Santana Minerals Ltd logo

Mining Studies Update

Operational Update21 April 2025SMIMaterials

1


22 April 2025


BOGP –– NEW RAS OPEN PIT STAGES


The Board of Santana Minerals Limited (SMI, ‘Santana’ or the ‘Company’) has previously advised its

intent to refine its initial Pre-feasibility Study (PFS) for its Bendigo-Ophir Gold Project (BOGP) released

on November 15, 2024, using the new drill results and revised Mineral Resource Estimate (MRE)

announced on March 4, 2025.

These works have so far been focussed on selective and manual pit designs on the Rise and Shine (RAS)

deposit with a two-fold purpose:

1. Improved staging of open pits in the initial years with a priority focus on the extraction of the

High-Grade (HG1) domain resource subset which contains a total MRE of 1.07 million ounces

of gold at an average grade of 4.7g/t with the Indicated component being 6.4 million tonnes

at 4.5g/t containing 919,000 ounces.

2. Estimating the minimum necessary overburden removal to enable a sustainable supply of ore

for processing. In doing so, lowering the pre-strip capital burden for the operations to become

self-sustaining from a cash flow perspective earlier in the project.

The outcomes of these studies are:

▪ The revised pit staging means the volume of pre-strip to expose ore can be 7.9 million bank

cubic metres (bcm) down from 15 million bcm modelled in the November 2024 PFS.

▪ Five initial stages of open pit mine designs result in 30.5 million bcm of total material for an

undiluted 5.95 million tonnes of Indicated resource at a grade of 3.38g/t containing 617,000oz

of gold (97% Indicated category).

Work on modifying factors related to ore dilution and the next phases of open pit and/or underground

mining is ongoing and will be incorporated into a forthcoming PFS Update expected in the ensuing

quarter. These continued efforts, focused on reducing the capital impost for development, may render

the current PFS mining strategy superseded. As such, shareholders should not consider the existing

PFS as the preferred development plan for the BOGP. The Company intends to present its revised

development strategy in the PFS Update.

Santana CEO, Damian Spring commented:

“This progressive step in finessing our initial PFS demonstrates the option to significantly reduce the

pre-strip volume. Smarter pit staging clearly rebalances the waste removal equation in the initial stage

and has the potential to re-shape the project’s capital burden. Furthermore, it shouldn’t be lost on the

investor that the Australian dollar gold price has risen over 25% since the initial PFS which substantially

enhances the robustness of the project.”




Announcement

ASX:SMI

NZX:SMI




2



Open Pit Mining – PFS Revisions

The initial PFS released in November 2024 assumed a much larger pre-strip as a critical path to gold

production, removing approximately 15 million bcm of bulk waste overburden with large scale mining

fleets. The geometry of the underlying orebody meant a significant ore stockpile and consequent glut

of mill feed for future production years, with inconsistent balance of waste and ore stripping over the

mining cycles.

As opposed to the global optimisation process applied in the initial PFS, a series of selective and

manually designed open pits with progressive cut-backs have now been designed. These all fall within

the ultimate pit design as outlined within the initial PFS and provide for a more balanced waste to ore

mining process. It should be noted at this point there remains further stages of mining to be refined

along with the integration of underground mine development for longer term sustainable ore

production. These works are progressing and will be presented in a wholesome PFS Update this

quarter.

The table below summarises the ore and waste inventories in the initial five stages of RAS manual pit

designs when intersected with the current MRE.

STAGE

TOTAL CONTAINED ESTIMATE FROM MRE

(undiluted)

WASTE

VOLUME

%

INDICATED

ROUNDED TOTALS

VOLUME TONNES GRADE OUNCES

(bcm) (t) (g/t) (oz) (bcm)


STAGE 1 287,400 783,600 1.56 39,350 7,920,000

93%

STAGE 2 305,000 831,000 2.23 59,600 4,112,000

100%

STAGE 3 - - - - 7,350,000


STAGE 4 359,500 976,200 3.59 112,750 5,351,000

100%

STAGE 5 1,239,900 3,364,700 3.75 405,300 5,791,000

96%

TOTAL 2,191,800 5,955,500 3.38 617,000 30,524,000

97%

Table 1. Mineral inventory contained in RAS updated pit stages (1 to 5)

RAS Revised Open Pit - Staged Mining Sequence

The updated RAS pit stages focus on the minimum pre-strip scenario by vectoring pit shells on near

surface ore at the southern end of the RAS deposit. The designs now incorporate updated advice on

geotechnical parameters which include minor wall angle improvements, achieved since the PFS.

While the average grade is lower at the southern end of RAS, this approach supports the early

establishment of sustainable ore production in a balanced manner, enabling a progressive ramp-up in

output. It also allows bulk stripping of subsequent pit stages to proceed in parallel without impacting

overall productivity.






3


RAS PIT STAGING STRATEGIC PLAN

Each stage of mining is defined and summarised below.

STAGE 1 – STARTER PIT




The Stage 1 Pit is designed to access near-

surface resource blocks at a grade of ~1.6g/t at

RAS South. This stage will be completed by

excavating ~7.9 million bcm of TZ3 waste to

expose ore for commissioning the plant.

The TZ3 bulk waste overburden will be stripped

off the deposit until exposure of the Thomson

Gorge Fault (TGF) interface, then the ore zone

beneath the TGF will undergo detailed control

practices and then be selectively mined with an

appropriately sized ore fleet.

The gold resource at RAS South inside Stage 1

includes 783kt at 1.56g/t of undiluted mineral

resources.

STAGE 2




The Stage 2 Pit incorporates a new ramp to

maintain access to the pit floor as the Stage 1

ramp is mined out.

The pit floor is mined down to the 590RL

providing access to higher grade resource

blocks. Stage 2 provides access to future pit

stages (Stage 3 and 4).

Stage 2 contains 4.1M bcm of waste rock and

831kt at 2.23g/t of undiluted mineral resource.


Indicated

Inferred

Indicated

Inferred




4


STAGE 3




The Stage 3 Pit is excavated concurrently with

Stage 2 with scheduling focussed on

continuous exposure of ore.

The Stage 3 Pit is essentially the strip out of the

northern section area to its full dimensions in

preparation for chasing the HG1 (high-grade

core) as it dips away from the pit.

Waste stripping is focused on ultimately

establishing a flat floor at the 655RL, to enable

easy access into the Stage 4 pit.

The Stage 3 Pit mines 7.3M bcm of waste rock

to expose Stage 4 ore.

STAGE 4




The Stage 4 Pit selectively strips waste as the

move north continues to expose the upper

zones of the HG1 domain.

This stage enables exposure of significantly

higher grades, increasing to 3.6g/t. The pit

advances 80m north down to the 570RL,

excavating the high-grade core while

maintaining strict control of the permanent

eastern wall, situated on the western side of

Battery Hill.

A permanent ramp is cut in at the 630RL

servicing Stage 4 and Stage 5, exiting at a low

point in Ferret Gully, to the north.

Stage 4 is mined to 570RL and contains 5.1M

bcm of waste rock and an undiluted resource

of 976kt at 3.59g/t.




Indicated

Inferred

Indicated

Inferred




5


STAGE 5




The Stage 5 Pit mines the western side of the

high-grade domain at 3.75g/t.

Mined to the 520RL, Stage 5 contains 5.7M

bcm of waste rock and exposes an undiluted

3.3Mt at 3.75g/t of mineral resources.

This ore will be progressively exposed and

mined to fulfill ore processing requirements

whilst additional waste stripping in future

stages expose additional open pit ore supply.

Stage 6 is likely to continue coincident with

Stage 5, however it remains subject to design

considerations as part of the efficient pit stage

planning toward the ultimate shell. Further, its

integration with a proposed underground

development also requires detailed

scheduling.


The progressive and initial open pit staging as illustrated in Figure 1, shows the pre-strip required to

access mill feed in Pit Stage 1 (blue line), with subsequent cut backs to access the HG1 domain (mauve

shape). The LG1 domain (green shape), is classified in the Indicated JORC category, and averages

1.5g/t. Figure 1 also shows subsequent pit stages in long section, focused on extraction of the HG1

domain, while staging through LG1 to minimise the pre-strip and fund the project within 12 months

from mining.

Indicated

Inferred




6



Figure 1. RAS Long Section showing pit stages and HG1/LG1 domains

Figure 2 below presents the revised pit stages in plan view, focusing on RAS South and progressively

cutting back toward the HG1 domain.


Figure 2. RAS plan view showing pit stages and HG1/LG1 domains




7


Figure 2 also shows the pre-strip required to access mill feed in Stage 1 (blue line), this time with

reference to the JORC-category resource domains (Inferred and Indicated), showing the focus on

Indicated material for all stages.


Figure 3. RAS Long Section showing pit stages and JORC resource categories

Figure 4 below shows the revised pit stages in plan-view, and shows the focus on Indicated resources

that underpin the revised mine plan.




8



Figure 4. RAS plan view showing pit stages and JORC resource categories

Key Outcomes of the Revised Option

This review of open pit staging shows there is imminent flexibility in the ultimate development

strategy for the RAS orebody.

Depending on the quantity and timing of capital allocated to waste pre-strip that the Company

chooses to endure, the revised options potentially allow for a more cost-effective mining ramp-up.

Under this revised plan, the first five stages intersect 617,000 ounces of the undiluted Mineral

Resource model.

Santana is pleased to present this interim development pathway as part of its broader update to the

initial PFS. While mining studies continue on further open pit stages and the integration of

underground operations, work is also advancing on process plant sizing, flow sheet refinement, and

revised capital estimates for the plant and associated infrastructure. Updates on these elements will

be released as they become available in the coming weeks.

The Company remains focused on delivering a development plan that is both realistic and achievable,

while continuing to seek opportunities for improvement as it progresses through the permitting

process. The updated PFS, which is scheduled to be released this quarter, will provide a refined

strategy for the development and funding of the project, reflecting what Santana believes will be

materially improved outcomes.





9



This announcement has been authorised by the Board.

Enquiries:


Damian Spring

Exec. Director & CEO

dspring@santanaminerals.com

Sam Smith

Exec. Director Corp Affairs & IR

ssmith@santanaminerals.com


10


Bendigo-Ophir Gold Project Mineral Resource Estimate

The Project contains a Mineral Resource Estimate (MRE) calculated at a cut-off grade of 0.5 g/t Au with top

cuts applied, as at March 2025:


Deposit Category tonnes (Mt) Au grade (g/t)

Contained

Gold (koz)

RAS

Indicated 18.9 2.5 1,538

Inferred 7.6 2.2 542

RAS Total Indicated and Inferred 30.6 2.3 2,080

CIT Inferred 1.2 1.5 59

SRX Indicated 2.2 0.8 54.7

SRX Inferred 2.9 1.0 90.5

SRX Total Indicated and Inferred 5 0.9 145

SRE Indicated 0.4 0.8 10.3

SRE Inferred 1.1 1.2 42

SRE Total Indicated and Inferred 1.5 1.1 52

BOGP Total

Indicated 21.5 2.3 1,603

Inferred 12.7 1.8 734

BOGP Total Indicated and Inferred 34.2 2.1 2,337

Table 2. Bendigo-Ophir Gold Project Mineral Resource March 2025

Previous Disclosure - 2012 JORC Code

Information relating to Mineral Resources, Exploration Targets and Exploration Data associated with the Company’s

projects in this announcement is extracted from the following ASX Announcements:

• ASX announcement titled “Bendigo-Ophir Gold Project – Pre-Feasibility Study” dated 15 November 2024

• ASX announcement titled “RAS Mineral Resource Estimate Review” dated 4 March 2024


A copy of such announcements is available to view on the Santana Minerals Limited website www.santanaminerals.com.

The reports were issued in accordance with the 2012 Edition of the JORC Australasian Code for Reporting of Exploration

Results, Mineral Resources and Ore Reserves. The Company confirms that it is not aware of any new information or data

that materially affects the information included in the original market announcements. The Company confirms that the

form and context in which the Competent Person’s findings are presented have not been materially modified from the

original market announcements.

Current Disclosure - Competent Persons Statement

The information in this report that relates to the March 2025 RAS Mineral Resource Estimates (MRE) and to the November

2024 SRX and SRE MRE, is based on work completed by Mr Kerrin Allwood, a Competent Person (CP) who is a Member of

The Australasian Institute of Mining and Metallurgy (AusIMM). Mr Allwood is a Principal Geologist of GeoModelling

Limited, Petone, New Zealand and has sufficient experience which is relevant to the style of mineralisation and type of

deposit under consideration and to the activity which is being undertaken to qualify as a Competent Person as defined in

the 2012 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. Mr

Allwood consents to the inclusion in this report of the matters based on his information in the form and context in which

it appears. Mr Allwood and GeoModelling Limited are independent of Santana Minerals Ltd.

The information in this report that relates to prior 2021 Mineral Resource Estimates (2021 MRE) for CIT deposit completed

by Ms Michelle Wild (CP) (ASX announcement on 28 September 2021) continue to apply and have not materially changed.

The Company confirms that the form and context in which the Competent Persons’ findings are presented have not been

materially modified.


11


Forward Looking Statements

Forward-looking statements in this announcement include, but are not limited to, statements with respect to Santana’s

plans, strategy, activities, events or developments the Company believes, expects or anticipates will or may occur. By their

very nature, forward-looking statements require Santana to make assumptions that may not materialise or that may not

be accurate. Although Santana believes that the expectations reflected in the forward-looking statements in this

announcement are reasonable, no assurance can be given that these expectations will prove to have been correct, as

actual results and future events could differ materially from those anticipated in the forward-looking statements.

Accordingly, viewers are cautioned not to place undue reliance on forward-looking statements. Santana does not

undertake to update publicly or to revise any of the included forward-looking statements, except as may be required

under applicable securities laws.

Data sourced from publicly available filings. Our datasets may not be complete. Automated analysis can produce errors. If you believe any data on this page is incorrect, please contact us at hello@nzxplorer.co.nz. For informational purposes only. Not investment advice.