Precinct Properties New Zealand Limited logo

Commercial Bay Programme Update

Operational Update28 May 2019PCTReal Estate

Precinct Properties New Zealand Limited Head Office Wellington Office
E hello@precinct.co.nz Level 12, 188 Quay Street, Auckland 1010 T 0800 400 599 Level 19, 157 Lambton Quay, Wellington T 0800 400 599

W www.precinct.co.nz PO Box 5140, Auckland 1141, New Zealand F +64 9 927 1655 PO Box 2, Wellington 6140, New Zealand F +64 4 494

2267

NZX announcement – 29 May 2019

Commercial Bay Programme Update

Precinct Properties New Zealand Limited (Precinct) (NZX: PCT) announces today that following

a detailed independent review of the construction programme for Commercial Bay, the

previously disclosed targeted opening dates have now been revised to March 2020 for the

retail centre and April 2020 for the new PwC Tower. The revised targeted opening dates are

due to observed delays in construction progress by the main contractor, Fletcher

Construction, across both the Tower and retail centre components.

Due to this revision the forecasted total project cost is now expected to be between $690 million

and $700 million with the potential increase of up to $10 million reflecting the cost of delays to

opening. The yield on cost is expected to remain largely unchanged in a range of 7.4% to 7.5%,

ensuring that the development remains on track to deliver the expected benefits to Precinct’s

long-term earnings.

Pleasingly, retail leasing commitment has increased to above 92%, and office leasing continues

to advance, with further leasing beyond the currently committed 80% progressing well.

Scott Pritchard, Precinct’s CEO, said: “As previously stated, the last two months have been

critical in progressing the project, and it is unfortunate to have to confirm that we have observed

further slippage beyond what we observed earlier this year”.

“We will continue to work closely with all retailers and office occupiers at Commercial Bay to

manage risks and minimise any potential disruptions that the revised opening dates may cause.

Our key priority is ensuring that all retailers can plan their opening at Commercial Bay with

confidence, and that our office occupiers can effectively transition to their new premises”.

“While we are very disappointed that the opening of Commercial Bay has been further

delayed, we remain steadfastly focused on the successful delivery of the overall project to the

highest quality standards. We are committed to what we set out to deliver - creating a world-

class waterfront destination on par with other gateway cities”.

The revised opening date for the retail centre takes account of expert advice that the base

building works are unlikely to be complete before December 2019. In addition, Precinct has

decided to provide additional time for completion of retail fitout works after these base building

works have been completed. This decision has been made to ensure retailers have the best



Precinct Properties New Zealand Limited Head Office Wellington Office

E hello@precinct.co.nz Level 12, 188 Quay Street, Auckland 1010 T 0800 400 599 Level 19, 157 Lambton Quay, Wellington T 0800 400 599

W www.precinct.co.nz PO Box 5140, Auckland 1141, New Zealand F +64 9 927 1655 PO Box 2, Wellington 6140, New Zealand F +64 4 494

2267

possible opportunity to open successfully as well as ensuring that the quality of the finished

centre meets our aspirations. Consequently, the retail opening date will be in March 2020,

approximately three months after estimated completion of base build works.

The main contractor has brought a number of claims against Precinct under the construction

contract seeking extensions of time and/or additional cost and further claims are anticipated.

To date these claims have not resulted in material additional costs or extensions of time being

awarded and Precinct remains confident that the provisions of the construction contract

appropriately protect Precinct from losses due to contractor delay and/or breach of contractor

obligations. Liquidated damages are expected to largely mitigate the impact on Precinct from

losses of income and other prolongation costs over the delayed period, however liquidated

damages will cease to apply following completion of base build works.

Precinct notes that the programme review was completed by its project manager, RCP, and

has been completed independently of the main contractor. The review has been undertaken

to inform Precinct of the likely completion date for the project, making appropriate risk

allowances based on RCP’s observance of contractor delays to date. This review was

commissioned because the main contractor has not kept Precinct informed of their programme

for completion of the base build works reflecting the construction methodology being

employed.

Earnings guidance for the 2019 financial year remains unchanged at approximately 6.60 cents

per share (before performance fees). Precinct will provide a full, detailed update on the

Commercial Bay project in our full year results in August 2019.

-ends-









Precinct Properties New Zealand Limited Head Office Wellington Office

E hello@precinct.co.nz Level 12, 188 Quay Street, Auckland 1010 T 0800 400 599 Level 19, 157 Lambton Quay, Wellington T 0800 400 599

W www.precinct.co.nz PO Box 5140, Auckland 1141, New Zealand F +64 9 927 1655 PO Box 2, Wellington 6140, New Zealand F +64 4 494

2267

For media enquiries, please contact:

Nicola McArthur

General Manager – Marketing and

Communications

Email: nicola.mcarthur@precinct.co.nz

For investor enquiries, please contact:

Scott Pritchard

Chief Executive Officer

Email: scott.pritchard@precinct.co.nz


George Crawford

Chief Operating Officer

Email: george.crawford@precinct.co.nz


Richard Hilder

Chief Financial Officer

Email: richard.hilder@precinct.co.nz


About Precinct (PCT)

Precinct is New Zealand’s only listed city centre specialist investing predominately in premium

and A-grade commercial office property. Listed on the NZX Main Board, PCT currently owns

Auckland’s PwC Tower, AMP Centre, ANZ Centre (50%), Zurich House, HSBC House, Mason

Bros. Building, 12 Madden Street, 10 Madden Street and Commercial Bay; and Wellington’s

AON Centre, Dimension Data House, No. 1 and No. 3 The Terrace, Pastoral House, Mayfair

House and Bowen Campus.

Data sourced from publicly available filings. Our datasets may not be complete. Automated analysis can produce errors. If you believe any data on this page is incorrect, please contact us at hello@nzxplorer.co.nz. For informational purposes only. Not investment advice.

Other issuers discussed similar conditions around this time

Matched by meaning across NZX announcement text, not keywords — based on our semantic index of announcement bodies.