Santana Minerals Ltd logo

Presentation - Bell Potter Unearthed

Investor Presentation8 February 2026SMIMaterials

Bendigo-Ophir Gold Project
Developing New Zealand’s Next Major

Gold Project in 2026

ASX/NZX: SMI

Disclaimer
Disclaimer

Allinformationcontainedinthispresentationisofageneralnature.Potentialinvestorsarecautionedagainstusingthecontentofthis

presentation,inisolation,formakinginvestmentdecisionsandshouldalsorefertoSantanaMineralsLimited(‘Santana’)AnnualReportsand

ASX/NZX:SMIreleases.ForfurtherinformationaboutSantanavisitourwebsiteatwww.santanaminerals.com.

Besteffortshavebeenmadetoensuretheaccuracyofinformationcontained(atthetimeofpreparation).Whereforwardtargetsand/or

assumptionshavebeenincluded–allsuchinstancesareindicativeonlyandsubjecttoalterationand/orcancellationasandwhenthe

managementofSantanadetermines.

Researchandadviceofaqualifiedfinancialadvisororaccountantarestronglyrecommendedtoanyoneconsideringinvestinginlisted

companysecurities,includingthoseofSantana.

ThePrefeasibilityStudy,includingtheproductiontargetandtheforecastfinancialinformationderivedfromtheproductiontarget,referredto

inthisPresentation(PFS)wasreleasedtotheASXon1July2025.ThisPresentationincludessummaryexcerptsfromthePFSanddoesnot

purporttobeall-inclusiveorcomplete.

Forward-LookingStatements

ThisPresentationcontainsvariousforwardlookingstatements.Forward-lookingstatementsinthispresentationinclude,butarenotlimited

to,statementsregardingtheproductiontarget,financialinformationbasedonthatproductiontargetandstatementsstatementswith

respecttoSantana’sfutureplans,strategy,activities,eventsordevelopmentstheCompanybelieves,expectsoranticipateswillormayoccur.

Bytheirverynature,forward-lookingstatementsrequireSantanatomakeassumptionsthatmaynotmaterializeorthatmaynotbeaccurate.

TheCompanyhasconcludedthatithasareasonablebasisforprovidingtheseforward-lookingstatements,includingtheproductiontarget

andtheforecastfinancialinformationincludedinthisPresentation.Thedetailedreasonsfortheseconclusionsareoutlinedthroughoutthe

ASXreleasesdated1July2025.However,noassurancecanbegiventhattheseexpectationswillprovetohavebeencorrect,asactualresults

andfutureeventscoulddiffermateriallyfromthoseanticipatedintheforward-lookingstatements.Accordingly,viewersarecautionednotto

placeunduerelianceonforward-lookingstatements.Santanadoesnotundertaketoupdatepubliclyortoreviseanyoftheincludedforward-

lookingstatements,exceptasmayberequiredunderapplicablesecuritieslaws.

ToachievetherangeofoutcomesanticipatedinthePFS,thePFSestimatesthatfinancingintheorderofA$277millionwillberequired.

Santanabelievesthattherearereasonablegroundsfortheassumptionsithasmadeinsatisfyingitselfthattherequisitefundingforthe

developmentoftheProjectwillbeavailablewhenrequired.However,Shareholdersandprospectiveinvestorsshouldbeawarethatthereis

noguaranteeSantanawillbeabletosecurethisfundingasrequired,anditispossiblethatthetermsavailablemaybedilutiveorotherwise

adverselyimpactthevalueofSantana’scurrentshares.Additionally,Santanamayexplorealternativevalue-creatingstrategies,suchas

divestingsomeorallpotentialrevenuestreamsfrompreciousmetalsorafullorpartialsaleofitsinterestintheBendigo-Ophirproject.

CautionaryStatement–InferredResourcesIncludedinProductionTarget

OftheMineralResourcesplannedforextractionunderthePFSproductionmodelapproximately93%iswithintheIndicatedResourcescategory,with

thebalance(7%)beingclassifiedwithintheInferredResourcescategory.ThereisalowlevelofgeologicalconfidenceassociatedwithInferredMineral

ResourcesandthereisnocertaintythatfurtherexplorationworkwillresultinthedeterminationofIndicatedMineralResourcesorthattheproduction

targetitselfwillberealised.

CompetentPersonsStatement

Theproductiontargetandtheforecastfinancialinformationderivedfromtheproductiontargetsetoutinthispresentationwerefirstcontainedina

publicannouncementreleasedtotheASXon1July2025.TheCompanyconfirmsthatallmaterialassumptionsunderpinningtheproductiontargetand

theforecastfinancialinformationderivedfromitcontinuetoapplyandhavenotmateriallychanged.

TheinformationinthisreportthatrelatestoMineralResourcesisbasedoninformationcontainedinthefollowingpublicannouncements:

4March2025–ASXAnnouncementtitled“RASMineralResourceEstimateReview”

15November2024–ASXAnnouncementtitled“Bendigo-OphirPre-FeasibilityStudy”

28September2021–ASXAnnouncementtitled“Bendigo-OphirGoldResourcesIncreased155%to643kOz”

TheinformationinthisreportthatrelatestoOreReservesisbasedoninformationcontainedinthepublicannouncementmadetotheASXon1July

2025.

AcopyoftheseannouncementsareavailabletoviewontheSantanaMineralsLimitedwebsitewww.santanaminerals.comorontheASXplatform

www.asx.com.au.

Thereportswereissuedinaccordancewiththe2012EditionoftheJORCAustralasianCodeforReportingofExplorationResults,MineralResourcesand

OreReserves.TheCompanyconfirmsthatitisnotawareofanynewinformationordatathatmateriallyaffectstheinformationincludedintheoriginal

marketannouncementsreferencedaboveand,inthecaseoftheMineralResourceestimates,thatallmaterialassumptionsandtechnicalparameters

underpinningtheMineralResourceestimatesintherelevantannouncementscontinuetoapplyandhavenotmateriallychanged.TheCompany

confirmsthattheformandcontextinwhichtheCompetentPerson’sfindingsarepresentedhavenotbeenmateriallymodifiedfromtheoriginalmarket

announcements.

Company Snapshot
Peter Cook

Non-Exec Chair

Geo and mine maker

Damian Spring

CEO & Exec Director

Engineer and NZ local

Kim Bunting

Non-Exec Director

Geo who discovered RAS

Sam Smith

Exec Director, Corporate

Engineer and IR

Board & Management

Well Funded

Substantial Ownership

>40%NZ private investors

12%Institutional investors

8%Board & management

Capital Structure

A$820 million

836 million FPO shares@ A$0.98/share –6 Feb 2026

Market

Capitalisation

1.2 million shares

Ave. 90 day trading volume

4.5m incentives

Options

A$85m

Cash at Bank,31 December

(net of

payables)

Craig McPherson

CFO & Co-Sec

Finance and compliance

Emma Scotney

Non-Exec Director

Lawyer, experienced Director

$0.98/sh

Low Risk Jurisdiction
Fraser Institute 2025 –NZ outranks

all Australian states

90km west of Macraesin Central

Otago

Private freehold farmland -under

purchase agreements by Santana

Area blessed with infrastructure,

power, water.

Access to skilled labourwith 1000's

of job applications being received

30-Year Mining Permit Granted
30-year mining permit granted

by NZPAM

FTA Resource Consent decision

due 29 October 2026

Legal rights to mine within the

permit

Secures RAS, CIT and SREX

New prospecting permit

application in play to the north

to secure new RAS extensions

Land Agreements Secured
Bendigo and Ardgour land

packages now under binding,

conditional agreements

Agreement reached with

CODC torelocate council

roads

Community benefit fund in

place for local environmental

and social initiatives

Ongoing environmental

studies to ensure robust

protections

Land under purchase agreement

Bendigo

Ardgour

2.3Moz ResourceInside Mining Permit
Come In Time

59koz @ 1.5 g/t Au

Rise and Shine (RAS)

2.08Moz @ 2.4 g/t Au

1.21Moz Probable Ore Reserve

Srex

145koz @ 0.9 g/t Au

30koz @ 0.7 g/t Au Ore Reserve

Srex-East

52koz @ 1.1 g/t Au

Combined Total

2.34Moz @ 2.1 g/t Au*

CIT

RSSZ

RAS

SRX

SRE

* Refer Appendix 1

2.1Moz at RAS Wide Thick & Long

Major RAS Extension
Step-out hole tagged the

orebody 465m away from

MRE drilling

Major zone of mineralised SBX

(42m)

Ore zone now 2.15km long

Potential to add significant

underground mine life

2.1Moz at RAS Long Section

RAS Mining Schematic
1.25Moz bankable

Reserve

993koz in open pits

316koz in

underground so far

Ongoing UG Resource

conversion

Major extensional

intercept with 38.6m

@ 1.70g/t

38.6m

@ 1.7g/t

993koz

316koz

Feasibility Study
Current metrics from Updated PFS 2025

ASX/NZX: SMI

Open Pit at 1.2Mtpa
1.02Moz

12.6Mt at 2.5g/t

RAS/SRX gold inventory

Mining physicals

13.8yrsmining

11Mt @ 2.75g/t from RAS

1.4Mt @ 0.68g/t from SRX

93% ore feed is Probable Reserve

Mined gold

993koz Au from RAS

30koz from SRX

>1Moz Au total

Overall grade 2.53g/t

953koz recovered

13

ASX release 1 July 2025 “Updated PFS –Bendigo Ophir Gold Project”

Mining method

Sevenstages of cutbacks

200t class excavators

90t class rear dump trucks

RAS

211Mt total rock

17.5Mt pre-strip

11.2Mt ore

14.6:1operating strip ratio

Underground Mine Plan
316koz

3.7Mt at 2.7g/t

RAS UG inventory

Mining physicals

7yrsmining

3.7Mt ore

Total development 17km

87% Indicated ore feed

Mining method

Long hole stopingw/paste fill

5.5mW x 5.5mW twin declines

Cable bolts and shotcrete

17km development

2.6Mtpaste fill

171kmof cables

10k m

3

shotcrete

Mined gold

316koz Au

Grade 2.66g/t

295koz recovered

14

ASX release 1 July 2025 “Updated PFS –Bendigo Ophir Gold Project”

Step out

drilling now

underway

Projected Metrics
-

20

40

60

80

100

120

140

Year 1Year 2Year 3Year 4Year 5Year 6Year 7Year 8Year 9Year 10Year 11Year 12Year 13Year 14

Pr

oduction (kOz)

Open PitUnderground

option to increase ounces per annum with mill upgrade to 1.8Mtpa

Metrics at A$6,500/oz

A$2,245/oz

all-in-cost per ounce

A$1,962/oz

all-in-sustaining-cost

A$1,270/oz

C1 cash operating cost

A$277M

CAPEX

A$3.8 billion

after tax free cash

94%

after tax IRR

1.33years

payback from production

A$2.3 billion

after tax NPV

6.5%

Ounce Profile at 1.2Mtpa

ASX release 1 July 2025 “Updated PFS –Bendigo Ophir Gold Project”

Reflected with recent AUD gold price metrics -02/02/2026

CIL Processing1.2 to 1.8Mtpa
16

Six phases of metallurgical testing

completed

Very high recoveries at RAS of 93%

THE PFS DESIGN USES SIMPLE CIL TECHNOLOGY TO GENERATE VERY HIGH RECOVERIES

Three stage crush

Ball millingGravity circuit

CIL

Electrowinning

Gold furnace

1

2

3

4

5

6

Exploration Growth
30km of strike

Strong soil anomalies at

DNS and ORK

Emerging new targets

coming from mapping and

soil sampling

Stacked tailings from

historic mining, untested

Permitting Timeline
Submitted FTA

Accepted by

EPA

CODC Land

Access

Panel

Appointment

&

Decision Date

Set

Decision

Date

Nov

‘25

Dec

‘25

Feb

‘26

Feb

‘26

Oct

‘26

2025

2026

Early Works Underway

Development Timeline
PATHWAY TO FIRST GOLD

PROJECT: Bendigo-Ophir Gold Project

Project start date:

Milestone description

Resource Consents

Early Works

Buildings

Mine Entrance Work

Services

Establishment

Pioneering

Haul Road

Construction

Process Plant Prep.

Pads and Dams

Pre-Strip

Mining Fleet Starts

Process Plant

Detailed Design

Civil Construction

First Gold

Q4

ExpectedPlanned

H1

20262027

Q3Q1Q3Q4Q2

Summary
Biggest NZ gold discovery in 40 years

Permitting underway with an approval

decision on 29 October 2026

120koz per annum low-cost, long-life

producer

Construction beginning in late 2026

Over 350 direct jobs, and over NZ$2billion in

taxes and government royalties

1

Derisked and ready to build

1

Calculated at NZ$7,100/oz, a discount to prevailing gold price at 02/02/2026

ASX release 23 July 2025 –“Rise and Shine –Northern Honeypot Emerges”

ASX release 22 August 2022 –“MDD054 JewelleryBox Re-Assays to 1400 g/t Gold”

Appendix 1: Mineral Resource Estimate
Contained Gold (koz)Au grade (g/t)tonnes (Mt)CategoryDeposit

1,5382.518.9Indicated

RAS

5422.27.6Inferred

2,0802.426.5Indicated and InferredRAS Total

591.51.2InferredCIT

54.70.82.2IndicatedSRX

90.51.02.9InferredSRX

1450.95Indicated and InferredSRX Total

10.30.80.4IndicatedSRE

421.21.1InferredSRE

521.11.5Indicated and InferredSRE Total

1,6032.321.5Indicated

BOGP Total

7341.812.7Inferred

2,3372.134.3Indicated and InferredBOGP Total

TheinformationinthisreportthatrelatestothisMarch2025RASMineralResourceEstimates(MRE)andtotheNovember2024SRXandSREMRE,isbasedonworkcompletedbyMrKerrinAllwood,aCompetentPerson(CP)whoisaMemberofTheAustralasian

InstituteofMiningandMetallurgy(AusIMM).MrAllwoodisaPrincipalGeologistofGeoModellingLimited,Petone,NewZealandandhassufficientexperiencewhichisrelevanttothestyleofmineralisationandtypeofdepositunderconsiderationandtothe

activitywhichisbeingundertakentoqualifyasaCompetentPersonasdefinedinthe2012Editionofthe“AustralasianCodeforReportingofExplorationResults,MineralResourcesandOreReserves”.MrAllwoodconsentstotheinclusioninthisreportofthe

mattersbasedonhisinformationintheformandcontextinwhichitappears.MrAllwoodandGeoModellingLimitedareindependentofSantanaMineralsLtd.

Theinformationinthisreportthatrelatestoprior2021MineralResourceEstimates(2021MRE)forCITdepositcompletedbyMsMichelleWild(CP)(ASXannouncementon28September2021)continuetoapplyandhavenotmateriallychanged.

Ore Reserve Table
Bendigo-Ophir

Maiden Ore Reserve

15Mt @ 2.58g/t

1. Please see full PFS Summary and Reserve estimate modifying factors in the disclosures announced to ASX

on 1 July 2025

Note 1: RAS Open pit cut-off grade 0.5g/t at $US2,000/oz Au price

Note 2: RAS Underground cut-off grade 1.7g/t at $US1,650/oz Au price

Note 3: SRX Open pit cut-off grade 0.30 g/t at $US2,100/oz Au price

Note 4: Underground Reserves are from the quoted Open pit Resources area

Note 5: The effective date of the Mineral Reserve is 30 June 2025, estimated under the supervision of Damian Spring (MAusIMMand CP-Mining).

Note 6: Approved consents and required permits are yet to be granted to enable mining of the RAS and SRX deposits.

TotalProbableProvenArea

Au kozAu g/tMtAu g/tMtAu g/tMt

9372.7810.52.7810.5--RAS open pit

2752.663.22.663.2

RAS

underground

300.701.30.701.3SRX

1,2422.5815.02.5815.0--Total

Data sourced from publicly available filings. Our datasets may not be complete. Automated analysis can produce errors. If you believe any data on this page is incorrect, please contact us at hello@nzxplorer.co.nz. For informational purposes only. Not investment advice.

Other issuers discussed similar conditions around this time

Matched by meaning across NZX announcement text, not keywords — based on our semantic index of announcement bodies.