Meridian Energy Limited logo

Harapaki wind farm project update

Operational Update23 August 2022MELUtilities

Release






M e r i d i a n E n e r g y L i m i t e d ( A R B N 1 5 1 8 0 0 3 9 6 ) A c o m p a n y i n c o r p o r a t e d i n N e w Z e a l a n d

287-2 9 3 D u r h a m S t r e e t N o r t h , C h r i s t c h u r c h 8 0 1 3


m e r i d i a n e n e r g y . c o . n z

Stock Exchange Listings NZX (MEL) ASX (MEZ)

Harapaki wind farm project update


24 August 2022

Meridian Energy is today providing an update on construction progress of its Harapaki wind farm in

Hawkes Bay, highlighting an expected $53m (13%) increase in costs. This will increase total project

capital costs from the original $395 million announced in February 2021 to $448 million.

The original first power milestone of June 2023 and full power by June 2024 both remain on

schedule in the project timeline, while the overall wind farm capacity of 176 MW is unchanged.

Meridian Energy Chief Executive Neal Barclay says multiple risks have eventuated since bulk

earthworks started in September 2021 and their magnitude exceeded cost expectations.

“The first construction season at Harapaki has been one of the wettest on record, with more than a

metre of rain on site in the last 3 months of 2021, while the first quarter of 2022 saw record rainfall

totals and damage inflicted by Cyclone Dovi. We have enjoyed more favourable weather conditions

since April 2022, which has helped maintain our overall programme, however that has required

additional civil crews”.

Mr Barclay says the combined impacts of the COVID pandemic, inflationary pressures and resource

constraints will impact the project’s overall costs. “The increase in inflationary pressures as well as

poor weather and COVID have combined to deliver an unavoidable impact on our project. To

maintain the project timeline, the team at Harapaki has also had to come up with innovative roading

design, which adds cost but mitigates future risk and I acknowledge them and our wider contractor

workforce in overcoming real adversity.”

“Harapaki’s economics remain very sound, and the renewable development outlook in New Zealand

has been made even more compelling by the Government’s Emissions Reduction Plan released last

month,” Mr Barclay says.


ENDS

Neal Barclay

Chief Executive

Meridian Energy Limited


For investor relations queries, please contact:

Owen Hackston

Investor Relations Manager

021 246 4772

For media queries, please contact:

Rheilli Uluilelata

External Communications Advisor

022 589 1052

HarapakiWind Farm
Project Update

24 AUGUST 2022

2
HARAPAKI WND FARM PROJECT UPDATE24 AUGUST 2022

Project overviewKey suppliers

SH5 egress

Located within the Hastings

District, approximately 50km

drive from Port Napier

Extending over 9km of the

MaungaharuruRange, covering

1,235 hectares

Elevation ranges from 730m at

the State Highway 5 entrance,

up to 1,100m at the highest

points

Transpower’s 220kV Whirinakito

Wairakei circuit passes across

the corner of the site

Meridian project delivery (not

EPC)

Supply, installation and maintenance

of 41 x 4.3MW direct drive wind

turbines

Construction of all roads, turbine

foundations and crane hardstands

Joint Venture

Supply, installation and commissioning

of substation and 220kV grid

connection

Electrical services for substation, cable

jointing and 33kV switchgear

installation

Supply, install and commissioning of

220/33kV transformers

Supply of 33kV reticulation cable

Today’s announcement
$53 million (13%) increase in total project capital costs from

the original $395 million announced in February 2021 to

$448million

Original first power milestone of mid 2023 and full power by

mid 2024 both remain on schedule

Wind farm capacity of 176 MW is unchanged

Additionalcivil costs to maintain overall programme against

the impact of very wet spring and summer conditions

COVIDimpacts of nationwide lockdown, prolonged Auckland

lockdown, workforce demarcations, ongoing infections

I

ncreasesin global material, labour, shipping costs, and

constraints across supply chains all mean an unavoidable

impact on the project

Revised roading design to address challengingsite geology,

improving resilience and site access

H

igher limestone extraction and processing emissions offset

by lower cement production/transport

3

HARAPAKI WND FARM PROJECT UPDATE24 AUGUST 2022

Civil Works, 60%

Inflation (incl. sea

freight), 31%

Erosion Repairs and Resilience, 4%

Electrical Works, 4%

Project Management, 1%

$53M Capital Cost Increase

4
Project update

HARAPAKI WND FARM PROJECT UPDATE24 AUGUST 2022

Schedule

On track

Mitigations put in place to

adapt to delays from COVID

lockdowns

Alterations made to pavement

design to allow working through

wetter conditions

Extra crews brought in to

maintain programme

Cost

13% increase, from:

COVID enforced delays

Record high rainfall

Inflation lifting escalation

amounts

Tight NZ labourconstruction

market

Global supply chain constraints

Capability

On track

Use of multi contract approach

with active management has

allowed the application of

mitigations

All contracts set at project

announcement protected most

overseas procurement from

commodity price rises

Holding expertise through detailed

design and construction allows

ability to effect change

5
Harapakikey project metrics

HARAPAKI WND FARM PROJECT UPDATE24 AUGUST 2022

February 2021August 2022Impact and notes

Generation capacity176MW176MW


unchanged

Expected annual output542 GWh542 GWh


unchanged

Capacity factor35%35%


unchanged

Capital project costs$395M

$2.24M/MW

$448M

$2.54M/MW


13% increase in costs

Expected first power datemid 2023mid 2023


on schedule

Expected full power datemid 2024mid 2024


on schedule

ASX 2024 Otahuhu Futures

(annual strip)

$122/MWh$172/MWh


40% increase in annual average

prices

Disclaimer
The information in this presentation was prepared by Meridian Energy with

due care and attention. However, the information is supplied in summary

form and is therefore not necessarily complete, and no representation is

made as to the accuracy, completeness or reliability of the information. In

addition, neither the company nor any of its directors, employees,

shareholders nor any other person shall have liability whatsoever to any

person for any loss (including, without limitation, arising from any fault or

negligence) arising from this presentation or any information supplied in

connection with it.

This presentation may contain forward-looking statements and projections.

These reflect Meridian’s current expectations, based on what it thinks are

reasonable assumptions. Meridian gives no warranty or representation as to

its future financial performance or any future matter. Except as required by

law or NZX or ASX listing rules, Meridian is not obliged to update this

presentation after its release, even if things change materially.

This presentation does not constitute financial advice. Further, this

presentation is not and should not be construed as an offer to sell or a

solicitation of an offer to buy Meridian Energy securities and may not be

relied upon in connection with any purchase of Meridian Energy securities.

This presentation may contain a number of non-GAAP financial measures,

including Energy Margin, EBITDAF, Underlying NPAT and gearing. Because

they are not defined by GAAP or IFRS, Meridian's calculation of these

measures may differ from similarly titled measures presented by other

companies and they should not be considered in isolation from, or construed

as an alternative to, other financial measures determined in accordance with

GAAP. Although Meridian believes they provide useful information in

measuring the financial performance and condition of Meridian's business,

readers are cautioned not to place undue reliance on these non-GAAP

financial measures.

The information contained in this presentation should be considered in

conjunction with the company’s financial statements, which are available at:

www.meridianenergy.co.nz/investors

All currency amounts are in New Zealand dollars unless stated otherwise.

6

HARAPAKI WND FARM PROJECT UPDATE24 AUGUST 2022

Data sourced from publicly available filings. Our datasets may not be complete. Automated analysis can produce errors. If you believe any data on this page is incorrect, please contact us at hello@nzxplorer.co.nz. For informational purposes only. Not investment advice.

Other issuers discussed similar conditions around this time

Matched by meaning across NZX announcement text, not keywords — based on our semantic index of announcement bodies.

  • CEN — Contact Energy Limited: 2022 Annual Shareholder Meeting
    2022-11-15

    Contact Energy Limited Level 2 Harbour City Tower, 29 Brandon Street, Wellington 6011 | PO Box 10742, Wellington 6143 P: +64 4 499 4001 | F: +64 4 499 4003 | W: contactenergy.co.nz Wednesday, 16 November 2022 CEO’s address to ASM Looking back over the past year, I feel…”