Fletcher Building/Announcement
Fletcher Building logo

Presentation for update on NZICC and WIAL Carpark projects

Investor Presentation4 February 2024FBUMaterials

Fletcher Building Limited, Private Bag 92114, Auckland 1142, 810 Great South Road, Penrose, Auckland 1061, New Zealand



Presentation for update on NZICC and WIAL Carpark projects


Auckland, 5 February 2024: Fletcher Building earlier today announced an update on the New

Zealand International Convention Centre and Hobson Street Hotel project (“NZICC”) and the

Wellington International Airport Carpark project (“WIAL Carpark”).


A short presentation is attached relating to today’s briefing.


Conference call to be held today


Fletcher Building management will host a Q&A briefing for investors and analysts today at

12:00pm NZDT / 10:00am AEDT to discuss today’s announcement. Participants can register for

the conference by navigating to the following link:


https://s1.c-conf.com/diamondpass/10036826-yu785e.html


Upon registration you will be provided with the dial in number, passcode, and your unique access

PIN. To join the conference simply dial the number and enter the passcode followed by your PIN,

and you will join the conference instantly.


A replay facility will be available after the conference call.


#Ends

Authorised by:

Ashleigh Harding

Company Secretary

For further information please contact:

MEDIA

Christian May

General Manager – Corporate Affairs

+64 21 305 398

Christian.May@fbu.com

INVESTORS AND ANALYSTS

Aleida White

Head of Investor Relations

+64 21 155 8837

Aleida.White@fbu.com

---

Fletcher Building Limited
Update on

NZICC and WIAL

Carpark Projects

5 February 2024

NZICC Update
Project remains on track for completion by end of calendar 2024, significant milestones delivered

▪NZICC remains on track for final completion by end of calendar 2024

▪Milestones to date:

▪Carparks complete

▪Steel remediation 98% complete

▪Hobson Street Hotel in final commissioning phase, hand over in Feb-24

NZICC -South FacadeNZICC –Operable Wall InstallAirbridge connecting Horizon Hotel & NZICC

NZICC Theatre SeatingUnderground Entrance to Horizon Hotel

Page 2| Fletcher Building Limited Update on NZICC and WIAL Carpark Projects | © February 2024

NZICC Update
Fire remediation works close to complete -majority of remaining scope back to completing original contract works

Basement Car Parks

Works Completed

Hotel completion

February 2024

NZICC completion

Late Calendar 2024

B4

L6

L5

L4M

L3

L2

L1

B1

B2

B3

Page 3| Fletcher Building Limited Update on NZICC and WIAL Carpark Projects | © February 2024

NZICC Update
Additional provision announced today of $165m is mainly from higher costs of steel remediation, and the updated

forecasts to complete the interior fit-out & operating systems install from the original contract scope

▪Additional NZICC provision mainly due to higher actual and forecast costs to complete the project

▪Largest single cost increase from steel remediation: work now broadly complete, but productivity

has been lower than forecast –greater resources required for a longer period

▪Encapsulation, stripping/blasting, repainting 3 coats on all NZICC primary and secondary steel

▪Up to 500 people, plus encapsulation and access equipment, burn rate c$750k / day

▪Other cost increases from refining scope and procuring subcontractor resource to complete

remaining parts of project: esp. internal fit-out and installation of operating systems

▪c. 5000 drawings, c. 200 subcontractor packages on remaining scope

▪Some original suppliers insolvent or no longer available (e.g. operable doors, theatre/AV),

work packages re-tendered

▪Limited capacity in commercial trades, pressure on rates

▪Some challenges in securing remaining Contract Works Insurance (CWI) revenue, smaller portion

of latest provision due to risk of non-recovery of these revenues

▪Cost and revenue risk remains through to completion of project

▪Consistent with prior position, no Third Party Liability (TPL) revenue is included in the project

forecast. FBU is pursuing TPL claims of >$100m, likely to take significant period to resolve (FY25+)

NZICC -L5 Stage Wall Blackout

Horizon Hotel Corridor

Page 4| Fletcher Building Limited Update on NZICC and WIAL Carpark Projects | © February 2024

NZICC Update
Cash flow impact of additional provision is expected to be spread across 2H24 and 1H25

▪Previous expectation was for a cash outflow on NZICC of c. $300m in FY24, ahead of a small positive cash inflow in FY25

▪Based on the latest provision, the cash outflow in FY24 is now expected to be c. $370m, followed by a cash outflow in FY25 ofc.$80m

▪Cash flow phasing remains subject to risk on timing of claim recoveries and project costs

▪No Third Party Liability (TPL) revenue is included in the cash flow forecasts

▪All cash flows shown are pre-tax

NZICC cash-flowFY24 TotalFY25

Prior Forecastc.$300m outflowc.$15m inflow

Latest Forecastc.$370m outflowc.$80m outflow

Page 5| Fletcher Building Limited Update on NZICC and WIAL Carpark Projects | © February 2024

Wellington Airport Carpark Update
Provision of $15m for estimated costs to remediate quality issues

▪Fletcher Construction (FCC) has been discussing technical solutions

with Wellington International Airport Limited (WIAL) to remediate

quality issues on the airport carpark

▪While the solution has not yet been agreed with WIAL, FCC considers

that it now has an effective solution and a robust estimate of the cost

to undertake the remediation. The $15m provision reflects these

expected remediation costs

▪Cash-flow impact of the provision is expected to be through calendar

2024

▪Additional claims exist in both directions between FCC and WIAL.

Upside and downside risk exists on settlement of these claims

Page 6| Fletcher Building Limited Update on NZICC and WIAL Carpark Projects | © February 2024

Important Information
ThispresentationhasbeenpreparedbyFletcherBuildingLimitedanditsgroupofcompanies(“FletcherBuilding”)forinformationalpurposes.Thisdisclaimerappliestothis

documentandtheverbalorwrittencommentsofanypersonpresentingit.

TheinformationinthispresentationhasbeenpreparedbyFletcherBuildingwithduecareandattention,however,neitherFletcherBuildingnoranyofitsdirectors,employees,

shareholdersnoranyotherpersongivesanyrepresentationsorwarranties(eitherexpressorimplied)astotheaccuracyorcompletenessoftheinformationandtothemaximum

extentpermittedbylaw,nosuchpersonshallhaveanyliabilitywhatsoevertoanypersonforanyloss(including,withoutlimitation,arisingfromanyfaultornegligence)arising

fromthispresentationoranyinformationsuppliedinconnectionwithit.

ThispresentationcontainsnotonlyinformationaboutactionstakenbyFletcherBuildinganditsoperations,butalsosomeforwardlookingstatements,thatisstatementsrelatedto

future,notpast,intentions,eventsorothermatters.Forwardlookingstatementsmayincludestatementsregardingourintent,belieforcurrentexpectationsinconnectionwiththe

informationavailabletoFletcherBuilding.Suchforwardlookingstatementsarebasedoncurrentexpectations,estimatesandassumptionsandaresubjecttoanumberofrisksand

uncertainties,includingmaterialadverseevents,significantone-offexpensesandunforeseeablecircumstances.Actualfiguresorestimatesmaydiffermateriallyfromthose

projected.Exceptasrequiredbylaw,ortherulesofanyrelevantstockexchangeorlistingauthority,nopersonisunderanyobligationtoupdatethispresentationatanytimeafter

itsreleaseortoprovidefurtherinformationaboutFletcherBuilding.

Theinformationinthispresentationdoesnotconstitutefinancialproduct,legal,financial,investment,taxoranyotheradviceorarecommendation.

Page 7| Fletcher Building Limited Update on NZICC and WIAL Carpark Projects | © February 2024

Data sourced from publicly available filings. Our datasets may not be complete. Automated analysis can produce errors. If you believe any data on this page is incorrect, please contact us at hello@nzxplorer.co.nz. For informational purposes only. Not investment advice.

Other issuers discussed similar conditions around this time

Matched by meaning across NZX announcement text, not keywords — based on our semantic index of announcement bodies.

  • AIA — Auckland International Airport Limited: AIA – FY24 Interim Results
    2024-02-21

    2024 Highlights Financial performance Building a better future Outlook Interim Results Page 18 Continued focus on improving efficiency and customer experience Collaboration with stakeholders •The rapid ramp-up in international travel resulted in passenger processing being be…”

  • IFT — Infratil Limited: Infratil Investor Day 2024
    2024-03-04

    Wellington International Airport Limited Infratil Investor Day March 2024 Matt Clarke, Chief Executive 2 Business Overview & FY24 Outlook Passenger Traffic Regulatory Environment Capex Plans PSE5 Progress FY25 Drivers Wellington Airport Update Wellington Airport Overview Gatew…”

  • PFI — Property for Industry Limited: Annual Meeting Presentation and Speeches
    2024-04-02

    NZX and media announcement — 3 April 2024 Moreover, our sustainability efforts remain a core focus. We've made significant progress in this area by embedding an in-house sustainability-focused facilities management team and advancing solar and power metering initiat…”