March quarterly report
The Board of Santana Minerals Ltd (ASX/NZX: SMI, "Santana" or "the Company") is pleased to report a quarter of strong
advancement across technical, regulatory, and strategic fronts at its flagship Bendigo-Ophir Gold Project (BOGP) in New
Zealand. The March quarter builds on the momentum from the Pre-Feasibility Study (PFS) completed in November
2024 and represents a shift from conceptual planning to tangible execution, with key milestones achieved in resource
definition and mine design, with permitting also well advanced.
Key Highlights
Operations
▪ During the quarter, an updated Mineral Resource Estimate (MRE) announced on 4 March 2025 lifted Rise and
Shine’s (RAS) Indicated inventory to 1.54 million ounces of gold at 2.5g/t, reinforcing confidence in mine
scheduling and providing a more robust platform for early production planning.
▪ An updated ‘HG1’ high-grade domain (1.07 million ounces at 4.7g/t) was delineated following reinterpretation
of the high-grade boundary at Rise and Shine (RAS) and now hosts approximately 60% of the deposit’s
Indicated ounces. HG1 is the focal point for mine planning and underpins the prioritisation of high-grade
material in the production schedule.
▪ Subsequent to quarter end, revised RAS open pit designs announced on 22 April 2025 reduced initial pre-strip
requirements by 47%, enabling earlier access to ore with only 7.9 million bank cubic metres (bcm) of waste to
be removed, compared to 15 million bcm in the PFS. The updated staging sequence begins at RAS South and
supports a more capital-efficient development profile.
▪ Drilling at RAS South aimed at infilling areas of the deposit in revised early pit stages identified mineralised
extensions beyond current pit boundaries, enhancing optionality and supporting greater flexibility in early mill
feed scheduling.
▪ In accordance with statutory processes, a Mining Permit Application (MPA) was lodged with NZPAM formalising
the Company’s transition from explorer to developer and further establishing the maturity of the BOGP.
▪ Final preparations are underway for the Fast-track Approvals (FTA) application to be submitted in June, which
is expected to enable a streamlined process with decisions delivered within six months from application.
▪ A PFS Update is now progressing to incorporate the revised pit staging, capital efficiencies, and refined
scheduling, forming the technical basis for development execution and upcoming funding decisions.
Corporate & Finance
▪ Emma Scotney was appointed to the Board as a Non-Executive Director during the quarter, bringing extensive
legal, commercial and governance experience to support the Company as it advances toward development of
the BOGP.
▪ The Company was added to the S&P/ASX All Ordinaries Index as part of the March 2025 quarterly rebalance,
a milestone viewed as a strong endorsement of its strategic direction and operational progress.
▪ 77.2 million options were converted during the quarter resulting in a total of ~A$36 million of cash inflow from
the tranche of options between the issue date and expiry date at the end of February 2025.
▪ The Company concluded the quarter with gross cash of ~A$55.35 million.
Enquiries
Damian Spring
Exec. Director & CEO
dspring@santanaminerals.com
Sam Smith
Exec. Director Corp Affairs & IR
ssmith@santanaminerals.com
ASX RELEASE
ASX:SMI
NZX:SMI
2
Operational Activities – Bendigo-Ophir Gold Project (“BOGP”)
The BOGP continues to evolve into New Zealand’s most advanced undeveloped gold project, backed by a growing
Mineral Resource base and now positioned within a regulatory framework that actively supports expedited
development. With the release of the initial PFS in late 2024 and the subsequent nomination to the Fast-track
Approvals process, the project has entered a new phase of strategic execution. Work during the March quarter has
focused on refining the development pathway by optimising mine staging, improving capital efficiency, and aligning
the technical schedule with solid progress made towards permitting milestones. Together, these developments are
converging into a cohesive, low-risk development story, one that is designed to be both capital-resilient and execution-
ready.
Following the release of the PFS, the Company entered a focused phase of development planning aimed at converting
study-phase concepts into executable outcomes. Detailed work during the quarter centred on optimising early-stage
pit staging and refining engineering designs, with the clear objective of reducing initial waste movement, prioritising
higher-margin ore, and establishing a more capital-efficient pathway to first gold.
Revised RAS Pit Staging (Subsequent to Quarter End)
Re-staging the RAS pit designs in the early phases of open pit mining has delivered a standout result. Ore can now be
accessed after moving just 7.9 million bcm of waste in Stage 1 which represents a 47% reduction in pre-strip volume
compared to the PFS. Across the first five stages of pits, the inventory contains 5.95Mt at 3.38g/t Au (for 617koz Au
with 97% in the Indicated category), with significantly smoother ore-to-waste ratios.
This could result in considerably lower upfront capital demand, earlier gold production, and improved financial
resilience. These refinements support a more attractive funding profile and accelerate the path to self-sustaining
operations.
Key geotechnical inputs have also been updated, including slightly improved wall angles allowing for tighter shells and
more efficient material movement. This has supported the definition of a more practical and capital-efficient series of
starter pits focused on RAS South.
Importantly, this revised scheduling is likely to support ore commissioning shortly after plant handover, allowing bulk
stripping for later stages to proceed in parallel with gold production. The table below summarises the ore and waste
inventories in the initial five stages of RAS manual pit designs when intersected with the current MRE.
STAGE
TOTAL CONTAINED ESTIMATE FROM MRE
(undiluted)
WASTE
VOLUME
%
INDICATED
ROUNDED TOTALS
VOLUME TONNES GRADE OUNCES
(bcm) (t) (g/t) (oz) (bcm)
STAGE 1 287,400 783,600 1.56 39,350 7,920,000
93%
STAGE 2 305,000 831,000 2.23 59,600 4,112,000
100%
STAGE 3 - - - - 7,350,000
STAGE 4 359,500 976,200 3.59 112,750 5,351,000
100%
STAGE 5 1,239,900 3,364,700 3.75 405,300 5,791,000
96%
TOTAL 2,191,800 5,955,500 3.38 617,000 30,524,000
97%
Table 1. Mineral inventory contained in RAS updated pit stages (1 to 5)
Figure 1 below presents the initial five pit stages in plan-view showing the progression toward the HG1 domain (purple
shape). Pit Stage 1 targets near-surface, lower-grade ore (1.56g/t Au) at RAS South, accessible beneath 7.9 million bcm
of overburden.
3
Figure 1. RAS plan view showing pit stages and HG1/LG1 domains
Figure 2. RAS Long Section showing pit stages and HG1/LG1 domains
4
The long-section view above (Figure 2) shows the movement of material required to access ore in Pit Stage 1 (blue
line), with subsequent cut-backs to the north accessing the HG1 domain. While early pit stages access ore in LG1, it is
notable that the average grades are well above 1.5g/t.
Underground mine integration studies are also underway, focused on timing, access designs and open pit interface.
This work is evaluating the potential to bring forward portions of high-grade underground material in tandem with pit
cutbacks, subject to the revised dilution and cost modelling now in progress.
Work on modifying factors (dilution, mining method, underground scenarios) continues and will feed into a PFS Update,
on track for release in the ensuing quarter. This update will present a clearer, de-risked development case for
investment decision-making.
RAS Mineral Resource Estimate (MRE) – March 2025
The updated MRE for the RAS deposit, released on 4 March 2025, marks a key advancement in the overall development
trajectory of the BOGP. The Indicated component of the resource now stands at 18.9Mt at 2.5g/t Au for 1.54Moz,
representing a 6.4% increase in contained ounces and a 7% uplift in grade compared to the July 2024 estimate.
Importantly, the MRE now incorporates an additional 7,060 metres of infill drilling since the July 2024 model and
includes refined geological domaining, particularly within the ‘HG1’ high-grade core. The HG1 domain alone now
contains 1.07Moz at 4.7g/t Au, with 919koz in the Indicated category, and has become the central focus of the revised
mining strategy.
The increased Indicated inventory has also enabled the re-optimisation of pit stages to target high-confidence ounces
in the southern part of the RAS deposit, resulting in a substantially reduced pre-strip requirement. The refined block
model also inherently enhances confidence in dilution control and underpins more accurate scheduling, both of which
are critical inputs for the PFS Update.
This revised MRE at RAS is a cornerstone of the Company’s funding and development strategy. It provides not only the
geological foundation for the reworked mine plan but also improves the robustness of technical assumptions required
for project financing and investment decision-making. The table below shows the tonnages and grades at RAS as they
stand in the March 25 MRE.
March 2025 RAS Mineral Resources Estimate (0.5g/t cut-off grade)
Deposit Category Tonnes (Mt) Au (g/t) rounded Contained Gold (koz)
RAS
Indicated 18.9 2.5 1,538
Inferred 7.6 2.2 542
RAS Total Indicated and Inferred 26.5 2.4 2,080
Table 2. Updated RAS March 25 MRE Report
Figure 3 below shows the new March 2025 Indicated (red) and Inferred (green) MRE domains which are the focus of
mine planning from open pit and underground perspectives. The blue traces are the previous July 2024 MRE extents.
The resource model (MRE) has also been refined in terms of geometry, with tighter control over southern and eastern
boundaries, enabling more confident pit optimisations that minimise the strip ratio.
5
Figure 3. March 25 MRE Indicated and Inferred Domains
Extension and Infill Drilling
In preparation for mining, drilling during the March quarter focused on defining the outer margins of the deposit to
concentrate mine designs around high-grade controls and guide pit optimisation in the most economically significant
zones. This work continued to enhance geological confidence and expand the mineable footprint of the RAS deposit.
Two major drilling campaigns were completed during the period: one targeting the eastern perimeter of the RAS pit,
and another focused on the underexplored southern margins (Figure 4). Both programs were designed to inform final
pit wall positions and convert Inferred material to Indicated ahead of mine scheduling.
The eastern margin program focused on defining the limits of the high-grade core, where mineralisation transitions
rapidly into narrower, lower-grade zones. This work successfully confirmed the outer limits of economic mineralisation
and will support refined wall designs that may reduce strip ratios.
6
Notable results from this program included:
▪ MDD387: 14.0m @ 7.4g/t Au from 155.0m
▪ MDD390: 23.0m @ 1.5g/t Au from 270.0m
▪ MDD393: 21.0m @ 1.4g/t Au from 279.0m
Figure 4. Plan of RAS Eastern margin & Southern extension Drilling – Notable Intercepts
Drilling at RAS South, where historical access was limited by topography, delivered particularly strong results including:
▪ MDD395: 3.0m @ 4.5g/t Au from 77.0m, and;
14.0m @ 4.7g/t Au from 88.0m
These southern intercepts confirm the presence of near-surface, high-grade zones in areas previously classified as
Inferred. This adds optionality to the early pit stages and supports ore availability closer to surface, an important factor
in reducing pre-strip quantities and bringing forward mill feed.
In parallel, infill drilling around the high-grade HG1 domain was also advanced, with results improving confidence in
resource domaining and grade continuity. Notable assays include:
▪ MDD379: 16.4m @ 5.7g/t Au from 167.6m and;
7.0m @ 21.7g/t Au from 194.0m
▪ MDD378: 12.0m @ 5.3g/t Au from 160.0m
▪ MDD382: 8.0m @ 4.2g/t Au from 161.0m, and;
7.0m @ 3.4g/t Au from 172.0m, and;
6.0m @ 11.9g/t Au from 188.0m
7
Together, these results continue to validate the continuity and scale of the HG1 domain, which is the focal point for
detailed mine planning.
The RAS orebody continues to deliver high-quality results that not only enhance confidence in near-term mining areas
but also present opportunities to optimise pit designs and reduce capital intensity. The current drill campaigns feed
directly into revised staging models and the forthcoming PFS Update, reinforcing the geological and technical
foundation for development.
Following quarter end, further infill results along the eastern and southern extents were received which upgrade
resource confidence in zones earmarked for early-stage mining, while also assessing potential lateral extensions
beyond the current pit shell and modelled domains. Notable new intercepts from RAS South include
Figure 5. RAS South drill results in long section, showing strong intercepts beneath the PFS ultimate pit shell
▪ MDD407 33.0m @ 2.7g/t Au from 98.0m (true width 30.1m)
including 4.0m @ 8.91g/t Au from 118m
3.0m @ 7.40 g/t Au from 129m
▪ MDD413
19.0m @ 1.5g/t Au from 179.0m (true width 17.9m)
including 3.0m @ 5.97g/t Au from 180m
▪ MDD416 8.0m @ 2.8g/t Au from 194.0m (true width 7.5m)
including 3.0m @ 5.10g/t Au from 194m
▪ MDD398 9.0m @ 2.1g/t Au from 69.0m (true width 7.1m)
including 2.0m @ 3.0 g/t Au from 69m
2.0m @ 5.11 g/t Au from 76m; and
2.0m @ 9.34g/t Au from 158.0m (true width 1.6m)
2.0m @ 5.59g/t Au from 181.0m (true width 1.6m)
8
These new results at RAS South fall outside current pit shells and HG1/LG1 domains (Figure 5), suggesting strong
potential to add near-surface ounces with minimal additional stripping. The southern extensions can enhance early
production flexibility and improve the ore profile feeding into the plant. Additional drilling in this area may further
expand the mineable envelope and support cost-effective mining in the earlier phases of the schedule.
Drilling activity continues across multiple fronts at the BOGP. At RAS South, the infill drilling is expected to conclude in
the coming weeks, with assays pending from five recently completed holes. Infill drilling has also commenced at RAS
North, targeting potential extensions to the HG1 domain and aiming to upgrade underground Inferred resources to the
Indicated category.
Geotechnical drilling within the RAS PFS pit is nearing completion and may inform updated pit design and scheduling
in the forthcoming PFS Update. Concurrently, regional work under the RINA (RAS-is-Not-Alone) program continues,
with sterilisation and exploration drilling progressing around prospective targets. Infill drill traverses are also being
planned at the CIT, SRX, and SRE satellite deposits to provide the grade variability data needed for early-stage mine
planning.
Permitting and Fast-track Approvals
On 20 March 2025, Santana submitted its Mining Permit Application (MPA) to New Zealand Petroleum & Minerals
(NZPAM), a regulatory step that formally transitions the BOGP from the exploration regime under the Crown Minerals
Act 1991 to the development phase. The MPA outlines the proposed mining method, schedule of activities,
environmental and rehabilitation plans, and financial capability of the applicant. It represents the cornerstone approval
required to extract gold in New Zealand and is a prerequisite to advancing the project toward production.
The MPA submission confirms the maturity and technical readiness of the BOGP and reflects the substantial work
completed to date in mine planning, environmental baseline collection, and operational design. Its acceptance initiates
NZPAM’s formal assessment process, which is expected to progress in parallel with broader environmental consenting
under the Fast-track pathway.
While documentation for the Fast-Track Approvals (FTA) process was initially targeted for submission during the
quarter, the application is now expected to be lodged at the end of June. The short delay reflects the integration of
recently completed technical data, ongoing consultation outcomes, and the availability of key external consultants,
who remain engaged across multiple workstreams to ensure full alignment with the legislative requirements of the
Fast-track Approvals Act.
The Bendigo-Ophir gold project has been included in Schedule 2 of the Fast-track framework, which enables projects
of regional or national significance to be assessed by an appointed expert panel, with time-bound decision-making and
a reduced risk of legal challenge. Once submitted, the FTA pathway could deliver full resource consents within six
months. This would provide the Company with critical visibility over development timelines and support the
commencement of early works. Together, the MPA and FTA processes form the core of the regulatory bridge to
construction and first gold.
Execution Readiness
As the technical and permitting fronts converge, Santana is progressing detailed contractor engagement and execution
planning. Early-stage engagement with mining contractors is underway to validate assumptions and provide cost
certainty for major pre-strip and infrastructure scopes.
The revised mine plan and potential for a reduced upfront capital burden provide greater optionality in funding
structuring and support a streamlined pathway to Final Investment Decision (FID). Discussions with key stakeholders
are now increasingly focused on development sequencing, construction mobilisation, and critical path readiness.
The Company is also advancing early works planning, including site access, water abstraction infrastructure, and
accommodation strategies in parallel with the permitting timeline.
The PFS Update expected in the ensuing quarter will consolidate this work and deliver an updated Mineral Reserve
along with revised financial projections. This data will be used to advance the project and inform the next steps toward
funding and execution.
9
Corporate and Appendix 5B Disclosures
New Board Appointment
Emma Scotney joined the Board as a Non-Executive Director during the quarter, bringing a breadth of legal and
commercial experience. She currently holds Non – Executive Director roles with ASX 200 De Grey Mining Limited and
Minerals 260 Limited, and serves as a Commissioner of the Insurance Commission of Western Australia. Her
appointment strengthens the Board’s capability as the Company advances the Bendigo-Ophir Gold Project through
permitting, feasibility, and development.
All Ordinaries Inclusion
The Company was added to the S&P/ASX All Ordinaries Index as part of the March 2025 quarterly rebalance, effective
prior to the open of trading on March 24, 2025.
This inclusion reflects the Company's growth and increased market capitalisation, highlighting investor confidence in
the Bendigo-Ophir Gold Project. Being part of the All Ordinaries Index enhances Santana's visibility among institutional
investors and index-tracking funds, potentially improving liquidity and broadening the shareholder base.
The Company views this milestone as a significant endorsement of its strategic direction and operational progress.
Options Exercised
Options issued to shareholders in February 2024 reached expiry during the quarter, resulting in total cash proceeds of
A$36 million from exercised options. Approximately 5.3 million options lapsed unexercised.
Financials
The Company closed the quarter with a gross cash balance (before creditors) of A$55.35M.
The Company’s Appendix 5B (Quarterly Cashflow Report) attached includes an amount in item 6.1 which constitutes
executive ($191k) and non-executive ($60k) directors’ fees paid during the Quarter. In addition, item 6.2 includes an
amount which constitutes project management ($7k) and equipment hire fees ($10k) paid to directors during the
Quarter.
During the period, the Company spent $3.7M on exploration activities and project studies in New Zealand.
Ends.
Enquiries:
Damian Spring
Exec. Director & CEO
dspring@santanaminerals.com
Sam Smith
Exec. Director Corp Affairs & IR
ssmith@santanaminerals.com
14
Bendigo-Ophir Project Mineral Resource and Reserve Estimate
The Project contains a Mineral Resource Estimate (MRE) calculated at a cutoff grade of 0.5 g/t Au with top cuts applied, as at
March 2025:
Deposit Category tonnes (Mt) Au grade (g/t)
Contained Gold
(koz)
RAS
Indicated 18.9 2.5 1,538
Inferred 7.6 2.2 542
RAS Total Indicated and Inferred 26.5 2.4 2,080
CIT Inferred 1.2 1.5 59
SRX Indicated 2.2 0.8 54.7
SRX Inferred 2.9 1.0 90.5
SRX Total Indicated and Inferred 5 0.9 145
SRE Indicated 0.4 0.8 10.3
SRE Inferred 1.1 1.2 42
SRE Total Indicated and Inferred 1.5 1.1 52
BOGP Total
Indicated 21.5 2.3 1,603
Inferred 12.8 1.8 734
BOGP Total Indicated and Inferred 34.3 2.1 2,337
Table 3. Bendigo-Ophir Gold Project Mineral Resource March 2025
Reserve Statement as at November 2024
Area Proven Probable Total
Mt Au g/t Mt Au g/t Mt Au g/t Au koz
RAS (open pit) - - 11.9 2.42 11.9 2.43 928
RAS
(Underground)
2.3 3.03 2.3 3.03 223
SRX 1.3 0.70 1.3 0.70 30
Total - - 15.5 2.37 15.5 2.37 1,181
Reserve Statement Notes
Note 1: RAS Open pit cut-off grade 0.3 g/t at $US1,650/oz Au price
Note 2: RAS Underground cut-off grade 1.75 g/t at $US1,650/oz Au price
Note 3: SRX Open pit cut-off grade 0.35 g/t at $US2,100/oz Au price
Note 4: Underground Reserves are from the quoted Open pit Resources area
Note 5: The effective date of the Mineral Reserve is 1 November 2024, estimated by Rodney Redden (MAusIMM and CP-Mining), a contractor to Santana
Minerals Ltd.
Note 6: Approved consents and required permits are yet to be granted to enable mining of the RAS and SRX deposits.
15
Cautionary Statement – Inferred Resources Included in Production Target
Of the Mineral Resources planned for extraction under the PFS production model approximately 94% is within the Indicated Resources category, with the balance
(6%) being classified within the Inferred Resources category. There is a low level of geological confidence associated with Inferred Mineral Resources and there is
no certainty that further exploration work will result in the determination of Indicated Mineral Resources or that the production target itself will be realised.
The production target and the forecast financial information derived from the production target set out in this report were first contained in a public announcement
released to the ASX on 15 November 2024.
The Company confirms that all material assumptions underpinning the production target and the forecast financial information derived from it continue to apply
and have not materially changed.
The information in this report that relates to Mineral Resources is based on information contained in the following public announcements:
• ASX announcement titled “RAS Mineral Resource Estimate Review” dated 4 March 2025
• ASX Announcement titled “Bendigo-Ophir Pre-Feasibility Study” dated 15 November 2024
• ASX Announcement titled “Infill drilling increases RAS Indicated category to 1.45Moz” dated 2 July 2024
• ASX Announcement titled “1.3M ounces upgraded to Indicated category from RAS drilling:” dated 16 February 2024
• ASX Announcement titled “Bendigo-Ophir Gold Resources Increased 155% to 643k Oz” dated 28 September 2021
The information in this report that relates to Ore Reserves is based on information contained in the public announcement made to the ASX on 15 November 2024.
The information in this report that relates to Exploration Results is based on information contained in the following public announcement:
• ASX announcement titled “Infill drilling increases RAS Indicated category to 1.45Moz” dated 2 July 2024
• ASX announcement titled “RAS Drill Results Continue to Glow” dated 8 January 2025
• ASX announcement titled “RAS South Drilling New Gold Intercepts Below PFS Pit” dated 10 April 2025
• ASX announcement titled “Mining Studies Update” dated 22 April 2025
The reports were issued in accordance with the 2012 Edition of the JORC Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. The
Company confirms that it is not aware of any new information or data that materially affects the information included in the original market announcements referenced
above and, in the case of the Mineral Resource estimates, that all material assumptions and technical parameters underpinning the Mineral Resource estimates in the relevant
announcements continue to apply and have not materially changed. The Company confirms that the form and context in which the Competent Person’s findings are presented
have not been materially modified from the original market announcements.
16
Additional ASX Listing Rule Information
Santana Minerals Limited (‘Santana’) provides the following additional information in accordance with ASX Listing Rule 5.3.3.
Mining tenements held at the end of the Quarter and their location
Name Status Interest Held
New Zealand
Bendigo-Ophir
Granted, Extension Pending 100%
Ardgour
Granted 100%
Cambodia
Snoul Granted
34%
#
# The consolidated entity currently holds a 34% interest in the project (diluting to not less than 12.75% assuming the consolidated entity does not exercise
contribution rights) and is free carried to completion of feasibility study.
Mining tenements acquired during the Quarter and their location
Not applicable.
Mining tenements disposed of during the Quarter and their location
Not applicable.
Beneficial percentage interests held in farm-in or farm-out agreements at the end of the Quarter
Cambodian Project
The consolidated entity’s subsidiary (Subsidiary) is party to an unincorporated joint venture agreement with Southern Gold Limited (SGL) in
respect of the Cambodian Exploration Licences, pursuant to which SGL has a 15% unincorporated joint venture interest in the Cambodian
Exploration Licences, which is free carried until completion of a feasibility study.
The consolidated entity’s subsidiary has also entered into a farm-out and incorporated joint venture agreement with Renaissance Cambodia Pty
Ltd (Renaissance) (Farm-Out Agreement), pursuant to which Renaissance will sole fund US$0.5 million of exploration expenditure on each of
the Cambodian Exploration Licences to earn a 30% shareholding in the Subsidiary. Renaissance can elect to sole fund a further US$1.0 million of
exploration expenditure on each of the two Cambodian Exploration Licences over the following two years, to increase its shareholding in the
Subsidiary to 60%. Upon Renaissance earning a 60% shareholding in the Subsidiary, the consolidated entity may elect to either contribute to
maintain its shareholding in the Subsidiary of 40% or not to contribute, in which case Renaissance may earn a further 25% shareholding in the
Subsidiary, by managing the Subsidiary and providing funding to complete a definitive feasibility study, during which period the consolidated
entity will be free carried.
Renaissance has met the expenditure requirements to earn a 60% interest in the Subsidiary. The consolidated entity has elected not to
contribute and is free carried to a definitive feasibility study.
Beneficial percentage interests in farm-in or farm-out agreements acquired or disposed of during the Quarter
Not applicable.
Rule 5.5
ASX Listing Rules Appendix 5B (17/07/20) Page 1
+ See chapter 19 of the ASX Listing Rules for defined terms.
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
SANTANA MINERALS LIMITED
ABN Quarter ended (“current quarter”)
37 161 946 989 31 MARCH 2025
Consolidated statement of cash flows
Current quarter
$A’000
Year to date
(9months)
$A’000
1. Cash flows from operating activities
- -
1.1 Receipts from customers
1.2 Payments for
- (51) (a) exploration & evaluation
(b) development - -
(c) production - -
(d) staff costs (338) (1,038)
(e) administration and corporate costs (590) (1,532)
1.3 Dividends received (see note 3) - -
1.4 Interest received 420 786
1.5 Interest and other costs of finance paid - -
1.6 Income taxes paid - -
1.7 Government grants and tax incentives - -
1.8 Other (provide details if material) - -
1.9 Net cash from / (used in) operating
activities
(508) (1,835)
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 2
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows
Current quarter
$A’000
Year to date
(9months)
$A’000
2. Cash flows from investing activities
- -
2.1 Payments to acquire or for:
(a) entities
(b) tenements - -
(c) property, plant and equipment (86) (444)
(d) exploration & evaluation (3,639) (11,659)
(e) investments - -
(f) other non-current assets - (228)
2.2 Proceeds from the disposal of:
- - (a) entities
(b) tenements - -
(c) property, plant and equipment - -
(d) investments - -
(e) other non-current assets - 40
2.3 Cash flows from loans to other entities - -
2.4 Dividends received (see note 3) - -
2.5 Other - -
2.6 Net cash from / (used in) investing
activities
(3,725) (12,291)
3. Cash flows from financing activities
- 10
3.1
Proceeds from issues of equity securities
(excluding convertible debt securities)
3.2 Proceeds from issue of convertible debt
securities
- -
3.3 Proceeds from exercise of options 28,171 36,184
3.4 Transaction costs related to issues of equity
securities or convertible debt securities
- -
3.5 Proceeds from borrowings - 268
3.6 Repayment of borrowings (34) (62)
3.7
Transaction costs related to loans and
borrowings
- -
3.8 Dividends paid - -
3.9 Other (Share Buy-back) - -
3.10 Net cash from / (used in) financing
activities
28,137 36,400
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 3
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows
Current quarter
$A’000
Year to date
(9months)
$A’000
4.
Net increase / (decrease) in cash and
cash equivalents for the period
4.1
Cash and cash equivalents at beginning of
period
31,449 33,079
4.2
Net cash from / (used in) operating
activities (item 1.9 above)
(508) (1,835)
4.3 Net cash from / (used in) investing activities
(item 2.6 above)
(3,725) (12,291)
4.4
Net cash from / (used in) financing activities
(item 3.10 above)
28,137 36,400
4.5 Effect of movement in exchange rates on
cash held
2 2
4.6
Cash and cash equivalents at end of
period
55,355 55,355
5. Reconciliation of cash and cash
equivalents
at the end of the quarter (as shown in the
consolidated statement of cash flows) to the
related items in the accounts
Current quarter
$A’000
Previous quarter
$A’000
5.1 Bank balances 681 301
5.2 Call deposits 54,674 31,148
5.3 Bank overdrafts - -
5.4 Other (provide details) - -
5.5 Cash and cash equivalents at end of
quarter (should equal item 4.6 above)
55,355 31,449
6. Payments to related parties of the entity and their
associates
Current quarter
$A'000
6.1
Aggregate amount of payments to related parties and their
associates included in item 1
251
6.2 Aggregate amount of payments to related parties and their
associates included in item 2
17
Note: if any amounts are shown in items 6.1 or 6.2, your quarterly activity report must include a description of, and an
explanation for, such payments.
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 4
+ See chapter 19 of the ASX Listing Rules for defined terms.
7. Financing facilities
Note: the term “facility’ includes all forms of financing
arrangements available to the entity.
Add notes as necessary for an understanding of the
sources of finance available to the entity.
Total facility
amount at quarter
end
$A’000
Amount drawn at
quarter end
$A’000
7.1 Loan facilities - -
7.2 Credit standby arrangements - -
7.3 Other (please specify) 229 229
7.4 Total financing facilities - -
7.5 Unused financing facilities available at quarter end -
7.6 Include in the box below a description of each facility above, including the lender, interest
rate, maturity date and whether it is secured or unsecured. If any additional financing
facilities have been entered into or are proposed to be entered into after quarter end,
include a note providing details of those facilities as well.
7.3 The company has obtained vehicle finance facilities to fund the purchase of 6 vehicles
through Toyota Finance on a secured basis. The facilities are payable monthly and attract
interest at a rate of 2% per annum with the last payments due in September (3 vehicles)
and October (3 vehicles) 2026.
8. Estimated cash available for future operating activities $A’000
8.1 Net cash from / (used in) operating activities (item 1.9) (508)
8.2 (Payments for exploration & evaluation classified as investing
activities) (item 2.1(d))
(3,639)
8.3 Total relevant outgoings (item 8.1 + item 8.2) (4,147)
8.4 Cash and cash equivalents at quarter end (item 4.6) 55,355
8.5 Unused finance facilities available at quarter end (item 7.5) -
8.6 Total available funding (item 8.4 + item 8.5) 55,355
8.7
Estimated quarters of funding available (item 8.6 divided by
item 8.3)
13.35
Note: if the entity has reported positive relevant outgoings (ie a net cash inflow) in item 8.3, answer item 8.7 as “N/A”.
Otherwise, a figure for the estimated quarters of funding available must be included in item 8.7.
8.8 If item 8.7 is less than 2 quarters, please provide answers to the following questions:
8.8.1 Does the entity expect that it will continue to have the current level of net operating
cash flows for the time being and, if not, why not?
Answer:
8.8.2 Has the entity taken any steps, or does it propose to take any steps, to raise further
cash to fund its operations and, if so, what are those steps and how likely does it
believe that they will be successful?
Answer:
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 5
+ See chapter 19 of the ASX Listing Rules for defined terms.
8.8.3 Does the entity expect to be able to continue its operations and to meet its business
objectives and, if so, on what basis?
Answer:
Note: where item 8.7 is less than 2 quarters, all of questions 8.8.1, 8.8.2 and 8.8.3 above must be answered.
Compliance statement
1 This statement has been prepared in accordance with accounting standards and policies which
comply with Listing Rule 19.11A.
2 This statement gives a true and fair view of the matters disclosed.
Date: 28 April 2025...................................................................................
Authorised by: The Board of Directors
(Name of body or officer authorising release – see note 4)
Notes
1. This quarterly cash flow report and the accompanying activity report provide a basis for informing the market about the
entity’s activities for the past quarter, how they have been financed and the effect this has had on its cash position. An
entity that wishes to disclose additional information over and above the minimum required under the Listing Rules is
encouraged to do so.
2. If this quarterly cash flow report has been prepared in accordance with Australian Accounting Standards, the definitions
in, and provisions of, AASB 6: Exploration for and Evaluation of Mineral Resources and AASB 107: Statement of Cash
Flows apply to this report. If this quarterly cash flow report has been prepared in accordance with other accounting
standards agreed by ASX pursuant to Listing Rule 19.11A, the corresponding equivalent standards apply to this report.
3. Dividends received may be classified either as cash flows from operating activities or cash flows from investing activities,
depending on the accounting policy of the entity.
4. If this report has been authorised for release to the market by your board of directors, you can insert here: “By the board”.
If it has been authorised for release to the market by a committee of your board of directors, you can insert here: “By the
[name of board committee – eg Audit and Risk Committee]”. If it has been authorised for release to the market by a
disclosure committee, you can insert here: “By the Disclosure Committee”.
5. If this report has been authorised for release to the market by your board of directors and you wish to hold yourself out as
complying with recommendation 4.2 of the ASX Corporate Governance Council’s Corporate Governance Principles and
Recommendations, the board should have received a declaration from its CEO and CFO that, in their opinion, the financial
records of the entity have been properly maintained, that this report complies with the appropriate accounting standards
and gives a true and fair view of the cash flows of the entity, and that their opinion has been formed on the basis of a
sound system of risk management and internal control which is operating effectively.
Data sourced from publicly available filings. Our datasets may not be complete. Automated analysis can produce errors. If you believe any data on this page is incorrect, please contact us at hello@nzxplorer.co.nz. For informational purposes only. Not investment advice.