Santana Minerals Ltd logo

Investor Presentation - Diggers and Dealers

Investor Presentation3 August 2025SMIMaterials

Diggers and Dealers
August 2025

Bendigo-Ophir Gold Project

Developing New Zealand's newest and richest gold mine

Disclaimer
2

Disclaimer

All information contained in this presentation is of a general nature. Potential investors are cautioned against using the content of this

presentation, in isolation, for making investment decisions and should also refer to Santana Minerals Limited (‘Santana’) Annual Reports and

ASX/NZX:SMI releases. For further information about Santana visit our website at www.santanaminerals.com.

Best efforts have been made to ensure the accuracy of information contained (at the time of preparation). Where forward targets and/or

assumptions have been included – all such instances are indicative only and subject to alteration and/or cancellation as and when the

management of Santana determines.

Research and advice of a qualified financial advisor or accountant are strongly recommended to anyone considering investing in listed

company securities, including those of Santana.

The Prefeasibility Study, including the production target and the forecast financial information derived from the production target, referred to

in this Presentation (PFS) was released to the ASX on 1 July 2025. This Presentation includes summary excerpts from the PFS and does not

purport to be all-inclusive or complete.

Forward-Looking Statements

This Presentation contains various forward looking statements. Forward-looking statements in this presentation include, but are not limited

to, statements regarding the production target, financial information based on that production target and statements statements with

respect to Santana’s future plans, strategy, activities, events or developments the Company believes, expects or anticipates will or may occur.

By their very nature, forward-looking statements require Santana to make assumptions that may not materialize or that may not be accurate.

The Company has concluded that it has a reasonable basis for providing these forward-looking statements, including the production target

and the forecast financial information included in this Presentation. The detailed reasons for these conclusions are outlined throughout the

ASX releases dated 1 July 2025. However, no assurance can be given that these expectations will prove to have been correct, as actual results

and future events could differ materially from those anticipated in the forward-looking statements. Accordingly, viewers are cautioned not to

place undue reliance on forward-looking statements. Santana does not undertake to update publicly or to revise any of the included forward-

looking statements, except as may be required under applicable securities laws.

To achieve the range of outcomes anticipated in the PFS, the PFS estimates that financing in the order of A$277 million will be required.

Santana believes that there are reasonable grounds for the assumptions it has made in satisfying itself that the requisite funding for the

development of the Project will be available when required. However, Shareholders and prospective investors should be aware that there is

no guarantee Santana will be able to secure this funding as required, and it is possible that the terms available may be dilutive or otherwise

adversely impact the value of Santana’s current shares. Additionally, Santana may explore alternative value-creating strategies, such as

divesting some or all potential revenue streams from precious metals or a full or partial sale of its interest in the Bendigo-Ophir project.

Cautionary Statement – Inferred Resources Included in Production Target

Of the Mineral Resources planned for extraction under the PFS production model approximately 93% is within the Indicated Resources category, with

the balance (7%) being classified within the Inferred Resources category. There is a low level of geological confidence associated with Inferred Mineral

Resources and there is no certainty that further exploration work will result in the determination of Indicated Mineral Resources or that the production

target itself will be realised.

Competent Persons Statement

The production target and the forecast financial information derived from the production target set out in this presentation were first contained in a

public announcement released to the ASX on 1 July 2025. The Company confirms that all material assumptions underpinning the production target and

the forecast financial information derived from it continue to apply and have not materially changed.

The information in this report that relates to Mineral Resources is based on information contained in the following public announcements:

4 March 2025 – ASX Announcement titled “RAS Mineral Resource Estimate Review”

15 November 2024– ASX Announcement titled “Bendigo-Ophir Pre-Feasibility Study”

28 September 2021 – ASX Announcement titled “Bendigo-Ophir Gold Resources Increased 155% to 643k Oz”

The information in this report that relates to Ore Reserves is based on information contained in the public announcement made to the ASX on 1 July

2025.

A copy of these announcements are available to view on the Santana Minerals Limited website www.santanaminerals.com or on the ASX platform

www.asx.com.au.

The reports were issued in accordance with the 2012 Edition of the JORC Australasian Code for Reporting of Exploration Results, Mineral Resources and

Ore Reserves. The Company confirms that it is not aware of any new information or data that materially affects the information included in the original

market announcements referenced above and, in the case of the Mineral Resource estimates, that all material assumptions and technical parameters

underpinning the Mineral Resource estimates in the relevant announcements continue to apply and have not materially changed. The Company

confirms that the form and context in which the Competent Person’s findings are presented have not been materially modified from the original market

announcements.

3
NZ claims #1 Mining investment spot

Fraser Institute – July 2025

Location – Central Otago Goldfields
▪Long history of gold

mining

▪One hour east of

Queenstown

▪90km West of

OceanaGold’s Macraes

gold mine

▪20min drive from

Cromwell with 8,000

people

▪In the semi-arid central

Otago

▪Private farmland, with

agreements to mine in

place

CROMWELL

GOLD RUSH

HISTORIC

DREDGING

RAS Deposit

Blessed with infrastructure
Bendigo-Ophir

Project RAS

Deposit

Cromwell

8,000 people

Queenstown

International Airport

1hr away

State Highway 8

EASY ACCESS

Borefield

FRESH WATER

5km

66kV Substation

8km from the project

5

Clyde Dam Hydro Power

LOW COST GREEN ENERGY

No FIFO

No airstrips

Clean water

Green hydro power

Low-cost power

Skilled workforce

•A blind discovery
•85,000m+ of

Diamond Drilling

•1.7 km down-

plunge and open

•450m wide

•High-grade core

(150m-200m wide)

(30 - 40m thick)

•Bulk barren waste

pre-strip


The Rise & Shine (RAS)

5

Battery Hill

Rise & Shine Valley

Shepherds Creek

6

Thomson Gorge

Fault/Unconformity

TZ4 Schist

TZ3 Schist

View – Looking South East

ARDGOUR STATION

BENDIGO STATION

Project discoveries
Come In Time

59koz @ 1.5 g/t Au

Rise and Shine (RAS)

2.08Moz @ 2.4 g/t Au

1.21Moz Probable Ore Reserve

Srex

145koz @ 0.9 g/t Au

30koz @ 0.7 g/t Au Ore Reserve

Srex-East

52koz @ 1.1 g/t Au

Combined Total

2.34Moz @ 2.1 g/t Au*

CIT

RSSZ

RAS

SRX

SRE

ASX release 4 March 2025 “RAS Mineral Resource Estimate Review”

▪Blind discovery in 2021
▪450m wide mineralised zone

▪High-grade core up to 150m

wide and 45m thick

▪Traced 1.7km down plunge

and open to North-East

8

Most significant NZ gold discovery in 40 years

Thick, high-grade, continuous ore system
42m @ 8.8g/t

Cross section A – up to 45m thick, 150m wide

10
▪1.7km long

▪Northern Honeypot

results extend HG1

▪Recent drilling at depth

shows system getting

thicker again

▪Underground mining

Reserve conversion

potential

31.9m @ 5.3g/t

“Honeypot” thickening

June ‘25 Updated PFS - Outcomes

Open pit mining for 13+ years
1.02Moz

12.6Mt at 2.5g/t

RAS/SRX gold inventory

Mining physicals

13.8yrs mining

11Mt @ 2.75g/t from RAS

1.4Mt @ 0.68g/t from SRX

93% ore feed is Probable Reserve

Mining method

Seven stages of cutbacks

200t class excavators

90t class rear dump trucks

RAS

211Mt total rock

17.5Mt pre-strip

11.2Mt ore

14.6:1 operating strip ratio

Mined gold

993koz Au from RAS

30koz from SRX

>1Moz Au total

Overall grade 2.53g/t

953koz recovered

12

ASX release 1 July 2025 “Updated PFS – Bendigo Ophir Gold Project”

Underground mining at RAS – an initial 7 years
316koz

3.7Mt at 2.7g/t

RAS UG inventory

Mining physicals

7yrs mining

3.7Mt ore

Total development 17km

87% Indicated ore feed

Mining method

Long hole stoping w/paste fill

5.5mW x 5.5mW twin declines

Cable bolts and shotcrete

17km development

2.6Mt paste fill

171km of cables

10k m

3

shotcrete

Mined gold

316koz Au

Grade 2.66g/t

295koz recovered

13

ASX release 1 July 2025 “Updated PFS – Bendigo Ophir Gold Project”

Step out

drilling now

underway

Gold production profile
Strong financialsUnitsTotal A$

Revenue$ billion6.2

EBITDA$ billion4.0

Free cash after tax$ billion2.5

Taxes$ million983

After tax NPV$ billion1.5

After tax IRR%65

After tax Paybackyrs.<1.7

Cash flows from pre-production to conceptual mine closure

-

20

40

60

80

100

120

140

Year 1Year 2Year 3Year 4Year 5Year 6Year 7Year 8Year 9Year 10Year 11Year 12Year 13Year 14

Production (kOz)

Open PitUnderground

(43)

(277)

(182)

91

358

597

855

1,070

1,315

1,508

1,762

2,006

2,186

2,431

2,532

2,534

(3,000)

(2,000)

(1,000)

-

1,000

2,000

3,000

(300)

(200)

(100)

-

100

200

300

Year -2Year -1Year 1Year 2Year 3Year 4Year 5Year 6Year 7Year 8Year 9Year 10Year 11Year 12Year 13Year 14

Cumulative net cash flow

($'000)

Cash Flow ($'000)

Project Free Cash Flow (inc tax)Cumulative FCF (RHS)

Gold production profile

option to increase ounces with mill upgrade to 1.8Mtpa

14

ASX release 1 July 2025 “Updated PFS – Bendigo Ophir Gold Project”

Bendigo-Ophir Gold Project PFS outcomes
Production profile at 1.2Mtpa

13.8 years

initial mine life

16.4Mt @ 2.54g/t

ore mined

1.25Moz of Gold

sold

~500koz Inferred resources

remaining at RAS

120koz pa

peak production

Capital & Operating

A$277M

total pre-production

A$1,741/oz

cash operating cost

A$1,842/oz

all-is-sustaining

A$2,126/oz

total cost per ounce

Financials at Current Gold Price A$4,950

<1.7yrs

simple payback (from

production)

A$6.2 billion

revenue

A$4.0 billion

EBITDA

A$2.5 billion

after tax free cash

A$1.5 billion

NPV

6.5

after tax

65%

IRR after tax

BOGP PFS Outcomes

•Robust economics

•Exceptional margins

•Low hurdles

•Rapid payback

•Growth not yet included

•~500koz Inferred

resources still to be

converted at RAS

•~190koz Inferred at

SRX and CIT

15

ASX release 1 July 2025 “Updated PFS – Bendigo Ophir Gold Project”

Proposed mine infrastructure and layout
Project is located on private free-hold farm

land with agreements in place to mine.

Allows a smooth pathway to permitting.

Open pit mines

Project infrastructure includes

Underground

mine

1.2Mtpa

process plant,

can scale to

1.8Mtpa

Workshops

and stores

Non-process

infrastructure

Tailings

storage facility

(TSF)

Engineered

land fill (ELF)

Water pipeline

Power line to

national grid

Maximum footprint

shown for illustration

purposes only

16

Conventional CIL processing plant
Six phases of metallurgical testing

completed

Very high recoveries at RAS of 93%


THE PFS DESIGN USES SIMPLE CIL TECHNOLOGY TO GENERATE VERY HIGH RECOVERIES

Three stage crush

Ball millingGravity circuit

CIL

Electrowinning

Gold furnace

1

2

3

4

5

6

17

Resistant against price fluctuations
18

Project NPV

6.5

Sensitivities (‘000) Post Tax – Gold Prices

Strong Base-Case

@

A$3,500/oz

NPV

6.5

A$780M

IRR 38%

Payback 2.6Yrs

(Unleveraged, Post Tax)

50% of Spot

Gold price

-10%/ozBase-CaseSpot Price+10%/oz

A$2,475/ozA$3,150/ozA$3,500/ozA$4,950/ozA$5,445/oz

NPV

6.5%

A$255M$601M$780M$1.52b$1.77b

IRR18%32%38%65%73%

Payback4.9Yrs3.0Yrs2.6Yrs1.7Yrs1.6Yrs

Gold price could halve, and the project is

still very profitable

ASX release 1 July 2025 “Updated PFS – Bendigo Ophir Gold Project”

PROJECT: Bendigo-Ophir Gold Project
Project start date:

Scrolling increment:

Wk 1Wk 2Wk 3Wk 4Wk 1Wk 2Wk 3Wk 4Wk 1Wk 2Wk 3Wk 4Wk 1Wk 2Wk 3Wk 4Wk 1Wk 2Wk 3Wk 4Wk 1Wk 2Wk 3Wk 4Wk 1Wk 2Wk 3Wk 4Wk 1Wk 2Wk 3Wk 4Wk 1Wk 2Wk 3Wk 4Wk 1Wk 2Wk 3Wk 4Wk 1Wk 2Wk 3Wk 4Wk 1Wk 2Wk 3Wk 4Wk 1Wk 2Wk 3Wk 4Wk 1Wk 2Wk 3Wk 4Wk 1Wk 2Wk 3Wk 4Wk 1Wk 2Wk 3Wk 4Wk 1Wk 2Wk 3Wk 4Wk 1Wk 2Wk 3Wk 4Wk 1Wk 2Wk 3Wk 4Wk 1Wk 2Wk 3Wk 4Wk 1Wk 2Wk 3Wk 4Wk 1Wk 2Wk 3Wk 4

Milestone description

Mining Permit NZPAM

Resource Consents

Early Works

Buildings

Mine Entrance Work

Services

Establishment

Pioneering

Haul Road Construction

Process Plant Earthworks

Pads and Dams

Pre-Strip

Large Mining Fleet Starts

Process Plant

Detailed Design

Civil Construction

Commissioning

First Gold

ExpectedPlanned

20272025

Q2SeptQ1Q2Q4Q1Q3Aug

2026

OctNovDec

Permitting and timeline to first gold

PATHWAY TO FIRST GOLD

19

EARLY WORKS

CONSTRUCTION STARTS

Corporate snapshot
Peter Cook

Non-Exec Chair

Geo and mine maker

Damian Spring

CEO & Exec Director

Engineer and NZ local

Kim Bunting

Non-Exec Director

Geo who discovered RAS

Sam Smith

Exec Director, Corporate

Engineer and marketer

Board & Management

Funded to FID

Substantial Ownership

NZ private investors>40%

Institutional investors8%

Board & management8%

Capital Structure

Market

Capitalisation

A$433 million

722 million FPO shares @ A$0.60/share – July 30, 2025

Options

11.7M employees incentives

Cash at Bank, 30 June (net of payables)

A$47.5m

Craig McPherson

CFO & Co-Sec

Finance and compliance

20

Emma Scotney

Non-Exec Director

Lawyer, experienced Director

Avg. Daily Volume (90 days) 1.1millon

0.60

21
Finding

the next

RAS

Christchurch

Dunedin

Queenstown

▪290sqkm of tenure

▪Strong soil

anomalies at DNS

and ORK

▪Stacked tailings

from historic

mining, untested

▪30km of strike

regional exploration

program unfolding

30km

2km of

stacked river

tailings

Investment case summary
▪Nationally significant Fast-track project

▪>$1 billion in taxes and gov’t royalties

▪>1000 job applications so far

▪Biggest NZ gold discovery in 40 years

▪Outstanding PFS economics

▪Construction early 2026

▪Significant discovery upside on highly

fertile tenure

MDD450R – VG interval 1m @ 20.5g/t

ASX release 23 July 2025 – “Rise and Shine – Northern Honeypot Emerges”

ASX release 22 August 2022 – “MDD054 Jewellery Box Re-Assays to 1400 g/t Gold”

MDD054

Data sourced from publicly available filings. Our datasets may not be complete. Automated analysis can produce errors. If you believe any data on this page is incorrect, please contact us at hello@nzxplorer.co.nz. For informational purposes only. Not investment advice.

Other issuers discussed similar conditions around this time

Matched by meaning across NZX announcement text, not keywords — based on our semantic index of announcement bodies.

  • MKR — Manuka Resources Limited: Corporate Presentation
    2025-10-07

    An ASX/NZX-listed Producer, Developer and Explorer with Precious Metals assets in the Cobar Basin and Iron Ore and Critical Minerals assets in New Zealand 7 October 2025 An undervalued Australian precious metals play On track to commence gold and silver production early 2026 1…”