Tauhara commissioning progress update
Commissioning works at Contact’s Tauhara geothermal plant have been progressing well,
with remedial work to the steam separation plant successfully completed.
Power station commissioning activities are expected to commence shortly, with first
synchronisation to the system occurring in late April / early May 2024 at the earliest. After
completion of power station testing activities, the 30-day reliability run required to support
commercial operations could begin in late May 2024.
Contact maintains its expectation that Tauhara will be online at an initial capacity of at least
152MW in Q3 2024 and notes that a range of timing outcomes within the quarter remain
possible. This reflects the potential discovery of latent commissioning issues in the next
stage of power station testing, as can be expected during commissioning. Within that
context, this progress announcement seeks to highlight the possibility that Tauhara could be
online for winter 2024.
The project team continues to work tirelessly to accelerate the Tauhara commissioning
timeline to deliver this worldclass geothermal project. Seeing Tauhara online will be a key
milestone in the delivery of Contact26, Contact’s strategy to lead the decarbonisation of New
Zealand.
- ends -
Investor enquiries
Shelley Hollingsworth
Investor Relations and Strategy Manager
+64 27 227 2429
shelley.hollingsworth@contactenergy.co.nz
Media enquiries
Louise Wright
Head of Communications and Reputation
+64 21 840 313
louise.wright@contactenergy.co.nz
Data sourced from publicly available filings. Our datasets may not be complete. Automated analysis can produce errors. If you believe any data on this page is incorrect, please contact us at hello@nzxplorer.co.nz. For informational purposes only. Not investment advice.
Other issuers discussed similar conditions around this time
Matched by meaning across NZX announcement text, not keywords — based on our semantic index of announcement bodies.
- MCY — Mercury NZ Limited: Growth continues, renewables underpin performance2024-02-19
“Key messages •Electricity futures three year forward price stable over HY24, this is partly a result of higher short term prices offsetting lower mid to long term prices •Short term futures pricing impacted by hydrology, generation commissioning delays, peak demand growth, av…”
- MEL — Meridian Energy Limited: Meridian Energy Limited 2024 Interim Results2024-02-27
“20 Energy policies from the new coalition government Hydrogen and other fuels §Plan for transitional low carbon fuels including hydrogen infrastructure §A Hydrogen National Policy Statement to be introduced to provide investment certainty Resource Management Act (RMA) reform §R…”
- SPN — South Port New Zealand Limited: Challenging market conditions impact South Port’s result2024-02-15
“was completed and officially opened on 20 November 2023. Shipments for the second stage of the development, although not confirmed, are expected to begin arriving in early 2025. A fast-track resource consent application for Contact Energy’s Southland Wind Farm project, was l…”