Infratil Limited/Announcement
Infratil Limited logo

Covid-19 impacts on Tilt Renewables

Operational Update26 March 2020IFTUtilities

Infratil Limited 5 Market Lane, PO Box 320, Wellington, New Zealand Tel +64-4-473 3663 www.infratil.com




26 March 2020




Covid-19 impacts on Tilt Renewables


Attached is a market release from Tilt Renewables Limited (TLT) outlining the impacts of Covid-19 on

its business.


Infratil is the 65% shareholder in TLT.



Any enquiries should be directed to:


Mark Flesher, Investor Relations, Infratil Limited

mark.flesher@infratil.com

---

Tilt Renewables GPO Box 16080
Phone: +61 1300 660 623 Collins Street West

tiltrenewables.com Melbourne Victoria, 8007

Australia

 

NZX AND ASX ANNOUNCEMENT 

25 March 2020 

 

COVID‐19 IMPACTS ON TILT RENEWABLES 

 

Tilt Renewables (TLT) is a strong robust business which owns 7 operational wind farms across 

Australia and New Zealand and 2 significant assets under construction, 1 in Australia and 1 in New 

Zealand.  TLT has a relatively small and highly mobile workforce which is

 often required to work 

remotely as part of normal business activities.  The infrastructure used to support the team is well 

established to enable remote working and is fully cloud based.   

 

Whilst our key focus right now is to secure the health and wellbeing of our team and their families, 

we 

are pleased to report that our people have been working from home successfully for nearly two 

weeks already and normal business activities have been sustained.   

 

Operational Assets 

 

TLT’s operational assets in both Australia and New Zealand provide a ‘lifeline utility’ or ‘essential 

service’ and are therefore not subject to lockdown 

restrictions.  Appropriate protective measures 

against the spread of COVID‐19 are in place.  To date, TLT has not experienced any impact attributable 

to the COVID‐19 pandemic on the operational asset fleet, generation volume, costs or revenue.   

 

TLT has worked with our operations and maintenance partners to take proactive measures to

 protect 

the health of all site employees, including segregation of workgroups, back‐up coverage for certain 

key skill sets, remote working for support staff and reinforcing general hygiene practices.   

 

Routine maintenance activities, typically set for 6 or 12 month intervals, may where required be 

deferred so that site crews can 

focus on fault responses requiring physical attendance.   

 

The 24/7 monitoring, bidding, dispatch, control of TLT’s windfarms is normally executed remotely or 

automatically. 

 

Production from the current operating assets is largely covered by long term offtake agreements with 

strong well capitalised counterparties, producing healthy cashflows which are resilient to short term 

market fluctuations.  

 

Construction Projects 

 

TLT currently has two large scale construction projects in progress representing nearly A$1B of total 

investment.   

 

TLT has been working closely with its project partners, Vestas for the Dundonnell Wind Farm (DDWF) 

in Victoria, Australia and Siemens Gamesa for the Waipipi Wind Farm (WWF) in Taranaki, 

New 

Zealand, to understand the impacts of COVID‐19 across the international supply chain, construction 

activities and movements of key personnel, with the situation currently as follows: 




 

 

DDWF 

 All wind turbine components for the DDWF have completed manufacturing with the final 

shipment to site underway (from China) in the coming days.  

 Construction and commissioning activities continue at DDWF at this time with no current 

restrictions in relation to on‐site activities.  Appropriate personnel distancing and

 hygiene 

protocols have been implemented.  28 turbines, out of a total of 80, are fully erected, with 

commissioning of these turbines ongoing.  Additional restrictions on activities such as 

construction are possible in Victoria, and these could lead to some delays associated with the 

erection of turbines.  We continue to monitor 

relevant official announcements, however the 

essential service nature of electricity generation assets, including late stage construction 

activities may allow the project to continue to progress.  Mitigation options are available to 

be implemented if required.  

 

WWF 

 Minor delays to manufacturing of turbine components for WWF have been observed due to 

the manufacturing shutdown in China during February and March.  However the Chinese 

manufacturing facilities have now returned to operation, and these delays are not expected 

to have a material impact on the total project schedule.  Components being manufactured in 

European factories have not been delayed. 

 Construction activities at WWF are

 not considered an ‘essential service’ and therefore in 

response to the COVID‐19 Level 4 Alert in New Zealand, on‐site activities will cease for a period 

of at least four weeks, as directed by the New Zealand Government. The WWF project was 

progressing to schedule up to this point, 

and TLT is confident there is sufficient contingency in 

both the project schedule and budget to ensure that the impact of this shutdown will not 

materially affect the project. Mitigation and expedition options will be explored and 

implemented where practical once construction activity resumes on site. 

 

Border restrictions in both New

 Zealand and Australia have presented some challenges with respect 

to movement of key project personnel.  However alternative local resources with sufficient expertise 

have been identified where required, and again at this time this is not expected to impact either 

project materially. 

 

Offtake agreements for both projects are not expected to 

be affected – noting that the likely project 

impacts are not considered to be material at this time and the fact there are significant buffers in place 

between expected project completion dates and those required under these offtake agreements. 

 

Once these two projects have been completed over 80% of annual revenue

 from the 835MW total 

installed capacity owned by TLT will be under long term off take contracts. 

 

Company Performance 

 

Following the completion of the sale of the Snowtown 2 Wind Farm in December 2019 TLT is in a 

healthy positive cash position which supports a very strong balance sheet.  The

 current unrestricted 

cash balance (as at 23

rd

 March 2020) for the TLT Group is A$535.2 million, which is primarily held in 

term deposits.   

 

 

 

 




 

 

In addition, following the Snowtown 2 sale, TLT repaid the NZ$66.9 million syndicated bank facility 

which was due for repayment in October 2020.  This has resulted in the next debt maturity for the TLT 

group not occurring until November 2023 followed by September 2024, for the Dundonnell Wind Farm 

Facility

 and for the Waipipi Wind Farm project finance facility respectively.   

 

TLT FY20 earnings result is expected to be up to $1m lower than the bottom end of the updated 

guidance range of $118m ‐ $122m provided in December 2019.  This is the result of both the 500kV 

transmission outages in Victoria

 during February, which impacted revenue from the Snowtown 1 Wind 

Farm, and a slower than anticipated ramp up of generation at DDWF in March.   

 

TLT notes that the final full year earnings result, which remains subject to external audit, will still be 

circa 16% above the original guidance for the

 year, when adjusted for the sale of Snowtown 2. 

 

ENDS 

 

 

 

 

For further information from Tilt Renewables, please contact: 

Steve Symons  

Chief Financial Officer 

Tilt Renewables 

Phone +61 419 893 746

Data sourced from publicly available filings. Our datasets may not be complete. Automated analysis can produce errors. If you believe any data on this page is incorrect, please contact us at hello@nzxplorer.co.nz. For informational purposes only. Not investment advice.