Taiko Critical Minerals Limited (NZX: TCM) filed “Fast-Track Panel Draft Decision - Approve Barrytown Project” with NZX on 5 November 2026, as an operational update announcement.
From the announcement:“www.taikocm.co.nz Tāiko Critical Minerals Limited (Tāiko, TCM or the Company) (NZX:TCM) has today received conditional approval of its fast-track application for the Barrytown Critical Minerals Project.”
- Which company?
- Taiko Critical Minerals Limited (NZX: TCM)
- When was it filed?
- 5 November 2026
- Where is the original?
- NZX announcement
Fast-Track Panel Draft Decision - Approve Barrytown Project
NZX and Media Release
5 November 2026
FAST-TRACK PANEL RELEASES DRAFT DECISION TO APPROVE
BARRYTOWN CRITICAL MINERALS PROJECT
Taiko Critical Minerals Limited (NZCN: 5824110)
c/o PriceWaterhouseCoopers, Level 26 PwC Tower, 15 Customs Street West,
Auckland Central, Auckland 1010, New Zealand
www.taikocm.co.nz
Tāiko Critical Minerals Limited (Tāiko, TCM or the Company) (NZX:TCM) has today received
conditional approval of its fast-track application for the Barrytown Critical Minerals Project.
The fast-track expert panel issued a draft decision proposing to grant all approvals sought by
Taiko, subject to final conditions of consent.
Invited parties will be given the opportunity to comment of the draft conditions of consent, and
the Company the opportunity to reply, before a final decision due on 8 December 2026.
Key Points
• The application covers the Canoe Creek, Barrytown Farms and Cargill South blocks, which
extend the already-consented Coates South block and would enable a project life of more
than 20 years.
• Together, the four blocks contain a JORC Code Mineral Resource of 35Mt at 21% Total
Heavy Mineral (THM), of which 34.1Mt is in the Measured and Indicated categories.
Chief Executive Robert Brand says the draft decision is a key step in the development of a high-
quality mineral resource.
“The Panel’s draft decision reflects the work of our team and close engagement with community
and stakeholders over the past nine years. We will work through the draft conditions of consent
carefully and provide our comments to the panel, and we look forward to receiving a final
decision by early December.”
Details of the panel’s draft decision is available on the fast-track website:
https://www.fasttrack.govt.nz/projects/barrytown-minerals-project/draft-decision-and-conditions
ENDS
For further information please contact:
Robert Brand
Chief Executive Officer
Mobile: +61 421 388 222
Email: robert.brand@taikocm.co.nz
Website: www.taikocm.co.nz
Page 2 of 3
ABOUT TĀIKO CRITICAL MINERALS
Tāiko is a New Zealand incorporated company preparing to extract, refine and export critical minerals
from privately owned farmland on the West Coast of the South Island of New Zealand, near
Greymouth. The Company has strong mana whenua support, with resource consents through to
implementation.
Tāiko plans to develop and produce ilmenite, zircon, garnet, and other critical minerals. The
Company’s “mine to market” strategy involves refining these critical minerals at a planned Mineral
Separation Plant on the West Coast and exporting them to global customers. The Company’s
operations are in start-up phase and are therefore pre-revenue.
BARRYTOWN CRITICAL MINERALS PROJECT
The Company’s core asset is the Barrytown Critical Minerals Project, contained on Mining Permit ML
60785 covering 1250ha of coastal heavy mineral sands located ~30 km north of Greymouth.
Tāiko has been granted resource consents to mine the mineral resource from the Coates South Block
property near Greymouth.
The Company has entered into a conditional Sale and Purchase Agreement with Barrytown Farms
Limited to acquire approximately 304 hectares of farmland on the Barrytown Flats, securing access
rights for the core mining blocks of the project.
The Company has also been granted resource consents to construct and operate a mineral separation
plant at nearby Rapahoe, which will produce high value critical minerals from the mineral resource.
In addition, Tāiko will transport refined minerals via established rail infrastructure to South Island
ports for export to global customers.
MINERAL RESOURCE
Tāiko has reported a JORC Code (2012) compliant Mineral Resource for the Barrytown Critical Minerals
Project comprising 34.1Mt @ 21% Measured & Indicated Total Heavy Mineral and 0.9Mt @ 23%
Inferred Total Heavy Mineral.
PROJECT DEVELOPMENT
The Company lodged its substantive application for resource consent under the Fast Track Approvals
Act 2024 on 8 June 2026, which is the subject of this announcement.
Tāiko has received strong support from Mana Whenua Te Rūnanga o Ngāti Waewae, whose vital input
is helping to shape the project from resource consents through to implementation.
COMPETENT PERSONS STATEMENT
The Mineral Resource information in this announcement is based on information compiled under the
supervision of Mathijs van de Ven (MAusIMM) and Michael Gazley (MAusIMM, MAIG) of RSC, who are
Competent Persons as defined in the JORC Code (2012). Both have sufficient experience relevant to
this style of mineralisation and consent to the inclusion of this information in the form and context in
which it appears.
Page 3 of 3
MINERAL RESOURCE ESTIMATES
All references to mineral resource estimates should be read in conjunction with the reports listed in
the table below.
Location Title of Document Competent person Report & (NZX
release) date
Barrytown
Farms and
Coates South
Initial Mineral Resource Estimate
for the Barrytown Critical Minerals
Project
Mr Rene Sterk MSc FAusIMM
(CP(Geo) MAIG (RPGeo) MSEG
20 Jan 2026
(pre NZX listing)
Barrytown
Farms and
Coates South
Listing Profile – Taiko Critical
Minerals Limited
Mr Rene Sterk MSc FAusIMM
(CP(Geo) MAIG (RPGeo) MSEG
5 Mar 2026
(NZX: 5 Mar 26)
Canoe Creek Canoe Creek Mineral Resource
Estimate
Mathijs van de Ven (MAusIMM)
Michael Gazley (MAusIMM,
MAIG)
4 May 2026
(NZX: 13 May 26)
Canoe Creek Initial Mineral Resource Estimate
for the Canoe Creek Block at the
Barrytown Critical Minerals Project
Mathijs van de Ven (MAusIMM) 6 May 2026
(NZX: 13 May 26)
Cargill South Initial Mineral Resource Estimate
for the Cargill South Block at the
Barrytown Critical Minerals Project
Mathijs van de Ven (MAusIMM)
Michael Gazley (MAusIMM,
MAIG)
11 Oct 2026
(NZX: 12 Oct 26)
The above reports were prepared by RSC and can be found at
www.taikocm.co.nz/mineral-resource-information.
All disclosures made in this document with reference to mineral resources estimates are quoted as
per those documents. Taiko confirms that it is not aware of any new information or data that will or
may materially affect the information included in this market announcement. In the case of mineral
resource estimates, all material assumptions and technical parameters underpinning the estimates
continue to apply and have not materially changed since the date of the above reports.
FORWARD LOOKING STATEMENTS
This announcement may contain forward-looking statements based on management’s expectations.
Actual results may differ materially from those expressed or implied in such statements.
Forward-looking statements, opinions, and estimates included in this document are based on
assumptions and contingencies which are subject to change without notice. These statements are
provided as a general guide only and should not be relied upon as a guarantee of future performance.
Project development pathways, timelines, production targets, and commercial outcomes are
indicative only and are based on current expectations. Actual timing and outcomes may vary
depending on technical, regulatory, funding, and market conditions. Tāiko does not undertake to
update forward-looking statements except as required by applicable law.
PUBLIC DISCLOSURES
This announcement should be read in conjunction with Taiko’s previous NZX announcements. It is not
intended to provide a comprehensive overview of all material information relating to the Company
and should not be relied upon as a substitute for those disclosures.
Data sourced from publicly available filings. Our datasets may not be complete. Automated analysis can produce errors. If you believe any data on this page is incorrect, please contact us at hello@nzxplorer.co.nz. For informational purposes only. Not investment advice.
Other issuers discussed similar conditions around this time
Matched by meaning across NZX announcement text, not keywords — based on our semantic index of announcement bodies.
- MKR — Manuka Resources Limited: June 2026 Annual Report2026-09-30
“shortcut to avoid environmental best practice and compliance. TTR’s application included 109 operating conditions and a set of comprehensive management plans to ensure there are no adverse effects on the marine environment. A five member panel was appoint…”
- MKR — Manuka Resources Limited: September 2026 Quarter Activities and Cashflow Reports2026-11-01
“Page | 6 Manuka Resources Limited - Level 4 Grafton Bond Building, 201 Kent St Sydney NSW Australia 2000 ABN 80 611 963 225 Tel 02 7253 2020 www.manukaresources.com.au Competent Person details, was included in that announcement. The Company confirms that it…”