Meridian to upgrade Waitaki Power Station

Operational Update29 September 2026MELUtilities

Release
M e r i d i a n E n e r g y L i m i t e d ( A R B N 1 5 1 8 0 0 3 9 6 ) A c o m p a n y i n c o r p o r a t e d i n N e w Z e a l a n d

L e v e l 2 , 9 8 C u s t o m h o u s e Q u a y , W e l l i n g t o n 6 0 1 1

m e r i d i a n e n e r g y . c o . n z

Stock Exchange Listings NZX (MEL) ASX (MEZ)

Meridian to upgrade Waitaki Power Station


30 September 2026


Meridian Energy will invest between $440 million and $510 million over the next ten years upgrading

its 92-year-old Waitaki Power Station, boosting hydro generation and setting the asset up for another

lifetime. Scheduled for completion by 2036, the project will increase the station’s available capacity

from 105MW to 120MW, replacing all seven turbines, generators and supporting balance-of-plant

systems, together with the station’s 21 headgates and associated equipment.

The investment will be treated as a combination of growth capital expenditure (15% of the investment)

and a new classification, repowering capital expenditure (85% of the investment). Repowering capital

expenditure, as it is incurred, will be excluded from the calculation of operating free cash flow under

Meridian’s Dividend Policy. It will, however, be added back into operating free cash flow calculations

proportionately over the expected useful life of the repowered station, currently estimated at 50 years.

Meridian’s revised total capital expenditure guidance for the 2027 financial year is unchanged at $370

million to $410 million. Stay in business capital expenditure is

expected to be between $110 million

and $120 million, growth capital expenditure expected to be between $220 million and $250 million

and repowering capital expenditure of $40 million.

Waitaki Power Station currently generates enough electricity for about 51,000 average homes. It was

constructed with manual labour as a ‘make-work’ project during the 1930 s Depression. The station

started generating electricity in 1935, with two 15MW generators able to meet almost half of the South

Island’s electric ity need s at the time . Three more generators were installed between 1940 and 1949,

bringing generation capacity up to 75MW. The remaining two units were constructed between 1952

and 1954, with the powerhouse extended to accommodate them.


“Waitaki Power Station is an important par t of our country’s social and energy history. This project will

breathe new life into this iconic asset, powering on the legacy of those who built it for decades to

come. As well as increasing generation output, this upgrade will improve seismic resilience,

operational reliability and long-term station performance,” sa ys Meridian Chief Executive Mike Roan.


“Hydro generation has an even more vital role to pla y in our energ y system as New Zealand

transitions away from thermal fuels and increases intermittent wind and solar generation. More

system firming is essential and, a s part of the Waitaki Power Scheme, the station benefits from the

reliabil ity of New Zealand’s biggest battery, Lake Pūkaki.”


The hydro station will continue to operate during project wor ks with unit outages carefully planned to

minimise impact on generation.

Meridian has appointed two main contractors. International hydro generation expert Voith Hydro will

supply the turbines and generators, with New Zealand-owned Gentec Solutions covering the


m e r i d i a n e n e r g y . c o . n z

PG 2


headgates and associated works. The project complements a broader programme of work to improve

availability and flexible generation output of Meridian’s generation assets, including others on the

Waitaki Power Scheme. Meridian has increased the operating capacity of its existing hydro assets by

75MW in the last two years and it expects more in the coming years. These incremental

improvements are important additions to an electricity system that is integrating increasing volumes of

intermittent renewable generation.


ENDS



Approved for release by:

Jason Woolley

General Counsel and Company Secretary

Meridian Energy Limited

For investor relations queries, please contact:

Owen Hackston

Investor Relations Manager

021 246 4772

For media queries, please contact:

Lachlan Forsyth

Media & Content Manager

021 243 5342

7 cm
Waitaki Upgrade Project

Investment Decision

30 SEPTEMBER 2026

30 SEPTEMBER 2026WAITAKI UPGRADE PROJECT
PAGE 2

Construction of the Waitaki hydro power station originally began in the 1930’s.

Today’s announcement
Meridian has committed to upgrading the 92-year-old

Waitaki hydro power station.

The investment will deliver a full mechanical and electrical

upgrade of all seven generating units.

$440M to $510M (nominal) investment over a 10-year

period, delivering a 15%-20% IRR.

The investment will be treated as a combination of growth

capital expenditure (15% of the investment) and a new

classification, repowering capital expenditure (85% of the

investment).

Repowering capital expenditure, as it is incurred, will be

excluded from the calculation of operating free cash flow

under Meridian’s Dividend Policy. It will, however, be added

back into operating free cash flow calculations

proportionately over the expected useful life of the

repowered station, currently estimated at 50 years.

30 SEPTEMBER 2026WAITAKI UPGRADE PROJECT

PAGE 3

Waitaki hydro power station began generating electricity in 1935, with two 15-megawatt

generators operating –enough to meet almost half of the South Island’s electricity needs at

that time.

Project overview
The investment will deliver a full mechanical and electrical

upgrade of all seven generating units, the connection assets,

and balance of plant.

The project represents Meridian’s first full mechanical and

electrical refurbishment of a hydro power station.

The upgrade will substantially extend the operational life of

the station, improve operational flexibility and resilience, and

increase available station capacity by 15MW.

The upgrade provides higher financial returns than further

deferral or decommissioning alternatives.

andselected as key partners.

30 SEPTEMBER 2026WAITAKI UPGRADE PROJECT

PAGE 4

Waitaki hydro power station currentlygeneratesenough electricity for about 51,000 average

New Zealand homes.

0
20

40

60

80

100

2027202820292030203120322033203420352036

$M

Financial Year ended 30 June

Waitaki Upgrade capital expenditure (indicative timing)

Project specifications

$440M-$510M(nominal) capital investment over 10years.

Capex will be treated as growthcapex, not included in stay in

business capex or operating free cashflow under Meridian’s Dividend

Policy.

The investment will be treated as a combination of growth capital

expenditure (15% of the investment) and a new classification,

repoweringcapital expenditure (85% of the investment).

Repowering capital expenditure, as it is incurred, will be excluded

from the calculation of operating free cash flow under Meridian’s

Dividend Policy. It will, however, be added backinto operating free

cash flow calculations proportionately over the expected useful life of

the repowered station, currently estimated at 50 years.

15MWincrease in available station capacity.

15%-20%IRR.

10,000tCO₂eof emissions for the maincontract works.

Sequential unit upgrades to minimise station outages.

30 SEPTEMBER 2026WAITAKI UPGRADE PROJECT

PAGE 5

Source: Meridian

Disclaimer
30 SEPTEMBER 2026WAITAKI UPGRADE PROJECT

PAGE 6

The information in this presentation was prepared by Meridian Energy with due care and attention. However, the information issupplied in summary

form and is therefore not necessarily complete, and no representation is made as to the accuracy, completeness or reliabilityofthe information. In

addition, neither the company nor any of its directors, employees, shareholders nor any other person shall have liability whatsoever to any person for

any loss (including, without limitation, arising from any fault or negligence) arising from this presentation or any informationsupplied in connection

with it.

This presentation may contain forward-looking statements and projections. These reflect Meridian’s current expectations, based on what it thinks are

reasonable assumptions. Meridian gives no warranty or representation as to its future financial performance or any future matter. Except as required

by law or NZX or ASX listing rules, Meridian is not obliged to update this presentation after its release, even if things changematerially.

This presentation does not constitute financial advice. Further, this presentation is not and should not be construed as an offer to sell or a solicitation

of an offer to buy Meridian Energy securities and may not be relied upon in connection with any purchase of Meridian Energy securities.

The information contained in this presentation should be considered in conjunction with the company’s financial statements, which are included in

Meridian’s integrated report for the year ended 30 June 2026, available at:

www.meridianenergy.co.nz/about-us/investors

All currency amounts are in New Zealand dollars unless stated otherwise.

Data sourced from publicly available filings. Our datasets may not be complete. Automated analysis can produce errors. If you believe any data on this page is incorrect, please contact us at hello@nzxplorer.co.nz. For informational purposes only. Not investment advice.

Other issuers discussed similar conditions around this time

Matched by meaning across NZX announcement text, not keywords — based on our semantic index of announcement bodies.