Quarterly Activities Report – 31 Mar 2020
1
New Talisman Gold Mines
Limited
Responsible,
Environmentally
Sustainable Mining
ASX/NZX Code NTL
____________________
Commodity Exposure
GOLD and SILVER
Board and Management
Charbel Nader Chairman/Independent Director
Matthew Hill Chief Executive/ Managing Director
Murray Stevens Non-Executive Director
Tony Haworth Independent Director
Jane Bell Company Secretary
Wayne Chowles Chief Operating Officer
Capital Structure
Ordinary Shares at 31/03/2020 2,692m
Share Price
Share Price at 28/04//2020 (NZX) 0.8cps
Share Price at 28/04//2020 (ASX) 0.6cps
New Talisman Gold Mines Limited
ACN
Address 541 Parnell Rd, Parnell,
Auckland
Phone +64 27 5557737
Website www.newtalisman.co.nz
Email info@newtalisman.co.nz
Market Announcement
For Immediate Release
QUARTER HIGHLIGHTS
• Highly prospective targets identified
• Resource estimate review by AMC
• Primary focus on processing plant
Starting the year few could have expected to see the world entering lockdowns
amid global uncertainty created by COVID-19. New Talisman was left, like many
companies, restricted in operations while the New Zealand Government imposed
complete lockdown on non-essential services by imposing COVID-19 Level 4.
As of 28 April 2020, the COVID-19 Alert Level has been lowered to Level 3 which
(although very restricted) will allow access to the site so long as distancing
measures are feasible. Underground works remain unlikely in Alert Level 3 due to
the size of the tunnels and the nature of ventilation in the mine. The Board has
been forced to delay underground works until compliance with all New Zealand
government restrictions can be achieved.
With the increasing likelihood for continued restrictions the team set about
reviewing the entire NTL database and identified activities which could be safely
undertaken and that have the highest resource potential.
While the global climate remains in varying degrees of distress, gold, a traditional
safe haven, has driven to recent highs and in NZD terms have peaked as high as
NZD2,894 dollars an ounce, bringing refreshed liquidity and new interest in the
company and its shares. NTL remains the only NZX-listed gold mine development
company.
The primary focus has been on delivering a production route for the Talisman ore
following the completion of a majority of the testwork at the pilot plant. The
testwork has informed the design of the larger plant with a minimum capacity of
300tpm and forms the basis for the consent. Potential site locations were
reviewed which may give some flexibility in council and district plans the plant
can operate under.
The highly anticipated Resource Estimate update is under final review following
the adoption of the interim report recommendations received from AMC during
the period. Shareholders should note that the review marks the final step in the
Talisman Deeps project and the commencement of applying the same
parameters to the remaining module of the historical database.
Quarterly Activities Report to 31 March 2020
2
TALISMAN RESOURCE ESTIMATE
As previously announced NTL commissioned Peter Stoker of AMC Consultants Pty Ltd (AMC) to
undertake an audit of the Talisman Gold Mine (NTGM) Mineral Resource estimate (the 2017 Model)
which was superseded by an updated estimate incorporating information obtained during the recent
rehabilitation works . This update also includes much of the test work AMC had intended to undertake,
including testing the effect of compositing of samples, testing the effect of top capping, and the use
of the historical metal prices in the gold equivalent formulae derived from the bullion sampling.
AMC has reviewed this updated Mineral Resource model and documentation and issued an internal
report to NTL with recommendations for improvement to the resource estimation methodology. A
new estimate, based on those recommendations, was compiled as a check estimate, resulting in no
material difference to the reported contained metal. AMC has reviewed the updated report and
concurs with the general conclusion that any changes in the estimate are not material.
A number of shareholder queries have been received relating to the resource estimate review and
whether the remaining data of the Talisman Deeps resource model is included in the estimate. To
clarify, the resource estimate referred to above includes only that data from the modules forming the
Deeps in 2014, namely the Dubbo, Talisman and Woodstock zones which utilised the database of
historical production data, and an upgrade of the Mystery Vein resource estimate. It does not include
the remainder of the data, covering the Crown Mine and broader permit area, which will be evaluated
following receipt of the resource estimate.
In compiling the Talisman Deeps resource model, which was released as part of the company resource
estimate in 2017 the NTL team followed a very complex process for producing a resource estimate
based on the historical database of samples NTL acquired in 2014. The final resource estimate update
currently under review by AMC will confirm JORC 2012 compliance of the process NTL used to apply
historical data at the mine. The completion of the peer review allows the application of the same
process to the remaining data a majority of which relates to the historically productive Crown Vein at
the deeper levels of the mine.
3
Sampling and exploration
Activities at Mystery that aim to test grade and geological continuity further forward of the face of the
Vein were finalised and costed early in the quarter. Immediately prior to mobilising the underground
team the NZ government placed the country on the highest lockdown Level 4 which left no option but
to defer the Mystery Sampling.
While limited in the works underground the team focused on prioritizing activities which could be
undertaken while restrictions remain likely. Following a comprehensive review of the NTL database 3
target areas on the Permit were identified which could be readily accessed and which provide the
highest value data. Analysis of the first of these highly prospective target areas has commenced and
will be followed by a surface sampling program.
Talisman Mine Plan
As announced previously the Life of Mine level design continues to be developed. Recent gold prices
have risen to such an extent that the impact on the mine design and economic cut-off grade allows
for a review of areas such as larger parts of the Woodstock zone which are likely to become economic
at the current gold price. The period saw the completion of the main operational plan which broadly
sets out the developmental and infrastructure requirements needed to support the mine.
The work completed on the plan during the quarter and which will accompany an application for
mining will assist the team to
• Identify options for exploitation of the orebody and risk/reward analysis to identify the option
with the highest value outcome.
• Design flexible mining and engineering infrastructure required for the most favourable option,
• Adopt a long term mine development schedule and production profile.
The remaining work on the plan was used, as noted above, to identify areas, both within the bounds
of the existing mine and the larger permit area, with the potential for economic ore deposits which
can be readily accessed while restrictions and distancing measures are in place.
Following the completion of the resource estimate review the plan will be further developed to exploit
any areas within the resource which may not have been previously included.
4
Processing Plant
The Company commenced reviewing a number of potential sites for a plant giving the option of 2
district plans to operate under which will be determined following the application review process.
At the same time evaluation of the potential for a collaboration on an independent processing
operation is being undertaken which may provide an ability for an alternate funding structure to
develop a plant for toll treatment by Talisman.
More recently a series of discussions with a high-profile NZ industry group were advanced. The focus
was on the potential for a formal collaboration that could facilitate funding, delivery, and operation
of a joint processing plant as part of a broader industry offering. NTL is currently working on the
delivery of a heads of agreement setting out the key criteria that would need to be met for the
development of a Joint venture.
As announced, the resource consent for bulk sampling which allows 2 years from commencement of
transporting ore from the portal, has focussed on ensuring that the plant design and commissioning
are aligned with extraction activities and the full 2 years of extraction of the maximum volumes can
be achieved by seamless material handling from the vein through to processing at the plant.
Mining Resource Consent
NTL currently holds a resource consent at the Talisman Mine allowing bulk sampling of up to twenty
thousand cubic meters of ore per year for approximately two years. Securing the resource consent for
full scale commercial production to enable the Company to extract the maximum possible value from
the mines high grade mineral resource over the ten year plus mine life is a high priority.
During the quarter, an independent planner was contracted to assess the impact of planned mining
operations, which are broadly similar to those for which the operation is already consented, against
the requirements of the Operative Hauraki District Plan. This assessment is complete and has
identified a number of technical investigations that will be required to underpin the resource consent
application.
While much of the required information has been quantified through the underground rehabilitation,
prospecting and test mining programme over the past 2.5 years, there are some aspects that need
addressing by subject matter experts. Key individuals and groups with this expertise have been
identified and cost estimates and their availability have been sought.
Corporate
The board continues to maintain a 20% reduction in fees and salaries which were introduced in 2019
while the global economy remains uncertain. The team prioritised activities which provide the lowest
cost and that can be undertaken while restrictions are in place and the plant design application and
consenting processes are being finalised. This resulted in 3 targets deemed accessible and the
activities proposed allowed under current Level 3, being prioritized.
During the quarter, the company reviewed a number of opportunities of which a small NZ based
project with an existing ML and resource was under review when Level 4 lockdown was
5
implemented. Any further work has had to be delayed until restrictions are at an end and the site
can be accessed for field review.
Tenements Held
Rahu Resources –EP90144 100% New Talisman
Talisman Mine – MP51326 100% New Talisman Gold Mines Limited
About New Talisman Gold Mines Ltd
New Talisman Gold is a dual listed (NZSX & ASX: NTL) with over 2250 shareholders who are mainly
from Australia and New Zealand and has been listed since 1986. It is a leading New Zealand minerals
development and exploration company with a mining permit encompassing the Talisman mine, one
of New Zealand’s historically most productive gold mines. The company has commenced prospecting
and upgrading activities at the mine and advance the exploration project to increase its considerable
global exploration target into JORC 2012 resources.
Its gold properties near Paeroa in the Hauraki District of New Zealand are a granted mining permit,
including one of New Zealand’s highest-grade underground gold mines, a JORC 2012 compliant
mineral resource of over 469,000 ounces AuEq at an average above 15 g/t AuEq and a JORC compliant
reserve statement.
Data sourced from publicly available filings. Our datasets may not be complete. Automated analysis can produce errors. If you believe any data on this page is incorrect, please contact us at hello@nzxplorer.co.nz. For informational purposes only. Not investment advice.