.25 3.39 4.52 5.62 6.74 7.78 8.95 10.13 10.79 -

Lift 3 - 1.19 0.66 - - - - - - - - 1.85

Lift 4 - - 0.40 0.97 - - - - - - - 1.38

Lift 5 - - - 0.17 1.13 0.08 - - - - - 1.38

Lift 6 - - - - - 1.02 0.35 - - - - 1.38

Lift 7 - - - - - - 0.76 0.61 - - - 1.38

Lift 8 - - - - - - - 0.43 0.95 - - 1.38

Lift 9 - - - - - - - - 0.23 1.15 - 1.38

Lift 10 - - - - - - - - - 0.02 0.66 0.69

Capacity - 1.19 1.06 1.14 1.13 1.10 1.12 1.04 1.17 1.17 0.66 10.79




Page 45




Figure A18: Conceptual design of TSF centre-line lifts vs the existing TSF embankment.


Power


Power to the process plant will be provided by four hired 1250KVA diesel gensets on

an N+1 basis. A single 1,675KVA genset (owned by Manuka) will be used to supply

power during process plant shutdowns and through process plant start-up to support

peak draw requirements. Power for the water bores and camp is supplied by separate

smaller 220KVA diesel generators.


Site Offices and Ablutions


An overhead view of existing site offices, buildings and associated infrastructure is in

Figure A19. The administration office block has eight office rooms that can each

accommodate two desks and two larger rooms that can accommodate at least four

desks each, a large manager’s office and meeting area, and a crib room that can seat

approximately 12-15 people. A large training room for 20-30 people is in a separate

building which also contains three female toilets and showers and changing area, the

site laundry and storeroom and a small office. Three male toilets, six showers and

change facilities are in a separate building. The First Aid building also has an office and

storeroom. A small spare office is also available.

Planned upgrades for when mining personnel are mobilised to site include the following:

• New ablution buildings for the mining personnel. Two buildings, one each for

males and females are planned, located in the area allocated for mining

equipment parking, maintenance, workshop and office. A new crib room with

office will also be required.

• A new sewerage system, or upgrade to the existing system may be required.




Page 46




Figure A19: Layout of the existing administration and ablution facilities


Water


Site make up water is provided from a borefield located approximately 4km south of the

processing plant. The borefield was developed in September 2012 based on the original

plant design and has an estimated 25L/s production capacity.

Bore water is received at the plant in the Raw Water Pond and it can also be directed

into the Process Water Pond. Both ponds are lined with HDPE liner to prevent leakage.

Raw water is distributed to the processing plant through a duty/standby pumping

arrangement and is available for dust suppression at a dedicated standpipe fed by a

diesel-powered pump. Raw water also feeds the Reverse Osmosis (RO) plant to

produce potable water.

The introduction of the deslime circuit will result in a negative overall site water balance

as significant water used in the process is lost with the slimes to the tailings dam. To

avoid this imbalance a dewatering thicker will be included in the deslime circuit to reduce

the slimes moisture content from 90% to between 45-55% and recover between 93 –

98L/s of water for reuse in the processing circuit (Table A19).




Page 47



Table A19: Site wide water balance


Base Case (30% to slimes) t/hr wt% solids wt% moist. L/s

ROM Feed 143 92 8 4

Deslime to Tailings 43 10 90 (107)

Leach Tailings 100 48 52 (30)

Decant Return


21

Site Dust Suppression


(2)

Total Losses


(115)

Bore water


25

Surface Water Harvesting


2

Total Inputs


27

Balance (pre-dewatering)


(88)

Dewatering Thickener


92.7 - 97.5

Balance (post-dewatering) 4.3 - 9.1


Camp Accommodation

The Wonawinta mine camp (Figure A20) lies just over 2 km east of the process plant

and administration buildings. The existing facility comprises eighteen industry-standard

accommodation units, housing up to 70 residents in single-bed, ensuite rooms equipped

with air conditioning, a wardrobe, small refrigerator, networked TV, desk and chair.

Manuka personnel will clean and maintain all rooms.

Central amenities include a fully segregated kitchen and food-storage area, a large

dining hall with seating for 30, and a recreation building with gym facilities. Camp

operations and support services will be staffed by Manuka employees.

To accommodate the anticipated increase in headcount, two additional four-room

blocks (each room with an ensuite) will be installed, boosting capacity to 78. Suitable

units are available at MKR’s Mt Boppy camp and can be relocated if required;

alternatively, new units have been budgeted for in the capex estimate.




Page 48




Figure A20: Layout of the existing accommodation camp


Infrastructure – Mt Boppy

Available infrastructure at Mt Boppy includes grid power, potable water from Cobar, tar

road access, and a ~40 person camp with kitchen and ablutions (Figure A21), a 70kL

diesel storage facility, an undercover heavy mining equipment workshop area (Figure

A22), and mine offices. A capital provision has been made to upgrade the

accommodation facilities and an engineered bund to manage the interaction between

cutback and the dry tailings impoundment (TSF3) located at the southern end of the Mt

Boppy Open Pit.


Wonawinta - Workforce

The Project will employ up to 140 personnel (Figure A23) operating on a mix of roster

patterns—5/24/3, 8/6 day-shift, 7/7 day-shift, 7/7 night-shift, and 7/7 continuous-shift.

Peak camp accommodation must support approximately 75 beds, including a 15%

percent contingency for contractors and visitors. Staffing forecasts and corresponding

camp requirements over time are illustrated in Figure A23.


The organisational structure is led by an Operations Manager with direct reports

including the Senior Metallurgist and Managers for Processing, Maintenance,

Administration, and HSE. During the construction and commissioning phase, an

experienced Construction Manager will be engaged to oversee project delivery. A Mine

Manager—holding the requisite statutory quarry ticket—will also report to the

Operations Manager. An organisational chart is provided in Figure A24.




Page 49




Figure A21: Existing camp facilities located at Mt Boppy.




Figure A22: Existing mining and diesel power infrastructure at Mt Boppy.




Page 50



Figure A23: Employee Count.


Figure A24: Project Organisation Chart.




Page 51


Environment and Approvals


Wonawinta


Wonawinta is situated on an existing mining lease, with approvals in place from prior

operations. These approvals are still in place for four pits. In essence nothing material

needs to be done to modify any current approval to recommence mining as the original

conditions which considered four pits have not varied. Regularising of existing approvals

will be undertaken to allow for additional open pits within the existing disturbance

footprint or to allow for greater footprints of waste dumps etc.


Manuka in April 2025 engaged Irwin Environmental Management Pty Ltd to undertake

an environmental compliance audit. The audit conclusions were that the Company is

maintaining the Wonawinta Mine Site under care and maintenance in a manner which

satisfactorily reduces the risk of harm to the environment. Some non-compliances have

been noted, with the majority of these representing matters which are administrative in

nature or have low risk of adverse environmental impact.


The following approvals are current for the Wonawinta Mine.

• Development Consent 2010/LD00074: issued by Cobar Shire Council (Council)

and modified three times (most recently 15 September 2015).

• Environment Protection Licence (EPL) 20020: issued by the NSW Environment

Protection Authority (EPA).

• Mining Lease (ML) 1659: Issued by the Minister for Resources and Energy on 23

November 2011.

• Water Supply Works Approval 85WA752614: issued by the Department of

Climate Change, Energy, Environment and Water (DCCEEW) for eight

groundwater bores.

• Water Access Licence (WAL) 30322: issued by WaterNSW for take of up to 750

units from the Kanmantoo Fold Belt MDB Groundwater Source.

The Life of Mine Plan proposes some new waste dump locations, capacities and

designs. These updated designs will be modified or regularised to existing approvals in

due course and will not impede development timelines.

A Material Characterisation Report was undertaken by Landloch Pty Ltd the conclusions

included:

• The main chemical constraints of the Clay and Waste rock material were salinity,

sodicity and alkalinity. Gypsum will ameliorate the sodicity and PH constraints.

Screening for PH and salinity needs to take place before the addition of gypsum.

• Plant species used in rehabilitation need to have a high salt tolerance.

Planning for the Tailings dam lifts and tailings disposal is still ongoing. This work is

well progressed by the Company’s TSF engineer but is not yet completed at the date

of publication of this Mine Plan.





Page 52



Mt Boppy


Existing Development Approvals with Cobar Shire Council (CSC), and related licences

and consents are summarised in Table A20 and A21:


Table A20: Cobar Shire Council Development Approvals


Development

Approvals

Date

Granted

Expiry Details / Comments

Development

Consent

2012/LD-00034

22 Nov 2012 N/A Granted by Cobar Shire Council (CSC) for the

expansion of the off-lease mining camp.

Development

Consent

2011/LD-00070

27 Sep 2012 N/A Granted for the continuation of mining and

processing of ore at an upgraded processing

plant on the Mine Site, including construction

of new TSF

Development

Consent

2011/LD-00070-

Rev01

27 Jul 2015 N/A Modification of DC granted by CSC to add five

new conditions and to alter specific conditions

within original DC.

Condition 1 altered to include the 2015

Statement of Environmental Effects ([SEE]

Reference No. 569/05) as legal

supplementary document.

Condition 23 altered to modify stated

timeframe to “the determination date of the

first modification approval of the consent.”

New Conditions (i) to (v) were added for

approval of, and supplementary conditions for:

•Submission of required plans.

•Obtaining site specific licences.

•Granting the extension and operation of the

mine including mining of approximately

630,000t of ore.

•Management of potentially acid forming

waste rock.

•Transportation of ore to the Manuka Mine

(Wonawinta).

•Construction of temporary mine water storage

dams, roadways and road drainage.

•24-hour 7-days per week operations.

•Additional rehab requirements.




Page 53


Table A21: Development Consent Licences


License Date

Issu

ed

Expi

ry

Details

Environment

Protection

Licence No.

20192

10

Jan

2013

N/A Issued by NSW EPA under the Protection of the

Environment Operations Act 1997 (‘POEO Act’).

Current licence version is Notice No: 1566717.

Groundwater

Licence

85BL256088

24

May

2011

N/A Issued by the (then) NSW Office of Water (NOW) for

monitoring bores PBP001, PBP003, PBP004, PBP018,

PBP019 and PBP020.

Groundwater

Licence

85WA752612

16

Jan

2012

16

Mar

2033

Issued by the NOW for water supply works associated

with three historic water supply bores within Lot 7301

DP 1170536.

Groundwater

Licence

85WA753524

10

Jun

2013

6

Jun

2033

Issued by NOW for water supply works associated with

excavation of the open cut pit and production water.

Licence

WAL30045

14

Jun

2012

N/A Issued by NOW providing entitlement to 250Ml from the

Lachlan Fold Belt MDB Groundwater Source.


Three mining leases (ML 240, 311 and 1681) issued under the Mining Act 1992 and

four Gold Leases (GL 3255, 5836, 5848 and 5898) issued under the Mining Act 1906,

are held by Mt Boppy Resources Pty Ltd (a wholly owned subsidiary of Manuka). All

permits are current and in good standing.


The property on which the Mount Boppy mine is situated is on Crown Land. A Native

Title Agreement is in place with the traditional owners over ML1681 however no current

production is anticipated from this lease. The Company notes that no land within the

licence area is classified as sensitive land. No further approvals other than those

required under the Mining Act 1992 are required.


Mt Boppy operates under Development Consents 2006/LD00015 and 2011/LD-00070-

Rev1, inclusive of an amended Mining Operations Plan (2020). A compliance review

was completed in Dec 2024 on the Mt Boppy Mine. The following approvals are

current for the Mt Boppy Gold Mine.

• Development Consent 2006/lD00015: issued by Cobar Shire Council (Council).

• Development Consent 2011/lD0070: issued by Council and modified in 2015.

• Environment Protection Licence (EPL) 20192: issued by the NSW Environment

Protection Authority (EPA).

• Water Supply Works Approval 85WA752611: issued by the Department of Climate

Change, Energy, Environment and Water (DCCEW) for two groundwater bores.

• Water Supply Works Approval 85WA753524: issued by DCCEW for groundwater

extraction from an open excavation (open cut).




Page 54


• Water Supply Works Approval 85WA753525: issued by DCCEW for watercourse

diversion.

• Water Access Licence (WAL) 30045: issued by WaterNSW for take of up to 250

units from the Lachlan Fold Belt MDB Groundwater Source.


Water quality of the Open Pit water is suitable for stock (based on prior and current

analysis), and approvals are in hand for pumping out using existing return water storage

dams, evaporation or else the mostly dry creek bed adjacent to the Open Pit.


Waste rock geochemical characterisation has been undertaken through ICP analyses

at ALS Orange of evaluation drilling sampling of the Mt Boppy orebody. The Mineral

Resource block model incorporates these analyses. Waste characterisation testing

completed to date confirms that a proportion of the waste rock is classified as Potentially

Acid Forming (PAF). PAF material has been encountered once mining reached depths

of approximately 50m to 60m below ground level. PAF waste rock material with total

sulphur content greater than 1% (~242,148bcm) will be placed either within the existing

TSF3 structure or a new separate area demarcated within the Main Waste Dump prior

to capping. The remaining PAF material with total sulphur content between 0.3% and

1% (~720,259bcm) will be placed within specially designed sections of the Waste Rock

Emplacement. The remaining ~2,500,000bcm of waste rock is considered non-acid

forming (NAF). It should be noted that no stockpiled PAF material exhibits any signs of

acid formation with generally clean water forming around those piles – this is exhibited

across the entire site.

Data sourced from publicly available NZX filings. Our datasets may not be complete. Automated analysis can produce errors. If you believe any data on this page is incorrect, please contact us at hello@nzxplorer.co.nz. For informational purposes only. Not investment advice.