Covid-19 impacts on Tilt Renewables
Infratil Limited 5 Market Lane, PO Box 320, Wellington, New Zealand Tel +64-4-473 3663 www.infratil.com
26 March 2020
Covid-19 impacts on Tilt Renewables
Attached is a market release from Tilt Renewables Limited (TLT) outlining the impacts of Covid-19 on
its business.
Infratil is the 65% shareholder in TLT.
Any enquiries should be directed to:
Mark Flesher, Investor Relations, Infratil Limited
mark.flesher@infratil.com
---
Tilt Renewables GPO Box 16080
Phone: +61 1300 660 623 Collins Street West
tiltrenewables.com Melbourne Victoria, 8007
Australia
NZX AND ASX ANNOUNCEMENT
25 March 2020
COVID‐19 IMPACTS ON TILT RENEWABLES
Tilt Renewables (TLT) is a strong robust business which owns 7 operational wind farms across
Australia and New Zealand and 2 significant assets under construction, 1 in Australia and 1 in New
Zealand. TLT has a relatively small and highly mobile workforce which is
often required to work
remotely as part of normal business activities. The infrastructure used to support the team is well
established to enable remote working and is fully cloud based.
Whilst our key focus right now is to secure the health and wellbeing of our team and their families,
we
are pleased to report that our people have been working from home successfully for nearly two
weeks already and normal business activities have been sustained.
Operational Assets
TLT’s operational assets in both Australia and New Zealand provide a ‘lifeline utility’ or ‘essential
service’ and are therefore not subject to lockdown
restrictions. Appropriate protective measures
against the spread of COVID‐19 are in place. To date, TLT has not experienced any impact attributable
to the COVID‐19 pandemic on the operational asset fleet, generation volume, costs or revenue.
TLT has worked with our operations and maintenance partners to take proactive measures to
protect
the health of all site employees, including segregation of workgroups, back‐up coverage for certain
key skill sets, remote working for support staff and reinforcing general hygiene practices.
Routine maintenance activities, typically set for 6 or 12 month intervals, may where required be
deferred so that site crews can
focus on fault responses requiring physical attendance.
The 24/7 monitoring, bidding, dispatch, control of TLT’s windfarms is normally executed remotely or
automatically.
Production from the current operating assets is largely covered by long term offtake agreements with
strong well capitalised counterparties, producing healthy cashflows which are resilient to short term
market fluctuations.
Construction Projects
TLT currently has two large scale construction projects in progress representing nearly A$1B of total
investment.
TLT has been working closely with its project partners, Vestas for the Dundonnell Wind Farm (DDWF)
in Victoria, Australia and Siemens Gamesa for the Waipipi Wind Farm (WWF) in Taranaki,
New
Zealand, to understand the impacts of COVID‐19 across the international supply chain, construction
activities and movements of key personnel, with the situation currently as follows:
DDWF
All wind turbine components for the DDWF have completed manufacturing with the final
shipment to site underway (from China) in the coming days.
Construction and commissioning activities continue at DDWF at this time with no current
restrictions in relation to on‐site activities. Appropriate personnel distancing and
hygiene
protocols have been implemented. 28 turbines, out of a total of 80, are fully erected, with
commissioning of these turbines ongoing. Additional restrictions on activities such as
construction are possible in Victoria, and these could lead to some delays associated with the
erection of turbines. We continue to monitor
relevant official announcements, however the
essential service nature of electricity generation assets, including late stage construction
activities may allow the project to continue to progress. Mitigation options are available to
be implemented if required.
WWF
Minor delays to manufacturing of turbine components for WWF have been observed due to
the manufacturing shutdown in China during February and March. However the Chinese
manufacturing facilities have now returned to operation, and these delays are not expected
to have a material impact on the total project schedule. Components being manufactured in
European factories have not been delayed.
Construction activities at WWF are
not considered an ‘essential service’ and therefore in
response to the COVID‐19 Level 4 Alert in New Zealand, on‐site activities will cease for a period
of at least four weeks, as directed by the New Zealand Government. The WWF project was
progressing to schedule up to this point,
and TLT is confident there is sufficient contingency in
both the project schedule and budget to ensure that the impact of this shutdown will not
materially affect the project. Mitigation and expedition options will be explored and
implemented where practical once construction activity resumes on site.
Border restrictions in both New
Zealand and Australia have presented some challenges with respect
to movement of key project personnel. However alternative local resources with sufficient expertise
have been identified where required, and again at this time this is not expected to impact either
project materially.
Offtake agreements for both projects are not expected to
be affected – noting that the likely project
impacts are not considered to be material at this time and the fact there are significant buffers in place
between expected project completion dates and those required under these offtake agreements.
Once these two projects have been completed over 80% of annual revenue
from the 835MW total
installed capacity owned by TLT will be under long term off take contracts.
Company Performance
Following the completion of the sale of the Snowtown 2 Wind Farm in December 2019 TLT is in a
healthy positive cash position which supports a very strong balance sheet. The
current unrestricted
cash balance (as at 23
rd
March 2020) for the TLT Group is A$535.2 million, which is primarily held in
term deposits.
In addition, following the Snowtown 2 sale, TLT repaid the NZ$66.9 million syndicated bank facility
which was due for repayment in October 2020. This has resulted in the next debt maturity for the TLT
group not occurring until November 2023 followed by September 2024, for the Dundonnell Wind Farm
Facility
and for the Waipipi Wind Farm project finance facility respectively.
TLT FY20 earnings result is expected to be up to $1m lower than the bottom end of the updated
guidance range of $118m ‐ $122m provided in December 2019. This is the result of both the 500kV
transmission outages in Victoria
during February, which impacted revenue from the Snowtown 1 Wind
Farm, and a slower than anticipated ramp up of generation at DDWF in March.
TLT notes that the final full year earnings result, which remains subject to external audit, will still be
circa 16% above the original guidance for the
year, when adjusted for the sale of Snowtown 2.
ENDS
For further information from Tilt Renewables, please contact:
Steve Symons
Chief Financial Officer
Tilt Renewables
Phone +61 419 893 746
Data sourced from publicly available filings. Our datasets may not be complete. Automated analysis can produce errors. If you believe any data on this page is incorrect, please contact us at hello@nzxplorer.co.nz. For informational purposes only. Not investment advice.