NZ’s biggest wind farm open for business
STOCK EXCHANGE LISTINGS: NZX (MCY) / ASX (MCY)
NEWS RELEASE
New Zealand’s biggest wind farm open for business
L-R Dr Megan Woods (Energy Minister), Prue Flacks (Mercury), Danielle Harris (Rangitāne o Manawatū)
4 May 2023 – Energy Minister Dr Megan Woods cut the ribbon to ceremonially “switch on” New Zealand’s
biggest wind farm today.
• Mercury’s Turitea Wind Farm in Manawatū adds 2% additional renewable energy to the country’s National Grid
• New Zealand’s largest wind farm will produce on average 840GWh each year, enough to power 120,000
households or 375,000 EVs
• Mercury has a strong pipeline of renewable development and is well positioned to continue developing
renewable projects at pace.
“New Zealand’s biggest wind farm is open for business, and we’re keeping up the pace with more new renewables
in construction, consented, and in the planning stages,” said Vince Hawksworth, Chief Executive.
“The energy sector is key to New Zealand’s low emissions future, and that’s reflected in the massive amount of
investment in the sector. Mercury invested nearly half billion dollars in to the Turitea Wind Farm and that’s just one
example of the commitment from across the sector in building new renewable generation,” said Vince.
Representatives of mana whenua Rangitāne o Manawatū, local government and community, and key contractors
attended the event, three and a half years after the ground-breaking in October 2019.
“A mighty team effort has landed this huge wind farm,” said Vince. “Turitea is a site of exceptional wind quality, and
our teams rose to the challenge of constructing 60 turbines and transmission infrastructure on its slopes. Over
2,500 people have worked together on this project to bring this new electricity to New Zealand.”
Mercury takes a long-term view when it comes to significant investment in new electricity generation, and this
includes our commitment to custodianship of this site. We acknowledge and thank Rangitāne, Department of
Conservation, our ecology specialists Wildlands, and the construction teams for the care they have taken to
safeguard the environment during construction.
The $465m project was announced in 2019 the same year the government passed the Zero Carbon Act that set up
a framework to achieve the aims of the 2015 Paris Agreement, including a target to reduce emissions of all
greenhouse gases (except biogenic methane) to net zero by 2050.
Turitea’s 33 northern turbines have been generating to the Grid since December 2021, and the southern 27
turbines are coming on stream with full operation scheduled for June. Our next project will be the 43MW Kaiwera
Downs Stage I, currently under construction near Gore, with commissioning scheduled for late this year. Our
pipeline of further projects is almost equivalent in size to Mercury’s existing generation portfolio with over
8,000GWh either in construction, consented or in consenting.
PROJECT DETAILS
Capacity and output 840GWh annually, enough to power 120,000 households or 375,000 EVs
Turbines 60 turbines, measuring 125m from ground to blade tip. Each blade is 55m long.
Transmission The 220kV transmission line and grid connection to Linton that will also cater for future
development of the consented Puketoi wind farm to the east
Contractors Vestas-New Zealand Wind Technology Limited, a local subsidiary of Vestas Wind
Systems A/S was contracted to construct and maintain the combined Turitea wind farm
development (engineer, procure and construct (EPC) contract and long-term service and
availability agreement)
Electrix and Transpower were contracted for the design and construction of the 220kV
transmission line and grid connection to Linton.
ENDS
Howard Thomas
General Counsel and Company Secretary
Mercury NZ Limited
For investor relations queries, please contact:
Paul Ruediger
Head of Business Performance & Investor Relations
021 38 10 10
investor@mercury.co.nz
For media queries, please contact:
Katy Scoullar
Communications and Community Engagement Manager
027 210 5337
mercurycommunications@mercury.co.nz
ABOUT MERCURY NZ LIMITED
We generate electricity from 100% renewable sources – hydro, geothermal and wind. We also sell utility services to our
customers through our retail brands – Mercury, Trustpower and GLOBUG. We’re listed on the New Zealand Stock Exchange
and the Australian Stock Exchange with foreign exempt listed status. We’re listed on both exchanges with the ticker symbol
‘MCY’. The New Zealand Government (the Crown) holds a legislated 51% shareholding in the Company.
Visit us at: www.mercury.co.nz
Data sourced from publicly available filings. Our datasets may not be complete. Automated analysis can produce errors. If you believe any data on this page is incorrect, please contact us at hello@nzxplorer.co.nz. For informational purposes only. Not investment advice.
Other issuers discussed similar conditions around this time
Matched by meaning across NZX announcement text, not keywords — based on our semantic index of announcement bodies.
- MEL — Meridian Energy Limited: Harapaki wind farm project update2023-07-17
“Release M e r i d i a n E n e r g y L i m i t e d ( A R B N 1 5 1 8 0 0 3 9 6 ) A c o m p a n y i n c o r p o r a t e d i n N e w Z e a l a n d 287-2 9 3 D u r h a m S t r e e t N o r t h , C h r i s t c h u r c h 8 0 1 3 m e r i…”
- MEL — Meridian Energy Limited: Meridian Energy Limited 2023 Interim Results2023-02-28
“m e r i d i a n e n e r g y . c o . n z PG 2 preparing to lodge consent applications for a new wind farm at Mount Munro in the Wairarapa and a 130MW solar farm, also at Ruakākā, both in the middle of 2023. We’re getting on with it,” adds Barclay. Meridian’s Harapaki win…”
- MEL — Meridian Energy Limited: Meridian Energy launches retail Green Bond offer2023-03-05
“4 Offer Highlights MARCH 2023RETAIL BOND OFFER IssuerMeridian Energy Limited (Meridian). Description 5.5 year unsecured, unsubordinated, fixed rate green bonds (Green Bonds). The Green Bonds are Green Debt instruments under Meridian’s Green Finance Framework dated February 2023 (…”